W911KB22B0003 Bid Abstract.pdf

PDF 246 KB Posted

Attached to
Ninilchik Revetment Replacement Federal contract opportunity
Solicitation number
W911KB22C0006
Issued by
Department of the Army Corps of Engineers Engineering District Alaska

About this file

This abstract of bids is for the Ninilchik Revetment Replacement project solicited by the Department of the Army Corps of Engineers Engineering District Alaska. Eight contractors submitted bids by the March 3rd opening date, with Tutka, LLC awarded the contract for $6,972,987.50 on March 30th, 2022. The project involves replacing an existing revetment through demolition, excavation, and construction of various rock sizes from station 10+00 to 21+50. Base line items include mobilization, surveys, demolition, excavation and construction of C, B, and A rocks. Three option items add additional sections for a total estimated quantity of 23,725 cubic yards of excavation and 17,275 cubic yards of rock construction.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES

24-Jan-2022 3-Mar-2022 1 of 3

DATE SIGNED

29-Mar-22

ITEM NO.

EST.

QUANTITY UNIT

UNIT

PRICE

ESTIMATED

AMOUNT

UNIT

PRICE AMOUNT

UNIT

PRICE AMOUNT

0001 Mobilization and Demobilization for First Year Work, complete 1 Job $238,000.00 $238,000.00 $65,900.00 $65,900.00 $575,000.00 $575,000.00

Demolish and Remove Existing Revetment

STA 10+00 to STA 15+00 and STA 21+50
to 22+00, complete

1 Job $200,000.00 $200,000.00 $177,000.00 $177,000.00 $64,000.00 $64,000.00

0003 Excavation and Embankment Preparation STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 12,725 CY $5.40 $68,715.00 $43.45 $552,901.25 $11.30 $143,792.50

0004 deleted $0.00 $0.00 $0.00

0005 Construct C Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 2,650 CY $500.00 $1,325,000.00 $365.55 $968,707.50 $503.00 $1,332,950.00

0006 Construct B Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 4,000 CY $630.00 $2,520,000.00 $441.50 $1,766,000.00 $582.00 $2,328,000.00

0007 Construct A Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 4,150 CY $760.00 $3,154,000.00 $648.00 $2,689,200.00 $695.00 $2,884,250.00

0008 Pre- and Post-Construction Surveys for First Year Work, complete 2 EA $50,000.00 $100,000.00 $30,000.00 $60,000.00 $10,500.00 $21,000.00 Total of Base Items 0001-0008 $7,605,715.00 $6,279,708.75 $7,348,992.50

0009 Demolish and Remove Existing Revetment STA 15+00 to STA 17+00, complete 1 Job $54,000.00 $54,000.00 $200,000.00 $200,000.00 $39,000.00 $39,000.00

0010 Excavation and Embankment Preparation STA 15+00 to STA 17+00, complete 4,200 CY $4.50 $18,900.00 $70.00 $294,000.00 $17.90 $75,180.00

0011 deleted $0.00 $0.00 $0.00 0012 Construct C Rock STA 15+00 to STA 17+00, complete 950 CY $410.00 $389,500.00 $356.00 $338,200.00 $503.00 $477,850.00 0013 Construct B Rock STA 15+00 to STA 17+00, complete 1,400 CY $550.00 $770,000.00 $398.00 $557,200.00 $582.00 $814,800.00 0014 Construct A Rock STA 15+00 to STA 17+00, complete 1,500 CY $620.00 $930,000.00 $583.00 $874,500.00 $695.00 $1,042,500.00

Total of Option 1 Items 0009-0014 $2,162,400.00 $2,263,900.00 $2,449,330.00

0015 Demolish and Remove Existing Revetment STA 17+00 to STA 19+00, complete 1 Job $54,000.00 $54,000.00 $200,850.00 $200,850.00 $38,000.00 $38,000.00

0016 Excavation and Embankment Preparation STA 17+00 to STA 19+00, complete 4,000 CY $5.30 $21,200.00 $70.00 $280,000.00 $18.80 $75,200.00

