Specs_Pt.3.pdf

PDF 679 KB Posted

Attached to
Renovation of TEMP Bldg 26041
Solicitation number
W91151-19-B-0016
Issued by

About this file

Tech Exhibit A- Specification Part -3

View the file

Other files

File Type Posted
Released-_Amend_-07_W91151-19-B-0016_8-14-2019.pdf PDF
Amend-06_W9115119B0016_8-6-2019.pdf PDF
Amendment-05__W9115119B0016_8-6-2019.pdf PDF
Amend-04_W91151-19-B-0016_7-29-2019.pdf PDF
Drawings_Pg.92-119.pdf PDF
Technical__Exhibit_D-Revised_Drawings_29-Jul-2019.pdf PDF
Amendment-05__W9115119B0016_8-6-2019.pdf PDF
Amend-03_W911519B0016_7-26-2019.pdf PDF
Amend-02-W9115119B0016_RENO_TEMF_7-23-2019.pdf PDF
Amendment_01__W91151-19-B-0016_7-22-2019.pdf PDF
Drawings_Pg.120-140.pdf PDF
Specs_Pt.7.pdf PDF
Drawings_Pg.64-91.pdf PDF
Specs_Pt.2.pdf PDF
Specs_Pt.6.pdf PDF
Specs_Pt.8.pdf PDF
Drawings_1-21.pdf PDF
Exh_-_C__HAZMAT_Survey._pg._29-50.pdf PDF
Specs_Pt.5.pdf PDF
Specs_Rev.pdf PDF
Specs_Pt.4.pdf PDF
Exh_-_C__HAZMAT_Survey._pg._1-28.pdf PDF
Drawings_43-63.pdf PDF
Drawings_22-42.pdf PDF
Revised_Specs_Tech_Exh._A_,30__June_2019_pages_1-761.pdf PDF
Revised_Specs_Tech_Exh._A_,30__June_2019_pages_1396-1479.pdf PDF
Revised_Specs_Tech_Exh._A_,30__June_2019_pages_762-1395.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_73-96.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_97-120.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_49-72.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_121-140.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_1-24.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_25-48.pdf PDF
Drawing_121-132_pages.pdf PDF
Drawing_145-148_pages.pdf PDF
Drawing_85-96_pages.pdf PDF
Drawing_13-24pages.pdf PDF
Drawing_97-108_pages.pdf PDF
Drawing_49-60_pages.pdf PDF
Drawing_61-72_pages.pdf PDF
Drawing_109-120_pages.pdf PDF
Drawing133-144_pages.pdf PDF
Drawing_1-12_pages.pdf PDF
Drawing_73-84_pages.pdf PDF
Drawing_25-36_pages.pdf PDF
Drawing_37-48_pages.pdf PDF
Drawing_Exhibit_B.pdf PDF
Specs_(Tech_Exh._A).pdf PDF
Attachment_1-Appendix_A_27-JUL-2018.pdf PDF
W9115119B0016_Renovation_of_TEMF_Building_.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEMF 26041 Fort Hood, Texas

CORRECTED FINAL

TEST PROCEDURES

TITLE: Test Index OBJECTIVE: The following is an index of tests.

NOTES: Tests one through twenty contain specific "item(s)" that apply to Sections 25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT END AND INTEGRATION) and 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC. The following index of tests provides a summary of which "items numbers" apply to which specification.

Test No. Test Title Section 23 09 00, Section 25 10 10

DDC for HVAC

One Initial System Equipment Verification

Items 1 through 15 Items 16 through 32

Two System Start-up Items 1 through 4 Items 5 and 6

Three Monitor and Control Software

Items 1 through 5 Not Applicable

Four Graphic Display of Data Items 1 through 18 Not Applicable

Five Graphic Navigation Scheme Items 1 and 2 Not Applicable

Six Command Functions Items 1 through 6 Not Applicable

Seven Command Input Errors Items 1 through 6 Items 1 through 6

Eight Special Functions Item 1 Not Applicable

Nine Software Editing Tools Items 1 through 42 Items 1 through 42

Ten Scheduling Items 1 through 7 Items 8 through 10

Eleven Alarm function Items 1 through 15 item 16

Twelve Trending Items 1 through 8 Not Applicable

Thirteen Demand Limiting Items 1 through 8 Not Applicable

Fourteen Report Generation Items 1 through 6 Not Applicable

Fifteen UPS Test Items 1 through 5 Not Applicable

Sixteen CTA CTA-709.1-D to IP Router Test

Items 1 through 3 Not Applicable

Seventeen CTA CTA-709.1-D Router and Repeater

Not Applicable Items 1 through 4

SECTION 25 08 10 Page 12

Test No. Test Title Section 23 09 00, Section 25 10 10

DDC for HVAC

Eighteen CTA CTA-709.1-D Gateway Test

Items 1 through 5 Items 1 through 5

Nineteen Local Display Panel Not Applicable Items 1 through 5

Twenty Network Configuration Tool

Items 1 through 8 Items 1 through 8

Twenty-One Custom Tests Item 1 and 2 Item 1 and 2

SECTION 25 08 10 Page 13

PVT Checklist

OBJECTIVE:

1. Inspect/test/verify that building-level DDC system is compliant with Section 23 09 00 and capable of integration with UMCS

INITIAL REQUIREMENTS/CONDITIONS

1. The following tests shall be completed and documentation shall be submitted to the Government.

2. Date of Checklist: __________

3. Time of Checklist: __________

4. Contractor's Representative: ____________________

5. Government's Representative: ____________________

CHECKLIST PROCEDURES

Expected Item Action Item Results Approved

UMCS AND DDC FOR HVAC

1 Draft or Final Drawings submitted and As-Built Drawings approved __________

Point schedule(s) showing all required UMCS SNVTs submitted __________

Point schedules(s) showing device network addresses submitted __________

Local display panel (LDP) locations indicated on drawings submitted __________

Notes: _____________________________________________________________

2 Network Bandwidth Test Test completed, accepted, Report and a report documenting results submitted __________

Notes: _____________________________________________________________

3 Programming software Most recent version of the programming software for each type of GPPC has been submitted __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 14

Expected Item Action Item Results Approved 4 XIF Files External interface files (XIF) files for each model of LONWORKS®-based DDC hardware has been submitted __________

Notes: _____________________________________________________________

5 LNS Database Copies of the LNS database for the completed control network has been submitted __________

Notes: _____________________________________________________________

6 LNS Plug-in LNS Plug-ins for each application specific controller has been submitted __________

Notes: _____________________________________________________________

7 Start-up testing report Start-up has been successfully completed and testing report submitted __________

Controller tuning has been completed and document on point schedule __________

Calibration accuracy check completed and documented in test report __________

Actuator range check completed and documented in test report __________

Functional test to demonstrate control sequence completed and documented in test report __________

Notes: _____________________________________________________________

8 Software License Software licenses received for all software on the project __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 15

Expected Item Action Item Results Approved

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 16

TEST NUMBER: One TITLE: Initial System Equipment Verification

OBJECTIVE:

1. To verify that the hardware and software components of the system provided by the Contractor are in accordance with the contract plans and specifications and all approved submittals.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Submit a detailed list of all approved hardware with Manufacturer, model number and location. This list is based on the contract plans, specifications, change orders (if any) and approved submittals which shall be available for reference purposes during the test.

b. Submit a detailed list of all approved software with revision number and purpose of software. This list is based on the contract plans, specifications, change orders (if any) and approved submittals which shall be available for reference purposes during the test.

2. Equipment

a. Verify all equipment is functional.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS

1 The workstation hardware is installed and complies with specification paragraph titled "Workstation Hardware". ________________ __________

Notes: _____________________________________________________________

2 The Server hardware is installed and complies with specification paragraph titled "Server Hardware". ________________ __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 17

Expected Item Action Item Results Approved

3 The fiber optic patch panel is installed and complies with specification paragraph titled "Fiber Optic Patch Panel". ________________ __________

Notes: _____________________________________________________________

4 The fiber optic media converter is installed and complies with specification paragraph titled "Fiber Optic Media Converter". ________________ __________

Notes: _____________________________________________________________

5 The Ethernet switch is installed and complies with specification paragraph titled "Ethernet Switch". ________________ __________

Notes: _____________________________________________________________

6 The IP router is installed and complies with specification paragraph titled "IP Router". ________________ __________

Notes: _____________________________________________________________

7 The CTA CTA-709.1-D to IP router is installed and complies with specification paragraph titled "CTA CTA-709.1-D to IP Router". ________________

Notes: _____________________________________________________________

8 The CTA CTA-709.1-D gateway is installed and complies with specification paragraph titled "CTA CTA-709.1-D Gateway". ________________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 18

Expected Item Action Item Results Approved 9 The alarm printer is installed and complies with specification paragraphs titled "PRINTERS" and "Alarm Printer". ________________ __________

Notes: _____________________________________________________________

10 The laser printer is installed and complies with specification paragraphs titled "PRINTERS" and "Laser Printer". ________________ __________

Notes: _____________________________________________________________

11 The color printer is installed and complies with specification paragraphs titled "PRINTERS" and "Color Printer". ________________ __________

Notes: _____________________________________________________________

12 The operating system is installed and complies with specification paragraph titled "Operating System (OS)". ________________ __________

Notes: _____________________________________________________________

13 The office automation software is installed and complies with specification paragraph titled "Office Automation Software". ________________ __________

Notes: _____________________________________________________________

14 The virus protection software is installed and complies with specification paragraph titled "Virus Protection Software". ________________ __________

