SOW_Package.pdf

PDF 7 MB Posted

Attached to
Remove Asbestos, Buildings 40-3, 119, 136
Solicitation number
W911PT19Q0106
Issued by

About this file

This solicitation seeks proposals for asbestos abatement projects at three buildings on Watervliet Arsenal. Work will be conducted under three contract line item numbers (CLINs). CLIN 0001 covers asbestos abatement of piping in Building 136 under project number 9PW019. CLIN 0002 addresses asbestos abatement of tile flooring in Building 119 under project number 9PW029. CLIN 0003 involves removal of a fume hood, asbestos flooring, and installation of an air conditioning unit in Building 40-3 under project number 9BL002. Proposals are due by October 1, 2019. The soliciting agency is the Department of the Army Materiel Command TACOM Life Cycle Management Command. The set-aside type is small business.

Statement of Work Package, drawings, specifications

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX B: Quality Assurance Surveillance Plan (QASP) STATEMENT OF WORK (SOW)

FOR

Remove Fume Hood and Floor Abatement

AT

Watervliet Arsenal Building 40-3, Rm 3-114A&B

Project #: WO9BL002

Installation Management, Public Works Division Facilities Engineering (TAWV-IMP-F)

PART 1 GENERAL

1.1 SUMMARY OF WORK

1.1.1 Project Description

a. This Statement of Work (SOW) defines the effort required for removing the existing fume hood and replacing asbestos containing floor located beneath the fume hood.

(i) Benet Laboratories is replacing the fume hood in the materials lab due a pipe failure in the wall and require the existing fume to be disposed of.

(ii) Removing the existing fume hood will uncover a portion of asbestos containing floor that will be required to be abated, removed, and replaced.

(iii) An eye wash station located next to the existing fume hood will require removal and drywall that was damaged during pipe repair requires repair.

1.1.2 Location of Work

a. The work is located at the north end of room 3-114A&B in building 40-3, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.1.3 Period of Performance

a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [60] calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.

1.1.4 Hours of Operation

a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are non-work days. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.

1.2 SUBMITTALS

1.2.1 General Submittal Requirements

a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.

b. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.

1.2.2 Contractor Safety Plan

a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.

1.2.3 Lockout / Tagout (LOTO) Acknowledgement

a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.

1.2.4 Asbestos Notification Acknowledgement Record

a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.

1.2.5 Project Schedule

a. The contractor shall create a project schedule and submit for Government review and approval.

b. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.

1.3 GENERAL REQUIREMENTS

1.3.1 Watervliet Arsenal Information for Contractors (WAIC)

a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:

<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>

1.3.2 Utility Outage Requests and Utility Connection Requests

a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.

http://www.wva.army.mil/Documents/Contracting/WAIC.pdf

1.3.3 Safety Requirements

a. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per

OSHA 29 CFR 1910.147.

b. The contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials.

1.4 ON-SITE PERMITS

1.4.1 Hot Work and Confined Space

a. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.

1.5 APPLICABLE DOCUMENTS

1.5.1 Specifications

a. The following specifications accompany this Statement of Work and are a part thereof.

i. 02 82 13 – WVA Asbestos Abatement

ii. 09 29 00 – Gypsum Board

1.5.2 References

a. The following references accompany this Statement of Work and are a part thereof.

i. Watervliet Arsenal Instructions for Contractors (WAIC).

ii. NFPA 70 – National Electric Code (NEC).

1.6 CONTRACTOR EQUIPMENT

1.6.1 Equipment Identification

a. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:

i. Company Name, POC Name (first, last), POC phone number, Project Number.

1.6.2 Waste Dumpster

a. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.

b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.

c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.

d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition C&D) debris.

PART 2 PRODUCTS

2.1 GENERAL

All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.

2.1.1 Hazardous Materials

a. The contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.

2.1.2 Asbestos, Mercury, Lead, PCB

a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.

2.1.3 DoD Green Procurement Program

a. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.