0017 deleted $0.00 $0.00 $0.00 0018 Construct C Rock STA 17+00 to STA 19+00, complete 950 CY $400.00 $380,000.00 $357.00 $339,150.00 $503.00 $477,850.00 0019 Construct B Rock STA 17+00 to STA 19+00, complete 1,400 CY $520.00 $728,000.00 $398.00 $557,200.00 $582.00 $814,800.00 0020 Construct A Rock STA 17+00 to STA 19+00, complete 1,500 CY $657.00 $985,500.00 $584.00 $876,000.00 $695.00 $1,042,500.00

Total of Option 2 Items 0015-0020 $2,168,700.00 $2,253,200.00 $2,448,350.00 0021 Demolish and Remove Existing Revetment STA 19+00 to STA 21+50, complete 1 Job $68,000.00 $68,000.00 $194,600.00 $194,600.00 $45,000.00 $45,000.00 0022 Excavation and Embankment Preparation STA 19+00 to STA 21+50, complete 5,600 CY $4.50 $25,200.00 $67.50 $378,000.00 $18.75 $105,000.00 0023 deleted $0.00 $0.00 $0.00 0024 Construct C Rock STA 19+00 to STA 21+50, complete 1,175 CY $400.00 $470,000.00 $345.00 $405,375.00 $503.00 $591,025.00 0025 Construct B Rock STA 19+00 to STA 21+50, complete 1,750 CY $520.00 $910,000.00 $384.00 $672,000.00 $582.00 $1,018,500.00 0026 Construct A Rock STA 19+00 to STA 21+50, complete 1,875 CY $650.00 $1,218,750.00 $576.00 $1,080,000.00 $695.00 $1,303,125.00

Total of Option 3 Items 0021-0026 $2,691,950.00 $2,729,975.00 $3,062,650.00

0027 Mobilization and Demobilization For Second Year Option Item Work, complete 1 Job $200,100.00 $200,100.00 $64,800.00 $64,800.00 $470,000.00 $470,000.00

0028 Pre- and Post-Construction Surveys for Second Year Work, complete 2 EA $57,000.00 $114,000.00 $30,000.00 $60,000.00 $11,000.00 $22,000.00

0029 Deconstruct First Year Work From STA 21+50 to 22+00 and Prepare Transition For Second Year Work, complete 1 Job $26,000.00 $26,000.00 $16,600.00 $16,600.00 $53,000.00 $53,000.00

Total of Option 4 Items 0027-0029 $340,100.00 $141,400.00 $545,000.00 Total of Base and Option Items 0001-0029 $14,968,865.00 $13,668,183.75 $15,854,322.50

Yes Yes

B. BID SECURTIY (TYPE AND AMOUNT)

6. NUMBER OF AMENDMENTS ISSUED

B. BID SECURTIY (TYPE AND AMOUNT)

C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

Yes Yes

ABSTRACT OF BIDS - CONSTRUCTION

1. SOLICITATION NUMBER

W911KB22B0003

4. ISSUING OFFICE

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

5. PROJECT TITLE 8. GOVERNMENT ESTIMATE

(Check A, B, C and complete D, E, and F)

No. 01 No. 02

7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)

U.S. Army Engineer District, Alaska PO Box 6898

JBER, AK 99506-6898

Christine A. Dale, Contracting Officer

SIGNATURE

9. OFFERS

Ninilchik Revetment Replacement, Ninilchik, Alaska A. OFFEROR A. OFFEROR

Ahtna Construction and Primary Products Co Intapela Infrastructure, LLC

24-Jan-2022 3-Mar-2022 2 of 3

DATE SIGNED

29-Mar-22

ITEM NO.

EST.