Notes: _____________________________________________________________

15 The configuration server is installed and complies with specification paragraph titled

SECTION 25 08 10 Page 19

Expected Item Action Item Results Approved "CTA CTA-852-C Configuration Server". __________ __________

Notes: _____________________________________________________________

DDC FOR HVAC

16 The CTA CTA-709.1-D Router is installed and complies with specification paragraph titled "CTA CTA-709.1-D Router". ________________ __________

Notes: _____________________________________________________________

17 The CTA CTA-709.3 Repeater is installed and complies with specification paragraph titled "CTA CTA-709.3 Repeater". ________________ __________

Notes: _____________________________________________________________

18 The TP/FT-10 network is installed in accordance with CTA CTA-709.3, with double-terminated bus topology. ________________ __________

Notes: _____________________________________________________________

19 Network wiring extends to the location of UMCS BPOC. ________________ __________

Notes: _____________________________________________________________

20 The Gateway is installed and complies with specification paragraph titled "Gateway". ________________ __________

Notes: _____________________________________________________________

21 All control valves are installed and comply with their associated specification paragraph under the section titled "Control Valves". ________________ __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 20

Expected Item Action Item Results Approved

22 All dampers are installed and comply with their associated specification paragraph under the section titled "Dampers". ________________ __________

Notes: _____________________________________________________________

23 All sensors are installed and comply with their associated specification paragraph under the section titled "Sensors". ________________ __________

Notes: _____________________________________________________________

24 All indicating devices are installed and comply with their associated specification paragraph under the section titled "Indicating Devices". ________________ __________

Notes: _____________________________________________________________

25 All user input devices are installed and comply with their associated specification paragraph under the section titled "User Input Devices". ________________ __________

Notes: _____________________________________________________________

26 All output devices are installed and comply with their associated specification paragraph under the section titled "Output Devices". ________________ __________

Notes: _____________________________________________________________

27 All multifunction devices are installed and comply with their associated specification paragraph under the section titled "Multifunction Devices". ________________ __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 21

Expected Item Action Item Results Approved

28 All compressed air equipment is installed and complies with their associated specification paragraph under the section titled "Compressed Air". ________________ __________

Notes: _____________________________________________________________

29 All ASCs are installed and comply with the specification paragraph titled "Application Specific Controller". ________________ __________

Notes: _____________________________________________________________

30 All LDPs and laptop computers are provided and comply with the specification paragraph titled "Local Display Panel". ________________ __________

Notes: _____________________________________________________________

31 All GPPCs are installed and comply with the specification paragraph titled "General Purpose Programmable Controller". ________________ __________

Notes: _____________________________________________________________

32 LNS-based system used to address nodes, bind variables, and LNS database of network exists on system. ________________ __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 22

TEST NUMBER: Two TITLE: System Start-up

OBJECTIVE:

1. To validate that the system properly initializes and that the GUI properly reconnects to all communicating devices.

2. To validate that both application specific and programmable devices retain all vital information upon a power cycle.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide a list of all software that will be used to verify point connection at field level controllers and user interface.

b. Provide a list of all software need to verify application specific and programmable controller start-up.

2. Equipment

a. All peripherals and cables shall be connected in accordance with manufacturer's requirements.

b. The workstation shall be in the off mode.

c. All controls shall be fully functional and tested.

d. A programmable and application specific controller shall be randomly selected for the test.

3. Date of Test: __________

4. Time of Test: __________

5. Contractor's Representative: ____________________

6. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS

1 Energize the workstation. The workstation will power-up and perform its start-up procedure without generating any errors or problems. __________

a) Operating system Operating system shall be latest version of windows. __________

b) Start Network The Network Configuration Configuration Tool. Tool drawing will open. __________

c) Start the System The System plug-in will Plug-in. open. __________

d) Start the Server. The Server will start. __________

e) Start the Workstation. The Workstation will start.

The operator shall now have the ability to view data from any device on the

SECTION 25 08 10 Page 23

Expected Item Action Item Results Approved network. __________

Notes: _____________________________________________________________

2 Check the communication Within the workstation from the server to the software, when a device is controllers. selected, dynamic points lists become visible.

Dynamic data represents success. A completion event failure message represents failure. __________

Notes: _____________________________________________________________

3 Verify on-line status. All devices shall have on-line status indicated by the workstation software (green indicator). __________

Notes: _____________________________________________________________

4 View data from the When a graphics page is graphical environment. opened, the points on the page should update.

Question marks in lieu of data reflect failure. __________

Notes: _____________________________________________________________

DDC FOR HVAC

5 Verify that configuration All configuration data in application parameters should be specific controllers is accessible. __________ written to EEPROM.

a) Open the LONWORKS® Software should open plug-in. without errors. __________

b) Note several Operator is able to view parameters such as a sample of parameters temperature setpoints (data values and setpoints).

and flow settings. __________

c) Remove power from the Device should go off-line controller for a in Network Configuration minimum of 3 minutes. Tool and workstation/server. __________

d) Replace power to the Device should return to controller. on-line status. __________

e) Using the plug-in, Parameters shall not have verify that the changed.

parameters have not __________

SECTION 25 08 10 Page 24

Expected Item Action Item Results Approved changes.

