THOMAS C. HALL
LETTERKENNY CONTRACTING OFFICE
1 OVERCASH AVENUE, CCAM-ALK
717-267-5583
CHAMBERSBURG PA 17201-4150
W25G1Q0091R001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to answ er prospective offeror questions.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 15-Apr-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W911N220Q0037
X 9B. DATED (SEE ITEM 11)
10-Apr-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Apr-2020
CODE
LETTERKENNY ARMY DEPOT
LETTERKENNY CONTRACTING OFFICE - ACC-RSA-LEAD
1 OVERCASH AVENUE, ATTN: CCAM-MLK, BLDG 2S
CHAMBERSBURG PA 17201-4150
W911N2 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W911N2
FACILITY CODECODE
EMAIL:TEL:
W911N220Q0037
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
The following have been added by full text:
QUESTION & ANSWERS
Q1. Is the unit pricing to be per platform regardless of how many square feet of new foam are to be sprayed?
A1. Per asset/application. No price change based on how much foam is needed. CK container is 8’x20’. However it doesn’t get a 100% coverage (fork pockets aren’t coated) plus the thickness of all the beams. Square footage is likely between 140-150 with 160 being the maximum (if the asset actually got 100% coverage, which it never will).
Q2. Is the new foam to be sprayed onto existing damaged foam or does the existing damaged foam need to be removed?
A2. We remove the foam when we replace the flooring. Vendor would need to ensure its all removed and ready for new foam (if there was a piece missed, they should remove it & dispose of it).
Q3. Who is to remove and dispose of the damaged foam?
A3. LEAD removes the foam and disposes of it. Vendor is responsible for all disposal of everything generated/removed on the day of the service.
Q4. The photos seem to indicate a black coating has been sprayed onto the foam. What is the purpose of this coating; fire protection? What are the required fire ratings of the foam and any fire-protective surface? I don’t see any such requirement in the specifications.
A4. That should be the undercoating which is applied by LEAD’s paint. There is no specific fire rating required in accordance with the Program Engineer.
(End of Summary of Changes)