2.1.4 Paint

a. To meet the Affirmative Procurement Program (Federal Government’s Buy Recycled Requirements) all paint used in the project shall adhere to the below listed requirements of the Comprehensive Procurement Guideline for recovered materials. This applies only to interior latex paint, only if available at the time of the project.

i. Reprocessed Latex Paint (White, Off-White, Pastel Colors) shall contain 20% Post consumer content.

ii. Reprocessed Latex Paint (Grey, Brown Earth tones, and Other Dark Colors) shall contain 50-99% Post consumer content.

iii. Consolidated Latex Paint shall contain 100% Post consumer content.

2.2 PRODUCTS

2.2.1 Vinyl composition floor time (VCT) – minimum 1/8” thickness, vinyl, commercial grade, color/pattern to match surrounding tile. Mannington “Essentials” line meets product requirements.

a. Static load limit minimum 125 psi

b. Though-body color/pattern

c. Installation shall include the use of manufacturer specified adhesive (Suggested Mannington V-11).

2.2.2 Floor primer – concrete substrate primer suitable for selected self-leveling underlayment installation.

Acrylic, solvent-free. Proma – “Pro Superprime” meets product requirements, primer shall be Pro Superprime or equivalent.

2.2.3 Floor leveler (underlayment) – Polymer-modified, calcium aluminate cement-based, self-leveling as underlayment. Note – Proma – “Pro Plan” meets minimum product specifications, floor leveler shall be Pro Plan WS or equivalent.

(a) Flexural strength (ASTM C-348) @ 28 days minimum = 1000 psi

(b) Compression strength (ASTM C-109) @ 28 days minimum = 4500 psi

2.2.4 Base cove molding – 6” commercial grade vinyl, color to match surrounding existing base cove molding.

2.2.5 Gypsum Board and Associated Materials – materials detailed in WVA Spec 09 29 00.

PART 3 EXECUTION

3.1 ITEMS OF WORK

3.1.1 Contractor shall field verify all measurements and sizes prior to purchase of material and start of work in order to prevent rework.

3.1.2 Contractor shall take measures to protect any lab equipment located in the area. The contractor shall notify the COR of any equipment required to be relocated to facilitate work in the area. The COR will coordinate with Benet Labs to relocate the equipment.

3.1.3 Items for removal:

a. The contractor shall remove and properly dispose of the following items following all NYS Industrial Code Rule 56 (ICR56) requirements for removal and disposal.

1. Fume Hood – Located in room 3-114, to the right of the double doors leading outside. Prior to removal: testing of black countertop for asbestos is required and will be completed by Watervliet Arsenal. Contractor shall remove this unit from the building and dispose of it properly. Contractor shall isolate all water lines at nearest valve and disconnect the unit. Any hard-wired electrical lines and/or plumbing without nearby isolation valve shall be turned over to Government COR for isolation/lockout-tagout on service order. Exhaust piping shall be disconnected at the unit and remain in place.

2. Eye Wash Station – Located in room 3-114, between the double doors and fume hood.

Contractor shall remove the eye wash station and relocate the unit to a temporary holding area for the duration of project work. Government personnel will direct the contractor via COR to a suitable location for storage. Contractor shall isolate all water lines at nearest valve and disconnect the unit. Any plumbing without nearby isolation valve shall be turned over to Government COR for isolation on service order.

3. The intent of the removal of the items is to expose underlying asbestos tile for abatement and to prepare for the arrival of new equipment.

3.1.4 Abate asbestos containing floor materials:

a. The contractor shall prepare and submit an Asbestos Abatement Work Plan to the COR. The work plan shall be IAW specification 02 82 13 WVA Asbestos Abatement.

b. The contractor shall remove the exposed vinyl floor tiles, plywood subflooring, underlying asbestos tile, mastic/tar, and base cove molding in accordance with the submitted Asbestos Abatement Work Plan.

c. Upon acceptable final clearance for this abatement effort, Contractor shall be permitted to continue to installation phase of this project.