QUANTITY UNIT

UNIT

PRICE

ESTIMATED

AMOUNT

UNIT

PRICE AMOUNT UNIT

PRICE AMOUNT

0001 Mobilization and Demobilization for First Year Work, complete 1 Job $111,000.00 $111,000.00 $2,225,000.00 $2,225,000.00 $1,975,000.00 $1,975,000.00

0002 Demolish and Remove Existing Revetment STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 1 Job $130,000.00 $130,000.00 $200,000.00 $200,000.00 $200,000.00 $200,000.00

0003 Excavation and Embankment Preparation STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 12,725 CY $22.50 $286,312.50 $11.00 $139,975.00 $40.00 $509,000.00

0004 deleted $0.00 $0.00 $0.00

0005 Construct C Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 2,650 CY $222.00 $588,300.00 $170.00 $450,500.00 $320.00 $848,000.00

0006 Construct B Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 4,000 CY $237.00 $948,000.00 $175.00 $700,000.00 $320.00 $1,280,000.00

0007 Construct A Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 4,150 CY $275.00 $1,141,250.00 $190.00 $788,500.00 $320.00 $1,328,000.00

0008 Pre- and Post-Construction Surveys for First Year Work, complete 2 EA $14,000.00 $28,000.00 $50,000.00 $100,000.00 $40,000.00 $80,000.00 Total of Base Items 0001-0008 $3,232,862.50 $4,603,975.00 $6,220,000.00

0009 Demolish and Remove Existing Revetment STA 15+00 to STA 17+00, complete 1 Job $65,000.00 $65,000.00 $75,000.00 $75,000.00 $60,000.00 $60,000.00

0010 Excavation and Embankment Preparation STA 15+00 to STA 17+00, complete 4,200 CY $22.50 $94,500.00 $11.00 $46,200.00 $40.00 $168,000.00

0011 deleted $0.00 $0.00 $0.00 0012 Construct C Rock STA 15+00 to STA 17+00, complete 950 CY $222.00 $210,900.00 $170.00 $161,500.00 $320.00 $304,000.00 0013 Construct B Rock STA 15+00 to STA 17+00, complete 1,400 CY $237.00 $331,800.00 $175.00 $245,000.00 $320.00 $448,000.00 0014 Construct A Rock STA 15+00 to STA 17+00, complete 1,500 CY $275.00 $412,500.00 $190.00 $285,000.00 $320.00 $480,000.00

Total of Option 1 Items 0009-0014 $1,114,700.00 $812,700.00 $1,460,000.00

0015 Demolish and Remove Existing Revetment STA 17+00 to STA 19+00, complete 1 Job $65,000.00 $65,000.00 $75,000.00 $75,000.00 $60,000.00 $60,000.00

0016 Excavation and Embankment Preparation STA 17+00 to STA 19+00, complete 4,000 CY $22.50 $90,000.00 $11.00 $44,000.00 $40.00 $160,000.00

0017 deleted $0.00 $0.00 $0.00 0018 Construct C Rock STA 17+00 to STA 19+00, complete 950 CY $222.00 $210,900.00 $170.00 $161,500.00 $320.00 $304,000.00 0019 Construct B Rock STA 17+00 to STA 19+00, complete 1,400 CY $237.00 $331,800.00 $175.00 $245,000.00 $320.00 $448,000.00 0020 Construct A Rock STA 17+00 to STA 19+00, complete 1,500 CY $275.00 $412,500.00 $190.00 $285,000.00 $320.00 $480,000.00

Total of Option 2 Items 0015-0020 $1,110,200.00 $810,500.00 $1,452,000.00 0021 Demolish and Remove Existing Revetment STA 19+00 to STA 21+50, complete 1 Job $65,000.00 $65,000.00 $75,000.00 $75,000.00 $60,000.00 $60,000.00 0022 Excavation and Embankment Preparation STA 19+00 to STA 21+50, complete 5,600 CY $22.50 $126,000.00 $11.00 $61,600.00 $40.00 $224,000.00 0023 deleted $0.00 $0.00 $0.00 0024 Construct C Rock STA 19+00 to STA 21+50, complete 1,175 CY $222.00 $260,850.00 $170.00 $199,750.00 $320.00 $376,000.00 0025 Construct B Rock STA 19+00 to STA 21+50, complete 1,750 CY $237.00 $414,750.00 $175.00 $306,250.00 $320.00 $560,000.00 0026 Construct A Rock STA 19+00 to STA 21+50, complete 1,875 CY $275.00 $515,625.00 $190.00 $356,250.00 $320.00 $600,000.00

