Amendment-05__W9115119B0016_8-6-2019.pdf

PDF 211 KB Posted

Attached to
Renovation of TEMP Bldg 26041
Solicitation number
W91151-19-B-0016
Issued by

About this file

Amend-05 is issued to revised the Statement of Work Period of performance to 365 days

View the file

Other files

File Type Posted
Released-_Amend_-07_W91151-19-B-0016_8-14-2019.pdf PDF
Amend-06_W9115119B0016_8-6-2019.pdf PDF
Amend-04_W91151-19-B-0016_7-29-2019.pdf PDF
Drawings_Pg.92-119.pdf PDF
Technical__Exhibit_D-Revised_Drawings_29-Jul-2019.pdf PDF
Amendment-05__W9115119B0016_8-6-2019.pdf PDF
Amend-03_W911519B0016_7-26-2019.pdf PDF
Amend-02-W9115119B0016_RENO_TEMF_7-23-2019.pdf PDF
Amendment_01__W91151-19-B-0016_7-22-2019.pdf PDF
Drawings_Pg.120-140.pdf PDF
Specs_Pt.7.pdf PDF
Drawings_Pg.64-91.pdf PDF
Specs_Pt.2.pdf PDF
Specs_Pt.6.pdf PDF
Specs_Pt.8.pdf PDF
Drawings_1-21.pdf PDF
Exh_-_C__HAZMAT_Survey._pg._29-50.pdf PDF
Specs_Pt.3.pdf PDF
Specs_Pt.5.pdf PDF
Specs_Rev.pdf PDF
Specs_Pt.4.pdf PDF
Exh_-_C__HAZMAT_Survey._pg._1-28.pdf PDF
Drawings_43-63.pdf PDF
Drawings_22-42.pdf PDF
Revised_Specs_Tech_Exh._A_,30__June_2019_pages_1-761.pdf PDF
Revised_Specs_Tech_Exh._A_,30__June_2019_pages_1396-1479.pdf PDF
Revised_Specs_Tech_Exh._A_,30__June_2019_pages_762-1395.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_73-96.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_97-120.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_49-72.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_121-140.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_1-24.pdf PDF
Revised_Drawing_Tech_Exh._B_,19_June_2019__pages_25-48.pdf PDF
Drawing_121-132_pages.pdf PDF
Drawing_145-148_pages.pdf PDF
Drawing_85-96_pages.pdf PDF
Drawing_13-24pages.pdf PDF
Drawing_97-108_pages.pdf PDF
Drawing_49-60_pages.pdf PDF
Drawing_61-72_pages.pdf PDF
Drawing_109-120_pages.pdf PDF
Drawing133-144_pages.pdf PDF
Drawing_1-12_pages.pdf PDF
Drawing_73-84_pages.pdf PDF
Drawing_25-36_pages.pdf PDF
Drawing_37-48_pages.pdf PDF
Drawing_Exhibit_B.pdf PDF
Specs_(Tech_Exh._A).pdf PDF
Attachment_1-Appendix_A_27-JUL-2018.pdf PDF
W9115119B0016_Renovation_of_TEMF_Building_.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0011338597 AD005585P

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment -05 is issued to revised the Statement of Work to extend the Period of Performance to 365 days

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9115119B0016

X 9B. DATED (SEE ITEM 11)

26-Jun-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2019

CODE

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

36000 DARNALL LOOP, ROOM 1300B

FORT HOOD TX 76544-5095

W91151 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9115119B0016

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The contractor period of performance end date has increased by 125 days from 240 days to 365 days.

The following have been modified:

REVISED PROJECT SYNOPSIS

REVISED PROJECT SYNOPSIS

Renovate TEMF Building 26041

Project No. AD005585P 06 August 2019

DESCRIPTION OF WORK:

The work shall be located at Building 26041, located near the intersection of West Ivy Division Ave and Hell on Wheels Ave, Fort Hood Texas. The exact location will be shown by the Contracting Officer. Building(s) will not be occupied during performance of work under this Contract.

The purpose of this project is to renovate TEMF Building 26041.

The following drawings are included as part of the Solicitation.