Notes: _____________________________________________________________

6 Verify that configuration data in programmable controllers is retained after a power cycle. ________________ __________

a) From the Workstation Values of the parameters view several can be viewed from the configuration tree structure.

parameters and note the values. __________

b) Remove power for a Controller will go offline minimum of 3 minutes. in workstation software. __________

c) Replace power to the Controller will return to controller. online status. __________

d) From the Workstation Parameters values shall view the same not have changed.

configuration parameters and note the values. __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 25

TEST NUMBER: Three TITLE: Monitor and Control (M&C) Software Passwords

OBJECTIVE:

1. To validate that the system utilizes four basic password levels

2. To validate that each password level has the specified authority

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide documentation of M&C user password capacity in comparison with specification.

b. Provide a complete list of all users along with their passwords and user level prior to testing.

2. Equipment

a. Server and Workstation

3. Reference Documentation

a. Provide user manual documentation for setting up passwords

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS

1 Create password for new New users shall exist in users. the server Database. __________

a) Set-up 4 users. ________________ __________

b) Assign different levels to each. ________________ __________

Notes: _____________________________________________________________

2 Demonstrate level 1 authority. ________________ __________

a) Sign in as the level 1 Sign in shall be user. successful. __________

b) Attempt to view a Action shall be possible.

system graphic. __________

c) Attempt to acknowledge Action shall be denied.

an alarm. __________

d) Attempt to configure a Action shall be denied.

trend. __________

e) Attempt to configure a Action shall be denied.

report. __________

SECTION 25 08 10 Page 26

Expected Item Action Item Results Approved

f) Attempt to override a Action shall be denied.

point. __________

g) Attempt to configure an Action shall be denied.

alarm. __________

h) Attempt to configure a Action shall be denied.

schedule. __________

i) Attempt to configure a Action shall be denied.

demand limiting parameter. __________

j) Attempt to modify a Action shall be denied.

graphic page. __________

k) Attempt to create a Action shall be denied.

custom program. __________

Notes: _____________________________________________________________

3 Demonstrate level 2 ________________ __________ authority.

a) Sign in as the level 2 Sign in shall be successful.

user. __________

b) Attempt to view a Action shall be possible.

system graphic. __________

c) Attempt to acknowledge Action shall be possible.

an alarm. __________

d) Attempt to configure a Action shall be possible.

trend. __________

e) Attempt to configure a Action shall be possible.

report. __________

f) Attempt to override a Action shall be denied.

point. __________

g) Attempt to configure an Action shall be denied.

alarm. __________

h) Attempt to configure a Action shall be denied.

schedule. __________

i) Attempt to configure a Action shall be denied.

demand limiting parameter. __________

j) Attempt to modify a Action shall be denied.

graphic page. __________

k) Attempt to create a Action shall be denied.

custom program. __________

Notes: _____________________________________________________________

4 Demonstrate level 3 authority. ________________ __________

a) Sign in as the level 3 Sign in shall be user. successful. __________

b) Attempt to view a Action shall be possible.

system graphic. __________

c) Attempt to acknowledge Action shall be possible.

an alarm. __________

d) Attempt to configure a Action shall be possible.

SECTION 25 08 10 Page 27

Expected Item Action Item Results Approved trend. __________

e) Attempt to configure a Action shall be possible.

report. __________

f) Attempt to override a Action shall be possible.

point. __________

g) Attempt to configure an Action shall be possible.

alarm. __________

h) Attempt to configure a Action shall be possible.

schedule. __________

i) Attempt to configure a Action shall be possible.

demand limiting parameter. __________

j) Attempt to modify a Action shall be denied.

graphic page. __________

k) Attempt to create a Action shall be denied.

custom program. __________

Notes: _____________________________________________________________

5 Demonstrate level 4 authority. ________________ __________

a) Sign in as the level 3 Sign in shall be user. successful. __________

b) Attempt to view a Action shall be possible.

system graphic. __________

c) Attempt to acknowledge Action shall be possible.

an alarm. __________

d) Attempt to configure a Action shall be possible.

trend. __________

e) Attempt to configure a Action shall be possible.

report. __________

f) Attempt to override a Action shall be possible.

point. __________

g) Attempt to configure an Action shall be possible.

alarm. __________

h) Attempt to configure a Action shall be possible.

schedule. __________

i) Attempt to configure a Action shall be possible.

demand limiting parameter. __________

j) Attempt to modify a Action shall be possible.

graphic page program. __________

k) Attempt to create a Action shall be possible.

custom program. __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 28

SECTION 25 08 10 Page 29

TEST NUMBER: Four TITLE: Graphic Display of Data

OBJECTIVE:

1. To validate that floor plans and equipment can be graphically displayed through GUI.

2. To validate the proper display of alarms on GUI.

3. To validate the proper display of trend data on GUI.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide hard copies of "snap shots" of sample graphics pages prior to testing.