3.1.5 Install new vinyl flooring in former fume hood location and where removed for access for pipe work:

a. The concrete shall be sufficiently clean and dry prior to the installation of any leveling compound, adhesive, etc – defined by having no visible debris or dust/dust covering. Contractor shall use means as necessary to expedite drying time, such as powered dehumidification and box fans for air circulation. Contractor shall ensure dryness meets adhesive/leveling compound manufacturer specifications at the time of product application.

b. Contractor shall first mechanically level the concrete floor to include grinding or hammering any remaining high surfaces metal and/or protrusions.

c. Contractor shall prime the floor surface prior to leveling compound. Prior to priming, the concrete shall be swept clean. Contractor shall use a primer/leveler system which requires no mechanical prep (no bead blasting or chemical washing required). Contractor shall NOT bead blast.

d. Contractor shall apply leveling compound across the concrete subfloor to fully cover and encapsulate the surface imperfections. Compound shall be self-leveling, with maximum height of pour not to exceed 1” from base to top surface. The contractor shall protect and prepare all wall bases and surrounding flooring from over-pour, and shall follow all manufacturer guidance for installation.

(i) The leveling compound shall be smooth and level in all directions, and shall be applied such that transitions to adjacent flooring heights is minimized once final VCT flooring is installed. The intent is for a smooth transition between old and new floor surfaces without lippage or a need for a reducer strip (ex. Seamless).

(ii) Contracting Officer Representative will inspect project work site after self-leveling compound has dried, but PRIOR to installation of any VCT for acceptance of workmanship.

(iii) Contractor shall submit product specifications for primer and self-leveling compound to project Contracting Officer for evaluation and approval prior to purchase and/or installation.

e. Contractor shall install new 12” x 12” vinyl composition tiles (VCT) throughout the LP&S areas in which flooring was removed.

(i) Tile shall be installed directly to the prepared concrete slab. Tiles shall be installed wall to wall, to existing thresholds with tight fitting cuts made for any protrusions, work of other trades, etc. Tiles shall be fitted tightly against one another for a neat professional appearance.

(ii) Contractor shall use tile manufacturer recommended adhesive which identifies direct gluing to concrete as an approved application, along with any primers associated with adhesive.

(iii) Contractor shall submit leveling compound, adhesive, primer, and any other products used in preparation for installation to project Contracting Officer for evaluation and approval prior to purchase/installation.

(iv) Contractor shall submit vinyl floor tile color/material samples to project Contracting Officer for evaluation, color choice, and approval prior to purchase/installation.

3.1.6 Install base cove molding:

a. Contractor shall install new vinyl base cove molding to the wall portion of the perimeter of the affected area.

3.1.7 Drywall repair:

a. Contractor shall repair/replace existing drywall as well as any drywall removed during the period of work.

(i) Contractor shall ensure installation is seamless with existing drywall and matches surrounding color.

3.2 CLOSEOUT REQUIREMENTS

3.2.1 Construction and Demolition Debris

a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.

3.2.2 Cleanup of Work Site

a. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.

b. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.

c. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.

3.2.3 Restoration of Work Site

a. The contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.

PART 4 APPENDICES

a. Consolidated List of Submittals

b. Quality Assurance Surveillance Plan (QASP)

APPENDIX A: Consolidated List of Submittals

Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)

1 Safety Data Sheets for Hazardous Materials

(SDS)

NLT 7 Calendar Days After Award

Safety Office

2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award

Environmental Office

3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record

NLT 7 Calendar Days After Award

Safety Office

4 Project Schedule NLT 7 Calendar Days After Award

COR

5 Contractor Safety Plan NLT 7 Calendar Days After Award

COR

6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials

Before Closeout Environmental Office

7 MSDS for VCT adhesive, underlayment, primer, solvents, mastics, paint, etc

NLT 7 Days After Award

COR

8 VCT color swatches / cutsheet(s) NLT 7 Days After Award

COR

9 Underlayment and primer specifications NLT 7 Days After Award

COR

10 Cove molding color swatches / cutsheet(s) NLT 7 Days After Award

COR

11 Asbestos Disposal Documentation Before Closeout Environmental Office

PURPOSE

This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.

SURVEILLANCE PROCEDURES

Timeliness: Progress is maintained to assure compliance with completion time.

Quality: Conformance with statement of work and industry standards.