Total of Option 3 Items 0021-0026 $1,382,225.00 $998,850.00 $1,820,000.00

0027 Mobilization and Demobilization For Second Year Option Item Work, complete 1 Job $75,000.00 $75,000.00 $25,000.00 $25,000.00 $200,000.00 $200,000.00

0028 Pre- and Post-Construction Surveys for Second Year Work, complete 2 EA $11,000.00 $22,000.00 $7,500.00 $15,000.00 $30,000.00 $60,000.00

0029 Deconstruct First Year Work From STA 21+50 to 22+00 and Prepare Transition For Second Year Work, complete 1 Job $36,000.00 $36,000.00 $12,500.00 $12,500.00 $60,000.00 $60,000.00

Total of Option 4 Items 0027-0029 $133,000.00 $52,500.00 $320,000.00 Total of Base and Option Items 0001-0029 $6,972,987.50 $7,278,525.00 $11,272,000.00

No. 05

A. OFFEROR

Qayak Construction, LLC Western Marine Construction, Inc.

6. NUMBER OF AMENDMENTS ISSUED C. AMENDEMENTS ACKNOWLEDGED

No. 03

A. OFFEROR

Tutka, LLC

B. BID SECURTIY (TYPE AND AMOUNT)

No. 04

4 Yes

A. OFFEROR

ABSTRACT OF BIDS - CONSTRUCTION

1. SOLICITATION NUMBER

W911KB22B0003

4. ISSUING OFFICE

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

5. PROJECT TITLE

Ninilchik Revetment Replacement, Ninilchik, Alaska

7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)

U.S. Army Engineer District, Alaska PO Box 6898

JBER, AK 99506-6898

Christine A. Dale, Contracting Officer

SIGNATURE

9. OFFERS

YesYes

B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)

Yes Yes

C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

Yes

24-Jan-2022 3-Mar-2022 3 of 3

DATE SIGNED

29-Mar-22

ITEM NO.

EST.

QUANTITY UNIT

UNIT

PRICE

ESTIMATED

AMOUNT

UNIT

PRICE AMOUNT UNIT

PRICE AMOUNT

0001 Mobilization and Demobilization for First Year Work, complete 1 Job $231,150.00 $231,150.00 $21,909.96 $21,909.96 $600,000.00 $600,000.00

0002 Demolish and Remove Existing Revetment STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 1 Job $240,250.00 $240,250.00 $177,372.31 $177,372.31 $150,000.00 $150,000.00

0003 Excavation and Embankment Preparation STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 12,725 CY $31.76 $404,146.00 $7.70 $98,002.99 $10.00 $127,250.00

0004 deleted $0.00 $0.00 $0.00

0005 Construct C Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 2,650 CY $351.00 $930,150.00 $313.35 $830,370.19 $250.00 $662,500.00

0006 Construct B Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 4,000 CY $394.50 $1,578,000.00 $303.24 $1,212,976.51 $290.00 $1,160,000.00

0007 Construct A Rock STA 10+00 to STA 15+00 and STA 21+50 to 22+00, complete 4,150 CY $571.25 $2,370,687.50 $325.65 $1,351,430.92 $420.00 $1,743,000.00

0008 Pre- and Post-Construction Surveys for First Year Work, complete 2 EA $14,300.00 $28,600.00 $15,154.96 $30,309.92 $25,000.00 $50,000.00 Total of Base Items 0001-0008 $5,782,983.50 $3,722,372.81 $4,492,750.00

0009 Demolish and Remove Existing Revetment STA 15+00 to STA 17+00, complete 1 Job $57,200.00 $57,200.00 $42,953.07 $42,953.07 $25,000.00 $25,000.00

0010 Excavation and Embankment Preparation STA 15+00 to STA 17+00, complete 4,200 CY $21.35 $89,670.00 $5.55 $23,291.82 $10.00 $42,000.00

0011 deleted $0.00 $0.00 $0.00 0012 Construct C Rock STA 15+00 to STA 17+00, complete 950 CY $293.00 $278,350.00 $271.65 $258,064.85 $250.00 $237,500.00 0013 Construct B Rock STA 15+00 to STA 17+00, complete 1,400 CY $313.00 $438,200.00 $268.25 $375,546.55 $290.00 $406,000.00 0014 Construct A Rock STA 15+00 to STA 17+00, complete 1,500 CY $469.00 $703,500.00 $288.27 $432,404.29 $420.00 $630,000.00