2. Equipment

a. Complete all graphics.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Notes

a. Different types of data and states should be clearly distinguishable from each other.

5. Date of Test: __________

6. Time of Test: __________

7. Contractor's Representative: ____________________

8. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved 1 Demonstrate the use of a Equipment shall be three dimensional represented in a three representation of a dimensional manner.

mechanical system. __________

Notes: _____________________________________________________________

2 Demonstrate the Dynamic real time data presentation of real time shall be presented on a data. graphics page. __________

Notes: _____________________________________________________________

3 Demonstrate the A user defined parameter presentation of user such as a setpoint shall be

SECTION 25 08 10 Page 30

Expected Item Action Item Results Approved entered data. presented on a graphics page.

Different types of data and states should be clearly distinguishable from each other. __________

Notes: _____________________________________________________________

4 Demonstrate the An indication of override presentation of a point condition shall be viewable in override. on the graphic page.

Different types of data and states should be clearly distinguishable from each other. __________

Notes: _____________________________________________________________

5 Demonstrate the An indication of the alarm presentation of a device state shall be viewable on in the alarm state. the graphic page. Different types of data and states should be clearly distinguishable from each other. __________

Notes: _____________________________________________________________

6 Demonstrate the An indication of out of range presentation of data that condition shall be viewable is out of range. on the graphic page.

Different types of data and states should be clearly distinguishable from each other. __________

Notes: _____________________________________________________________

7 Demonstrate the An indication of missing data presentation of missing shall be viewable on the data (controller is graphic page. Different offline). types of data and states should be clearly distinguishable from each other. __________ Notes: _____________________________________________________________

SECTION 25 08 10 Page 31

Expected Item Action Item Results Approved 8 Demonstrate an error An error message shall be message when the operator displayed.

attempts to execute in improper command. __________

Notes: _____________________________________________________________

9 Demonstrate point and click Operator shall be able to access to context sensitive easily access context help. sensitive help using the mouse. __________

Notes: _____________________________________________________________

10 Demonstrate point and click Operator shall be able to access to an engineering access an engineering diagram. diagram using the mouse. __________

Notes: _____________________________________________________________

11 Demonstrate the creation of Operator shall be able to an engineering diagram. create an engineering diagram. __________

Notes: _____________________________________________________________

12 Demonstrate the printing of Operator shall be able to a prepared report. print a report using the mouse. __________

Notes: _____________________________________________________________

13 Demonstrate the display of Operator shall be able to one or more points. request the display of one or more points. __________

Notes: _____________________________________________________________

14 Demonstrate the operator Operator shall be able to override of a point. override a point. __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 32

Expected Item Action Item Results Approved 15 Demonstrate the Operator shall be able to modification of a modify a time schedule.

time schedule. __________

Notes: _____________________________________________________________

16 Demonstrate the execution Operator shall be able to of a report. initiate a report. __________

Notes: _____________________________________________________________

17 Demonstrate the Operator shall be able to presentation of an view an alarm with all of alarm to include: the required data. __________

a) Identification ________________ __________

b) Date and time ________________ __________

c) Alarm Type ________________ __________

d) Set Points ________________ __________

e) Units ________________ __________

f) Current Value ________________ __________

g) Priority ________________ __________

h) Associated message & Secondary message ________________ __________

Notes: _____________________________________________________________

18 Demonstrate the Operator shall be able to presentation of view real time trend data real time trend data. as a function of time. __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 33

TEST NUMBER: Five TITLE: Graphic Navigation Scheme

OBJECTIVE:

1. To validate hierarchical graphic displays from main screen to end devices.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide a hierarchical block diagram of the system network prior to testing.

2. Equipment

a. Have all programming completed to demonstrate graphic display.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS

1 Demonstrate the creation Operator shall be able to of a hierarchical tree organize point data graphic structure for the display in a hierarchical presentation of point tree structure based on any data with at least five organization desired.

levels.

A typical organization could be:

- Installation

- Building

- Building sub area

- Main System-Unit

- Terminal Unit __________

Notes: _____________________________________________________________

2 Demonstrate the creation Operator shall be able or of a hierarchical organize the graphical navigation structure for navigation from page to the graphic pages. page using any hierarchical structure desired.