Tasks: Performed according to statement of work requirements.

Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.

Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.

PERFORMANCE AREAS

Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.

Schedule Control: Evaluate the contractor’s adherence to completion schedule.

Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.

EVALUATION CRITERIA

(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.

(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.

(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.

DOCUMENTATION

Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.

RATING

Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, using the above 3 evaluation criteria.

STATEMENT OF WORK (SOW)

Benet Laboratories Materials Lab Projects

Bldg. 40-3

1.1.1 Project Description

a. This Statement of Work (SOW) defines the effort required for the

1.1.2 Location of Work

a. The work is located within building 40-3, as specified within the respective sub-SOWs.

1.1.3 Period of Performance

a. The Contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and

(iii) complete the entire work ready for use no later than the specific period of performance indicated in each of the sub-SOWs. The time stated for completion shall include final cleanup of the premises.

1.1.4 Hours of Operation

a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are

1.2.1 General Submittal Requirements

a. The Contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require Government approval unless otherwise explicitly stated.

b. The Contractor shall reference the sub-SOWs for the requisite submittals per each effort.

a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The Contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:

<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>

1.3.2 Utility Outage Requests and Utility Connection Requests

a. The Contractor shall schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, the Contractor shall coordinate schedule with COR. The Contractor shall schedule utility outages and connections to minimize disruptions to the Government. The Government shall not be liable for additional payments for utility outages and connections required to be performed outside the regular work hours.

b. The Contractor shall notify the Contracting Specialist a minimum of two (2) business days before the Contractor starts work. The Contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.

1.3.3 Safety Requirements

a. The Contractor shall provide the proper control of hazardous energy (lockout/tagout) per

OSHA 29 CFR 1910.147.

b. The Contractor shall inspect the project work site prior to starting work, and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos- containing materials.

1.4.1 Hot Work and Confined Space

a. The Contractor shall obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.

1.5.1 References

a. The following references accompany this Statement of Work and are a part thereof.

iii. 9BL002-1_SOW_Fume Hood

iv. 9BL002-2_SOW_AC Replacement

a. The Contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:

i. Company Name, POC Name (first, last), POC phone number, and Project Number.

1.6.2 Waste Dumpster

a. The Contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.

b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.

c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.

d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight

The Contractor shall complete all work in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.

2.1.1 Hazardous Materials

a. The Contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.

2.1.2 Asbestos, Mercury, Lead, and PCB

a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.

2.1.3 DoD Green Procurement Program

a. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, biobased products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.

2.1.4 Paint

http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf

a. To meet the Affirmative Procurement Program (Federal Government’s Buy Recycled Requirements) all paint used in the project shall adhere to the below listed requirements of the Comprehensive Procurement Guideline for recovered materials. This applies only to interior latex paint, only if available at the time of the project.

i. Reprocessed Latex Paint (White, Off-White, Pastel Colors) shall contain 20%

Post consumer content.

ii. Reprocessed Latex Paint (Grey, Brown Earth tones, and Other Dark Colors) shall contain 50-99% Post consumer content.

3.1 ITEMS OF WORK

3.1.1 Execute SOW 9BL002-1_SOW_Fume Hood.

a. The Contractor shall execute the full statement of work as described in the referenced SOW

9BL002-1.

3.1.2 Execute SOW 9BL002-2_SOW_AC Replacement.

a. The Contractor shall execute the full statement of work as described in the referenced SOW

9BL002-2.

3.2 CLOSEOUT REQUIREMENTS

3.2.1 Construction and Demolition Debris

a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.

3.2.2 Cleanup of Work Site

a. The Contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.

b. The Contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.

c. The Contractor shall remove its equipment from Watervliet Arsenal premises within five

(5) working days after completion of project work.