GENERAL SHEETS

G-101 01 COVER SHEET

G-102 02 INDEX SHEET

G-103 03 ABBREVIATIONS

G-104 04 GENERAL NOTES AND LEGEND

G-105 05 CONTRACTOR STAGING AREA

G-106 06 CONTRACTOR HAUL ROUTE MAP

CIVIL SHEETS

C-100 07 INDEX OF SHEETS, ABBREVIATIONS, AND LEGEND

C-101 08 DEMOLITION PLAN

C-102 09 UTILITY PLAN

C-103 10 STRIPING PLAN

C-104 11 FENCING IMPROVEMENTS

C-301 12 WATER LINE SECTIONS

C-501 13 WATER LINE DETAILS

C-502 14 SWING GATE DETAILS

C-503 15 MISCELLANEOUS DETAILS

STRUCTURAL SHEETS

S-100 16 GENERAL NOTES

S-101 17 FOUNDATION PLAN

S-102 18 SECOND FLOOR FRAMING

S-103 19 CEILING FRAMING

ARCHITECTURAL SHEETS

G-005 20 GENERAL NOTES AND ABBREVIATIONS

AD-101 21 DEMOLITION PLAN - FIRST FLOOR

AD-102 22 FIRST FLOOR AREA A

AD-103 23 FIRST FLOOR AREA B

AD-104 24 DEMOLITION PLAN - SECOND FLOOR

AD-201 25 DEMOLITION ELEVATIONS - EXTERIOR NORTH AND SOUTH

AD-202 26 EXTERIOR ELEVATIONS - EXTERIOR EAST AND WEST

AD-301 27 DEMOLITION BUILDING SECTION

AD-302 28 DEMOLITION BUILDING SECTION

A-101 29 FLOOR PLAN - FIRST FLOOR OVERALL

A-102 30 FLOOR PLAN - FIRST FLOOR AREA A

A-103 31 FLOOR PLAN - FIRST FLOOR AREA B

A-104 32 FLOOR PLAN - SECOND FLOOR OVERALL

A-105 33 FLOOR PLAN - SECOND FLOOR

A-121 34 REFLECTED CEILING PLAN - FIRST FLOOR OVERALL

A-122 35 REFLECTED CEILING PLAN - CORE AND SECOND FLOOR

A-201 36 EXTERIOR ELEVATIONS - NORTH AND SOUTH

A-202 37 EXTERIOR ELEVATIONS - EAST AND WEST

A-301 38 BUILDING SECTIONS

A-302 39 BUILDING SECTIONS

A-311 40 WALL SECTIONS

A-401 41 ENLARGED CORE PLANS AND ELEVATIONS

A-521 42 MILLWORK DETAILS

A-601 43 PARTITION TYPES

A-602 44 SCHEDULE - DOOR AND WINDOW TYPE

I-101 45 FINISH PLAN AND SCHEDULE

MECHANICAL, ELECTRICAL, PLUMBING, AND TELECOMMUNICATION SHEETS

M-001 46 LEGEND

M-101 47 DEMOLITION PLAN - HVAC FIRST FLOOR

M-102 48 FIRST FLOOR HVAC PLAN OVERALL

M-103 49 SECOND FLOOR HVAC PLAN OVERALL

M-601 50 MECHANICAL SCHEDULES

P-001 51 PLUMBING LEGEND SCHEDULES AND GENERAL NOTES

P-101 52 DEMOLITION PLAN - FIRST FLOOR

P-102 53 FIRST FLOOR PLAN OVERALL

P-401 54 PLUMBING ENLARGED PLAN

P-402 55 PLUMBING ENLARGED PLAN

P-501 56 PLUMBING DETAILS

P-601 57 PLUMBING RISER

P-602 58 PLUMBING RISER

EG-001 59 LEGEND

EG-002 60 GENERAL NOTES

ED-101 61 FIRST FLOOR DEMOLITION PLAN - OVERALL

ED-102 62 SECOND FLOOR DEMOLITION PLAN - OVERALL

E-101 63 FIRST FLOOR LIGHTING OVERALL

E-102 64 SECOND FLOOR LIGHTING OVERALL

E-103 65 FIRST FLOOR POWER PLAN OVERALL

E-104 66 SECOND FLOOR POWER PLAN OVERALL

E-105 67 FIRST FLOOR HVAC PLAN - OVERALL

E-106 68 SECOND FLOOR HVAC PLAN - OVERALL

E-501 69 DETAILS

E-602 70 LIGHTING FIXTURE SCHEDULE AND SEQUENCE OF OPERATIONS

E-603 71 ONE LINE DIAGRAM

E-604 72 GROUNDING DIAGRAM

TN-100 73 SYSTEMS OVERVIEW, NOTES, AND SYMBOLS

TND-101 74 DEMOLITION PLAN - FIRST FLOOR

TND-102 75 DEMOLITION PLAN - SECOND FLOOR

TN-101 76 FIRST FLOOR OVERALL

TN-103 77 FIRST FLOOR AREA B