SECTION 25 08 10 Page 34

Expected Item Action Item Results Approved Examples:

Home page to building 1 Building 1 to AHU 1 Building 1 back to Home Page Building 1 to 1st Floor Plan AHU 1 back to Building 1 AHU 1 back to Home Page AHU 1 to Terminal Unit Summary 1st Floor Plan back to Building 1 1st Floor Plan back to Home Page 1st Floor Plan to Any Terminal Device Terminal Unit Summary back to AHU 1 Terminal Unit Summary back to Building 1 Terminal Unit Summary back to Home Page Terminal Unit Summary to Individual Device __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 35

TEST NUMBER: Six TITLE: Command Functions

OBJECTIVE:

1. To demonstrate the functionality and ability to execute command to the end devices.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide documentation of all command functions prior to testing.

2. Equipment

a. Have all command functions programmed and functional.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS AND DDC FOR HVAC

1 From the tree structure, The modified value shall be modify a parameter such as downloaded to the controller a set point. without delay and the controller performance shall be viewable by the monitoring of other dynamic points. __________

Notes: _____________________________________________________________

2 From a graphic page, modify The modified value shall be a parameter such as a set downloaded to the controller point. without delay and the controller performance shall be viewable by the monitoring of dynamic points. __________

Notes: _____________________________________________________________

3 From the tree structure, The analog output point place an analog output shall accept the assigned point under operator value and ignore changes

SECTION 25 08 10 Page 36

Expected Item Action Item Results Approved override and assign a from application logic until fixed value. the point is taken out of override. __________

Notes: _____________________________________________________________

4 From a graphic page, place The analog output point shall an analog output point accept the assigned value and under operator override ignore changes from and assign a fixed value. application logic until the point is taken out of override. __________

Notes: _____________________________________________________________

5 From the tree structure, The digital output point shall place a digital output accept the assigned value and point under operator ignore changes from application override and assign a logic until the point is taken fixed value. out of override. __________

Notes: _____________________________________________________________

6 From a graphic page, place The digital output point shall a digital output point accept the assigned value and under operator override ignore changes from application and assign a fixed value. logic until the point is taken out of override. __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 37

TEST NUMBER: Seven TITLE: Command Input Errors

OBJECTIVE:

1. To validate that the system ensures the necessary authority for command inputs

2. To validate that the system can control the range of command input values

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide all command input error messages prior to testing.

2. Equipment

a. UMCS and DDC hardware and software

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS AND DDC FOR HVAC

1 Login using a password Login occurs. __________ with point command.

Notes: _____________________________________________________________

2 Request a display of a The system displays the SNVT. controllers SNVT value. __________

Notes: _____________________________________________________________

3 Override the SNVT point The SNVT value override to a selected value. changes the value in the controller. __________

Notes: _____________________________________________________________

4 Release the override of The SNVT value returns to

SECTION 25 08 10 Page 38

Expected Item Action Item Results Approved a SNVT. normal. __________

Notes: _____________________________________________________________

5 For an nvi to a The value will go the controller with a limit of maximum of 80.

50 to 80, command the nvi to a value of 90. __________

Notes: _____________________________________________________________

6 For an nvi to a The operator will be denied controller for which the the ability to command the operator only has read nvi to any value.

privileges, command the nvi to a value of 90. __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 39

TEST NUMBER: Eight TITLE: Special Functions

OBJECTIVE:

1. Verify system has special integration as defined.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide documentation of all integrations prior to testing.

2. Equipment

a. Have all UMCS and DDC hardware and software programmed, integrated, and completed.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS

1 Verify that a building Data from the other vendors that uses controls from a controllers shall be integrated vendor other than the one into the GUI and the same being installed can be functionality that would exist integrated into the GUI if the controllers were from without any loss of the same manufacture shall functionality. exist.

(A simulated building will be set up using an IP-L router and controllers from Honeywell, TAC, Trane, etc.) __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 40

TEST NUMBER: Nine TITLE: Software editing tools

OBJECTIVE:

1. To validate the performance of the M & C application programming tool for the GPPC.

2. To validate the performance of the display editing tool.

3. To validate the performance of the report generation display tool.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide documentation and a backup softcopy of the editing tool prior to testing.

b. Provide documentation of any future software upgrade versions that pertain to the software-editing tool.