3.2.3 Restoration of Work Site

a. The Contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW and referenced SOWs in Sections

3.1.1 and 3.1.2 at no additional cost to the Government. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.

b. Grass, trees, and other vegetation affected by project work shall be restored to same or better condition as existed prior to the start of project work. The Contractor shall prepare the affected areas to eliminate uneven areas and low spots. Remove foreign materials, weeds, and damaged soil. The Contractor shall scratch the area to a depth of three (3) inches where topsoil is to be placed. Spread topsoil to a uniform, compacted depth of less than five (5) inches over areas to be reseeded. Rake until smooth. The Contractor shall seed, fertilize, and water the area to establish grass for the entire duration necessary for new grass to become self-sustaining.

3.2.4 Warranty

The contractor shall provide warranties as detailed in the sub-SOWs

Installation of AC System Bldg. 40-3

Bldg. 40-3

A. Project Description

a. This Statement of Work (SOW) defines the effort required for the installation of a new 5 ton split system AC unit in the Materials Lab Bldg. 40-3. Upon successful completion, the new 5 ton AC unit and associated hardware shall be installed, fully and properly connected to the existing electrical and the Metasys building monitoring system. Overall installation of the unit includes; new split system AC, piping, insulation, electrical, controls and all hardware associated with the unit.

B. Location of Work

a. The work is located at Building 40-3, Benet Materials Lab. The exact location will be shown by the Contracting Officer.

C. Period of Performance

a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [60] calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.

D. Hours of Operation

a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are

A. General Submittal Requirements

a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.

b. All contractors are responsible for complying with DOD, Army, Federal, and State Health and Safety requirements. Use all means and precautions necessary to insure the safety of the occupants and protection to the existing buildings and structures.

c. The contractor is required to review the project site, and obtain and/or verify all measurements and project data/information required to perform this project work. In addition, the contractor is required to review all contract documents, and provide written notice to Contracting Officer of any discrepancies that are found.

d. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.

B. Contractor Safety Plan

a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.

C. Lockout / Tagout (LOTO) Acknowledgement

a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.

D. Asbestos Notification Acknowledgement Record

a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.

E. Project Schedule

a. The contractor shall create a project schedule and submit for Government review and approval.

b. The project schedule shall detail the phases of work and the overall timeline for the execution of the

A. Watervliet Arsenal Information for Contractors (WAIC)

a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:

<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>

b. The contractor shall supply all tools, materials, supplies, equipment, labor, temporary utilities and supervision necessary for a complete and appropriate execution of the contract documents and requirements of this SOW.

B. Utility Outage Requests and Utility Connection Requests

a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.

C. Safety Requirements

a. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per

OSHA 29 CFR 1910.147.

b. The contractor shall inspect the project work site prior to starting work, and shall request a copy of

A. Excavation (Dig Permit)

a. The clearance of buried utilities will be performed by the Government in advance of the Contractor performing subsurface work, unless otherwise explicitly stated.

b. The Contractor shall obtain a copy of the completed Utility Clearance Permit (WVA Form 420-2-E) from the COR prior to performing subsurface work. Verify existing utility locations indicated on contract drawings, within area of work.

B. Hot Work and Confined Space

A. Specifications

a. The following specifications accompany this Statement of Work and are a part thereof.

i American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)

ii. National Fire Protection Association (NFPA)

iii. National Electrical Code, NFPA 70, 2017 (NEC)

iv. 23 05 15 - Common piping for HVAC (Steam, Condensate, Copper)

v. 26.05.00 Common Electrical Work 120 V

B. References

a. The following references accompany this Statement of Work and are a part thereof.

C. Drawings

a. Building 40-3 Floor plan. See attachment.

A. Equipment Identification

a. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:

i. Company Name, POC Name (first, last), POC phone number, Project Number.

B. Waste Dumpster

a. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.

b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with, and approved by the COR before any dumpsters are mobilized.

c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.

d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight

All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.

A. Hazardous Materials

a. The contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.

B. Asbestos, Mercury, Lead, PCB

a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.

C. DoD Green Procurement Program

a. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, bio-based products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.

