WATERVIET ARSENAL
STATEMENT OF WORK
Electronic Gauge Installation Contract May 3, 2017
AAS # 171230009
Purpose
Contractor is to provide labor, material, and equipment for install of new gauging systems for Tanks # 101, 102, and 103. Tank 101 is a 425,000 gallon vertical #2 fuel oil tank. Tanks 102 and 103 are 30,000 and 25,000 gallon horizontal #2 fuel oil tanks, respectively.
The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publically available at:
http://www.wva.army.mil/Documents/Contracting/WAIC.pdf Description
Provide a lump sum cost to cover all Travel, Labor, Equipment and Parts/Materials to complete the following work. Where a name brand product is described, an equivalent product may be substituted.
· Mobilize to site.
· Remove all existing leak detection and gauging units from dike wall.
· Removal existing float sensor from all tanks for high level alarm.
· Provide and Install 41’ Omntec flexible probe in Tank 101.
· Provide and Install 10’6” Omntec rigid probe in Tank 102.
· Pull all existing wires from existing conduit running to the top of Tank 101 and Tank 102 and clear seal off outs.
· Provide and install new Omntec Proteus color touch screen leak detection and gauging stytem in boiler house control room exterior wall.
· Provide and install Omntec RD625-2 remote display with 2-LED displays in NEMA 4 X enclosure for level indication of Tank 101 and 102.
· Provide and install one Omntec remote annunciator on dike wall for high level alarm in Tank 101 and 102.
· Provide and install two new ¾” conduits from Proteus in boiler house control room out to the remote displays and high level alarms.
· Provide and install all required cables and wire for a complete system.
· Connect probes and sensors.
· Start up system and test.
· Demobilize from site.