2. Equipment

a. Have working knowledge of the full capability of the software-editing tool.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS and DDC for HVAC 1 Demonstrate the Operator shall be able to programming of an override use the programmed function function in a GPPC. to override an output point in a GPPC. __________

Notes: _____________________________________________________________

2 Demonstrate software that Operator shall be able to enables the monitoring of monitor points from a GPPC.

data from a GPPC. __________

Notes: _____________________________________________________________

3 Demonstrate timer Control logic shall honor

SECTION 25 08 10 Page 41

Expected Item Action Item Results Approved functions within the built in timers.

applications of GPPC. __________

a) delay on ________________ __________

b) delay off ________________ __________

c) one second delays ________________ __________

d) interval timers ________________ __________

Notes: _____________________________________________________________

4 Demonstrate logic loops Control logic shall honor ("for" and "while") in the criteria.

GPPC. __________

Notes: _____________________________________________________________

5 Demonstrate if-then-else Control logic shall properly logic in GPPC. follow the if, then, else requirements. __________

Notes: _____________________________________________________________

6 Demonstrate basic math Control logic shall properly functions in GPPC. execute math functions. __________

Notes: _____________________________________________________________

7 Demonstrate Boolean math Control logic shall properly functions in GPPC. execute the functions. __________

Notes: _____________________________________________________________

8 Demonstrate exponential Control logic shall properly math functions in GPPC. execute the functions. __________

Notes: _____________________________________________________________

9 Demonstrate trigonometric Control logic shall properly math functions in GPPC. execute the functions. __________

Notes: _____________________________________________________________

10 Demonstrate bitwise math Control logic shall properly functions in GPPC. execute the functions. __________

SECTION 25 08 10 Page 42

Expected Item Action Item Results Approved

Notes: _____________________________________________________________

11 Create a user defined Subroutine/function shall subroutine/function in work correctly and be easily GPPC. reused. __________

Notes: _____________________________________________________________

12 Create alarm conditions Alarm variables shall be in GPPC. created according to the criteria. __________

Notes: _____________________________________________________________

13 Create and save a graphic Symbol shall be reusable symbol at the server. on a new graphic. __________

Notes: _____________________________________________________________

14 Modify a graphic symbol Operator shall be able to at the server. open an existing symbol and make changes. __________

Notes: _____________________________________________________________

15 Save a graphic symbol to Symbol shall be available a library at the server. from the library for reuse. __________

Notes: _____________________________________________________________

16 Delete a graphic symbol Symbol shall no longer exist at the server. for use. __________

Notes: _____________________________________________________________

17 Place a graphic symbol When the new page is opened, on a new graphic page at the symbol shall be there.

server. __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 43

Expected Item Action Item Results Approved

18 Associate particular When the conditional variable conditions with changes, the display should particular displays at change.

the server. __________

Notes: _____________________________________________________________

19 Overlay alphanumeric Text shall properly display.

text on a graphic at the server. __________

Notes: _____________________________________________________________

20 Create a new graphic New graphic shall properly from an old one at the display.

server. __________

Notes: _____________________________________________________________

21 Place dynamic data on The dynamic data shall be a graphic at the server. viewable on the graphic. __________

Notes: _____________________________________________________________

22 Define the background The new graphic shall show color of a new graphic the selected background at the server. color. __________

Notes: _____________________________________________________________

23 Define a foreground The color of the dynamic color for an element on data that uses the a graphic to distinguish foreground color shall display it from the background in the foreground color.

color at the server. __________

Notes: _____________________________________________________________

24 Position a symbol on a The operator shall be able to graphic at the server. place a symbol at any location on a graphic. __________

Notes: _____________________________________________________________

SECTION 25 08 10 Page 44

Expected Item Action Item Results Approved

25 Position and edit The alphanumeric display shall alphanumeric descriptors be as designed.

at the server. __________

Notes: _____________________________________________________________

26 Draw lines on a graphic Lines shall display as at the server. drawn. __________

Notes: _____________________________________________________________

27 Associate source of Correct data shall be dynamic data for displayed.

presentation on a graphic at the server. __________

Notes: _____________________________________________________________

28 Display analog data on Correct data shall be a graphic page at the displayed.

server. __________

Notes: _____________________________________________________________

29 Demonstrate the movement Crosshairs shall follow of the curser (crosshairs) the commands from the mouse.

by the use of the mouse at the server. __________

Notes: _____________________________________________________________

30 Demonstrate the Operator shall see the use simultaneous use of of the tile function and multiple graphics the use of the tab function (coincident graphics)at to manage multiple graphics.

the server. __________

Notes: _____________________________________________________________

31 Associate graphic Graphic properties shall properties such as color change as the value of the with the values from dynamic variable changes.

dynamic variables at

SECTION 25 08 10 Page 45

Expected Item Action Item Results Approved the server. __________

Notes: _____________________________________________________________

32 Create conditional The graphic display shall displays based on the change as the dynamic value of a dynamic variable changes.

variable at the server. __________

Notes: _____________________________________________________________

33 Review the standard Operator shall see how to symbol library at the access symbols from the standard symbol library. __________

Notes: _____________________________________________________________

34 Demonstrate how to move The executed report shall data from the database to contain data from the a report at the server. database. __________

Notes: _____________________________________________________________

35 Add comments and headers The executed report shall to a report at the server. contain the comments and headers. __________

Notes: _____________________________________________________________

36 Demonstrate the time Data presented in a report stamping of data in a shall include the date and report at the server. time the data was sampled. __________

Notes: _____________________________________________________________

37 Demonstrate the time A report shall include the stamping of the report date and time it executed.

generation at the server. __________

Notes: _____________________________________________________________

38 Demonstrate basic Report shall display the mathematical manipulation results of the mathematical

SECTION 25 08 10 Page 46

Expected Item Action Item Results Approved of data within a report manipulations.