D. Paint

a. To meet the Affirmative Procurement Program (Federal Government’s Buy Recycled Requirements) all paint used in the project shall adhere to the below listed requirements of the Comprehensive Procurement Guideline for recovered materials. This applies only to interior latex paint, only if available at the time of the project.

i. Reprocessed Latex Paint (White, Off-White, and Pastel Colors) shall contain 20% Post consumer content.

ii. Reprocessed Latex Paint (Grey, Brown Earth tones, and Other Dark Colors) shall

a. 5 ton, York YFK60B21S condenser, R-410A, two stage, 208/230 -1- 60, microchannel condenser coil, Minimum 16 SEER, or equivalent

b. 5 ton, York AE60DX21 Air Handler, horizontal flow, 208/230-1-60, or equivalent

c. Johnson Controls FEC 2611, or equivalent.

d. Johnson Controls lockable metal enclosure, or equivalent.

e. Return and Outside Air Dampers

f. Belimo Actuators for Dampers, 2-10 VDC signal, modulating, spring return or equivalent.

g. Johnson Controls Network Sensor, NS-BTB7003-0 or equivalent.

3.1 INSTALLATION OF NEW AC SYSTEM

a. Contractor shall be responsible to LOTO all sources of power before beginning the removal of the old AC system.

b. Contractor shall recover refrigerant from old existing AC unit and remove condensing unit along with all associated hardware and components. Once the old AC system and components have been removed it becomes property of the contractor and shall be disposed of off-post.

c. Contractor shall remove old steel bracket for old condenser as well as disconnect from existing AC unit and install new 2” by 2” welded steel bracket. New bracket shall be painted with corrosion resistant paint and be brown in color. Bracket shall be mounted so new condenser is at the same approximate height as the existing condenser.

d. Contractor shall remove old air handling unit and associated hardware and components and replace with new horizontal flow indoor unit. Once old AHU has been removed it is property of the contractor and is to be disposed of off-post. New AHU shall have ductwork installed and transitioned into the existing supply ductwork and into the return/mixing box. New ductwork connections shall be sealed using low VOC sealant/mastic.

e. Contractor shall install new dampers for outside air and return air in the mixing box/economizer as well as new actuators.

f. Contractor shall set new condensing unit on wall bracket outside and anchor in place. Contractor shall install new disconnect and liquid tight flexible conduit for the condenser. New fuses and breakers shall be replaced as per manufacturer’s specifications for the indoor and outdoor units.

g. Contractor shall install AC System following all manufacturer’s recommendations and follow all NEC codes. Contractor shall label disconnects for the AHU and condenser to identify source of power as well as label the electrical panel to identify equipment.

h. Contractor shall install new line sets from the condenser to the evaporator. All refrigerant lines are to be brazed, properly insulated, secured and pressure tested with nitrogen and tested for leaks.

Penetration into building shall be sleeved and sealed.

i. Contractor shall install a properly pitched and trapped condensate drain from the new air handler that will be reconnected to the existing drain line.

j. Contractor shall remove existing thermostat and replace with a network sensor and install in location to be approved by COR.

k. Contractor shall be responsible to start up and commission new unit and verify proper operation

3.2 INSTALLATION OF NEW CONTROLS FOR AC SYSTEM AND ECONOMIZER

a. Contractor shall install new Johnson Controls metal lockable enclosure. New enclosure shall be of sufficient size to accommodate FEC controller and an additional controller for future use. Location of FEC/Enclosure is to be approved by COR.

b. Contractor shall install new properly sized transformer and new FEC controller. Contractor shall supply all necessary electrical wiring, control wiring, new sensors and relays for a complete control installation.

c. Contractor shall label new Metasys panel and identify source of power as well as label the electrical panel to identify Metasys.

d. New FEC controller shall be programmed and shall have all necessary inputs, outputs and programming necessary to control and monitor the economizer and AC system. Commands and status shall include but not limited to, compressor command and status, supply fan command and status, supply air temperature, return air temperature, space temperature, minimum position, damper command and outside air temperature. All points shall be made visible on the operator work station.

e. Contractor shall start-up, commission and verify proper operation of new programming for the new AC system and economizer.

3.3 CLOSEOUT REQUIREMENTS

A. Construction and Demolition Debris

a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.

B. Cleanup of Work Site

a. The contactor shall clean all work areas daily and remove all tools, equipment, debris, materials, and all waste from the premises.

b. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.

c. The contractor shall remove their equipment from Watervliet Arsenal premises within one (1) working day after completion of project work.