Total of Option 1 Items 0009-0014 $1,566,920.00 $1,132,260.58 $1,340,500.00

0015 Demolish and Remove Existing Revetment STA 17+00 to STA 19+00, complete 1 Job $49,533.00 $49,533.00 $42,953.07 $42,953.07 $25,000.00 $25,000.00

0016 Excavation and Embankment Preparation STA 17+00 to STA 19+00, complete 4,000 CY $21.35 $85,400.00 $5.82 $23,291.82 $10.00 $40,000.00

0017 deleted $0.00 $0.00 $0.00 0018 Construct C Rock STA 17+00 to STA 19+00, complete 950 CY $292.60 $277,970.00 $271.65 $258,064.85 $250.00 $237,500.00 0019 Construct B Rock STA 17+00 to STA 19+00, complete 1,400 CY $313.70 $439,180.00 $268.25 $375,546.55 $290.00 $406,000.00 0020 Construct A Rock STA 17+00 to STA 19+00, complete 1,500 CY $469.00 $703,500.00 $288.27 $432,404.29 $420.00 $630,000.00

Total of Option 2 Items 0015-0020 $1,555,583.00 $1,132,260.58 $1,338,500.00 0021 Demolish and Remove Existing Revetment STA 19+00 to STA 21+50, complete 1 Job $51,915.00 $51,915.00 $42,264.99 $42,264.99 $25,000.00 $25,000.00 0022 Excavation and Embankment Preparation STA 19+00 to STA 21+50, complete 5,600 CY $21.25 $119,000.00 $5.80 $32,503.04 $10.00 $56,000.00 0023 deleted $0.00 $0.00 $0.00 0024 Construct C Rock STA 19+00 to STA 21+50, complete 1,175 CY $286.00 $336,050.00 $259.61 $305,036.19 $250.00 $293,750.00 0025 Construct B Rock STA 19+00 to STA 21+50, complete 1,750 CY $303.00 $530,250.00 $258.50 $452,375.03 $290.00 $507,500.00 0026 Construct A Rock STA 19+00 to STA 21+50, complete 1,875 CY $465.00 $871,875.00 $278.56 $522,308.67 $420.00 $787,500.00

Total of Option 3 Items 0021-0026 $1,909,090.00 $1,354,487.92 $1,669,750.00

0027 Mobilization and Demobilization For Second Year Option Item Work, complete 1 Job $0.00 $0.00 $81,990.13 $81,990.13 $50,000.00 $50,000.00

0028 Pre- and Post-Construction Surveys for Second Year Work, complete 2 EA $0.00 $0.00 $39,698.38 $79,396.77 $10,000.00 $20,000.00

0029 Deconstruct First Year Work From STA 21+50 to 22+00 and Prepare Transition For Second Year Work, complete 1 Job $0.00 $0.00 $64,179.65 $64,179.65 $25,000.00 $25,000.00

Total of Option 4 Items 0027-0029 $0.00 $225,566.54 $95,000.00 Total of Base and Option Items 0001-0029 $10,814,576.50 $7,566,948.43 $8,936,500.00

7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)

U.S. Army Engineer District, Alaska PO Box 6898

JBER, AK 99506-6898

Christine A. Dale, Contracting Officer

SIGNATURE

9. OFFERS

ABSTRACT OF BIDS - CONSTRUCTION

1. SOLICITATION NUMBER

W911KB22B0003

4. ISSUING OFFICE

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

5. PROJECT TITLE No. 06 No. 07 No. 08 Ninilchik Revetment Replacement, Ninilchik, Alaska A. OFFEROR A. OFFEROR A. OFFEROR

Brice Civil Constructors, Inc Leisnoi Diversified Services, LLC Alaska Marine Excavation, LLC B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)

Yes Yes

4 Yes Yes Yes

Yes

6. NUMBER OF AMENDMENTS ISSUED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED

IGE & Offerors 1-2
Offerors 3-5
Offerors 6-8