(daily averages, highs, lows, etc.) at the server. __________

Notes: _____________________________________________________________

39 Demonstrate the Reports shall execute per operator's ability to the operator's instructions.

select either automatic or manual generation of a report. Report one shall execute per the operator's instructions.

Report two shall execute automatically on a time basis per operator's instructions. __________

Notes: _____________________________________________________________

40 Demonstrate the Reports shall execute per selection of either the operator's instructions.

display, print to printer or print to file. Report one is printed to printer.

Report two is printed to file. __________

Notes: _____________________________________________________________

41 Demonstrate how a Modified list of variables modified application shall be available from program is imported into a workstation.

the server database for presentation to the workstations. __________

Notes: _____________________________________________________________

42 Demonstrate how a new New list of variables from device is added to the the new device shall be server database for available from a workstation.

presentation to the workstations. __________

Notes: _____________________________________________________________

End of Test

SECTION 25 08 10 Page 47

Expected Item Action Item Results Approved

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 48

TEST NUMBER: Ten TITLE: Scheduling

OBJECTIVE:

1. Verify that M&C software has ability to operate end devices off a time of day schedule utilizing defined parameters.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide documentation of the minimum programmable schedules in comparison to the specification requirement prior to testing.

b. Provide documentation of all schedules programmed in the UMCS prior to testing.

c. Provide a trend or report log of all equipment on a schedule prior to testing.

2. Equipment

a. Have GPPC and ASC with all scheduling completed for testing.

3. Reference Documentation

a. List user manual documentation and sections pertaining to the testing.

4. Date of Test: __________

5. Time of Test: __________

6. Contractor's Representative: ____________________

7. Government's Representative: ____________________

TEST PROCEDURES

Expected Item Action Item Results Approved

UMCS

1 Demonstrate the basic The value of SNVT_occupancy functionality of a time shall properly track the schedule by monitoring time schedule.

the value of SNVT_occupancy as the time changes through a start time or a stop time. __________

Notes: _____________________________________________________________

2 Setup a weekly time Scheduling software shall schedule for a demo accommodate the described system with independent requirements.

times for each day of the week and with up to 6 events per day. __________

SECTION 25 08 10 Page 49

Expected Item Action Item Results Approved

Notes: _____________________________________________________________

3 Setup a special event or The special event schedule date specific time shall take precedence.

schedule and verify that this schedule takes precedence over the weekly schedule. __________

Notes: _____________________________________________________________

4 Setup a group time The group schedule shall schedule for a collection take precedence.

of systems. This group schedule shall take precedence over the individual time schedules. __________

Notes: _____________________________________________________________

5 Demonstrate operator Operator shall be able to access to a time schedule access the time scheduling from a graphic page. editor from a graphic page. __________

Notes: _____________________________________________________________

6 Display the current date Operator shall be able to and time on a graphic view the current date and page. time from a graphic page. __________

Notes: _____________________________________________________________

7 Demonstrate automatic Time of day shifts daylight savings time automatically.

adjustment. __________

Notes: _____________________________________________________________

HVAC

8 Demonstrate the ability Equipment shall change of GPPC to accept an modes based on the UMCS or occupied, unoccupied and from "system scheduler" standby command from the SNVT schedule data.

UMCS. __________

SECTION 25 08 10 Page 50

Expected Item Action Item Results Approved

Notes: _____________________________________________________________

9 Demonstrate the ability Equipment shall change of ASC to accept an modes based on the UMCS occupied, unoccupied and SVNT schedule data.

standby command from the

UMCS. __________

Notes: _____________________________________________________________

10 Demonstrate use of the Equipment should use the default schedule when default schedule until communication is lost to communication is the UMCS. reestablished. __________

Notes: _____________________________________________________________

End of Test

Specific Abbreviations:

Y = Yes N = No NA = Not Applicable

SECTION 25 08 10 Page 51

TEST NUMBER: Eleven TITLE: Alarm Function

OBJECTIVE:

1. Verify M&C software is capable of alarm notification and routing.

INITIAL REQUIREMENTS/CONDITIONS

1. Submittals

a. Provide documentation of alarm managing capacity in caparison with specification.

b. Provide documentation of all alarm types and priorities utilized in the M&C prior to testing.

c. Provide documentation of the alarm routing in this particular M&C.

2. Equipment

a. Provide GPPC and ASC will alarms…