C. Restoration of Work Site

a. The contractor shall repair any items, building surfaces, walls, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.

b. Grass, trees, and other vegetation affected by project work shall be restored to same or better condition as existed prior to the start of project work. The Contractor shall prepare the affected areas to eliminate uneven areas and low spots. Remove foreign materials, weeds, and damaged soil. The Contractor shall scratch the area to a depth of three (3) inches where topsoil is to be placed. Spread topsoil to a uniform, compacted depth of less than five (5) inches over areas to be reseeded. Rake until smooth. The Contractor shall seed, fertilize, and water the area to establish grass.

D. Warranty

a. The contractor shall provide warranty on parts as specified by manufacturer. If warranty period is not specified warranty shall be one (1) year on parts and one (1) year on labor after acceptance of completed project.

E. Operations and Maintenance Manuals

a. The contractor shall provide (2) copies of operations and maintenance manuals to the project COR and one electronic copy on disc in pdf format for the newly installed AC System.

PART 4 APPENDICES

a. Consolidated List of Submittals

Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)

1 Safety Data Sheets for Hazardous Materials

(SDS)

NLT 7 Calendar Days After Award

Safety Office

2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award

Environmental Office

3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record

NLT 7 Calendar Days After Award

Safety Office

4 Project Schedule NLT 7 Calendar Days After Award

COR

5 Contractor Safety Plan NLT 7 Calendar Days After Award

COR

6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials

Before Closeout Environmental Office

7 Operation and Maintenance Manuals Before Closeout COR

8 AC System Submittals, indoor and outdoor units NLT 7 Calendar Days After Award

COR

9 Metasys Controller Submittals NLT 7 Calendar Days After Award

COR

10 Damper Submittals NLT 7 Calendar Days After Award

COR

11 Network Sensor Submittals NLT 7 Calendar Days After Award

COR

12 Lockable Enclosure Cabinet NLT 7 Calendar Days After Award

COR

13 Actuator Submittals NLT 7 Calendar Days After Award

APPENDIX B: Quality Assurance Surveillance Plan (QASP)

PURPOSE

This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.

SURVEILLANCE PROCEDURES

Timeliness: Progress is maintained to assure compliance with completion time.

Quality: Conformance with statement of work and industry standards.

Tasks: Performed according to statement of work requirements.

Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.

Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.

PERFORMANCE AREAS

Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.

Schedule Control: Evaluate the contractor’s adherence to completion schedule.

Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.

EVALUATION CRITERIA

(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.

(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.

(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.

DOCUMENTATION

Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.

RATING

Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, using the above 3 evaluation

Asbestos Abatement

Building 136, Ground Level

Project #: 9PW019

1.1.1 Project Description

a. This Statement of Work (SOW) defines the effort required for the abatement of roughly 1000 LF of asbestos containing pipe insulation and installation of new mineral fiber pipe insulation from Building 136.

1.1.2 Location of Work

a. The work is primarily located within the ground level of Building 136 of the Watervliet Arsenal, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.1.3 Period of Performance

a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than 60 calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.

i. Note: The portion of the target insulation is covering steam piping. Steam systems will be activated with steam and condensate running through piping during the months of October through April. The contractor shall plan work accordingly.

1.1.4 Hours of Operation

a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays (the arsenal is closed every-other Friday). Federal holidays are

1.2.1 General Submittal Requirements

a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.

b. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.

1.2.2 Contractor Safety Plan

a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.

1.2.3 Lockout / Tagout (LOTO) Acknowledgement

a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.

1.2.4 Asbestos Notification Acknowledgement Record

a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.

1.2.5 Project Schedule

a. The contractor shall create a project schedule and submit for Government review and approval.

b. The project schedule shall detail the phases of work and the overall timeline for the execution of the

a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:

<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>

1.3.2 Utility Outage Requests and Utility Connection Requests

a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be provided for utility outages and connections required to be performed outside the regular work hours.

b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor…

This is the start of the file's text. The full file is on GovTribe.