TN-201 78 SECOND FLOOR OVERALL

TN-401 79 COMM ROOMS ENLARGED

TN-601 80 DETAILS

FIRE PROTECTION SHEETS

LS-101 81 LIFE SAFETY PLAN FIRST FLOOR

LS-102 82 LIFE SAFETY PLAN SECOND FLOOR

FP-001 83 GENERAL NOTES AND SYMBOLS

FP-002 84 DESIGN CRITERIA FIRST FLOOR AREA A

FP-003 85 DESIGN CRITERIA FIRST FLOOR AREAB

FP-101 86 FLOOR PLAN - FIRST FLOOR AREA A

FP-102 87 FLOOR PLAN - FIRST FLOOR AREA B

FD-101 88 FIRE SPRINKLER DEMO PLAN

FP-004 89 DESIGN CRITERIA SECOND FLOOR AREA A

FP-005 90 DESIGN CRITERIA SECOND FLOOR AREA B

FP-103 91 FLOOR PLAN - SECOND FLOOR AREA A

FP-104 92 FLOOR PLAN - SECOND FLOOR AREA B

FP-501 93 GENERAL FIRE SPRINKLER DETAILS

FA-001 94 GENERAL NOTES/SYMBOL LEGEND

FA-101 95 FLOOR PLAN - FIRST FLOOR

FA-102 96 FLOOR PLAN - SECOND FLOOR

FA-501 97 FIRE ALARM DETAILS

FA-601 98 FIRE ALARM SCHEDULES AND DIAGRAMS

After award, one set of Adobe PDF contract drawings and PDF specifications, and one set of MicroStation format drawings (if available) will be furnished to the Contractor on CD. Reference publications will not be furnished.

Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

A project construction sign will not be required for this project. Contractor shall keep all permits and other documents required to be on the job site in a 3-ring binder or posed on a bulletin board within the construction area.

PERFORMANCE PERIOD: Barring any contingencies that arise during construction, the Government requires this project be completed within 365 calendar days. An additional 30 days will be added to the project completion dated to account for processing of award. Completion is defined as completion of all contractual obligations.

*******END OF SCOPE OF WORK********

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001 is to provide the Government's response to questions received from industry, correct the project number to AD005585P, Incorporate Revised Technical Exhibit A -Specification, B- Drawings, HAZMAT Survey, and revised renovate TEMF Bldg 26041 Synopsis.

Amendment 0002 is to extend the Bid opening date until 30 July 2019 at 10:00am to allow significant time to review revised documents posted to FBO.gov on 22 July 2019

1. Technical Exhibit A - Specification,

2. Technical Exhibit B - Drawings,

3. Technical Exhibit C - HAZMat Survey,

4. revised Renovate TEMF Bldg 26041 Synopsis.

Amendment 0003 is to extend the Bid opening date to 06 August 2019 at 10:30am.

Amendment 0004 is to extend the Bid opening date to 07 August 2019 at 10:30am, provide Gov’t answer to Questions from Industry, to incorporate missing drawings pages 91 (ED-101) thru 119 (ET-402), and to attach Revised drawings (S-001, A-610, C-101, C-102, C-302, C-502, C-503).

Amendment 0005 corrects the Scope of Work contract performance days to 365 days.

(End of Provision)

(End of Summary of Changes)

File details come from the government source that posted it.