AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to answ ers requests for information (RFIs) from industry, change the number of days to complete w ork from 180 to 240 days, and change the bid opening date to 14 June 2018.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Jun-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9115118B0006

X 9B. DATED (SEE ITEM 11)

08-May-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Jun-2018

CODE

MISSION AND INSTALLATION CONTRACTING

MISSION CONTRACTING OFFICE (MCO)

36000 DARNALL LOOP, ROOM 1300B

FORT HOOD TX 76544-5095

W91151 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9115118B0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 08-Jun-2018 02:00 PM to 14-Jun-

2018 02:00 PM.

The contractor period of performance end date has increased by 60 days from 180 days to 240 days.

The following have been added by full text:

RFI ANSWERS

Request For Information (RFI) Answers:

Question1 : Will the building be occupied and functional during this project? If so, Will the work have to be done in phases? If so, can more time be added to complete the project?

Answer: Yes- Original scope was set at 180 days. The number of days has been amended from 180 to 240 days.

Question 2: Is there existing fire alarm devices that are associated with the MAUs or EFs for this project?

Answer: Units are connected to existing fire alarm devices. New units shall be re-connected.

Question 3: Is there any existing fire suppression that needs removal in order to replace the existing units?

Answer: No.

Question 4: How much gas piping is required to be replaced with each unit?

Answer: Depends on the new unit gas line location. Contractor’s responsibility. The flex connector is the only required gas line replacement.

The following have been modified:

SYNOPSIS

PROJECT SYNOPSIS

REPLACE FRESH AIR FURNACES

Building 88030 Project No. DI012991P

Contract Number: W91151-18-C-XXXX January 8, 2018

DESCRIPTION OF WORK: The purpose of this project is to replace all the fresh air furnaces located in building 88030, and replace several backdraft dampers with automated control dampers.

The following Edited As-Built drawings are included as part of the Solicitation (Technical Exhibit B:

Drawings).

M – 101A M – 101B M – 101C M – 101D M – 101E M – 101F M – 101G M – 101H M – 101I M – 101J M – 501 M – 601

PERFORMANCE PERIOD: Barring any contingencies that arise during construction, the Government requires this project be completed within 240 calendar days. Completion is defined as completion of all contractual obligations.

IDENTIFICATION OF THE PROCUREMENT TEAM:

Contracting Officer (ACO): The Contracting Officer has sole authority to obligate the Government.

Contracting Officer's Representative (COR): The COR is appointed by the Contracting Officer and serves as the Government's technical representative and primary point of contact in the field following contract award. The COR will inspect various phases of work in progress to ensure the 3-phase inspection plan is in place and being adhered to. The COR will perform all inspection and acceptance on behalf of the Government for this project.

Project Manager: The Project Manager developed and reviewed this requirement, and will participate in further developing the project through negotiation of a firm fixed price. The PM will serve as the technical liaison between the Government (fire and safety staff) and the contractor in clarifying work requirements, performance standards, and other technical requirements.

Following contract award, the Project Manager is accessible only through coordination with the

COR.

Design Engineer: Design Engineer developed this requirement, and will participate in further developing and reviewing the project through negotiation of a firm fixed price with the Project Manager. The DE will serve as a technical liaison to the in clarifying work requirements, performance standards, and other technical requirements. Following contract award, the Design Engineer is accessible only through coordination with the COR to the PM.

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 01 - Answers to questions from industry (RFIs); extension of POP days; change in bid opening date.

(End of Summary of Changes)