Headquarters III Corps, Fort Hood Directorate of Public Works (DPW)

Technical Exhibit “C”

AD015813P/AD015793P

REPAIR AREAS B AND D DRAINAGE AT NFH

SPECIFICATIONS

July 3, 2017

Contract No. W91151-17-C-XXXX

Directorate of Public Works Engineering Division

US Army, III Corps 4612 Engineer Dr.

Fort Hood, TX 76544

DPW Specification Jan 11, 2016

DPWSPECS TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 32 01.00 10 1 JAN PROJECT SCHEDULE

01 33 00 1 JAN SUBMITTAL PROCEDURES

01 35 13 1 JAN SPECIAL PROJECT PROCEDURES

01 35 23.00 40 1 JAN OWNER SAFETY REQUIREMENTS

01 35 29 1 JAN SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01 45 01.00 20 1 JAN QUALITY CONTROL (QC)

01 57 20.00 10 1 JAN ENVIRONMENTAL PROTECTION

01 77 00 1 JAN CLOSEOUT PROCEDURES

01 78 23 1 JAN OPERATION AND MAINTENANCE DATA

01 80 00 1 JAN UTILITIES

DIVISION 02 - EXISTING CONDITIONS

02 41 00 10/14 DEMOLITION

MASTER TABLE OF CONTENTS Page 1

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 - EXTERIOR IMPROMENTS

32 12 10 32 12 16 32 13 13.06 32 92 19

BITUMINOUS TACK AND PRIME COATS

HOT-MIX ASPHALT (HMA) FOR ROADS

PORTLAND CEMENT CONCRETE PAVEMENT

SEEDING

DIVISION 33 - UTILITIES

33 01 10.15 33 05 27 33 11 00 33 11 00.11 33 11 00.15 33 11 23 33 12 16.11 33 12 19 33 40 00 33 71 01

DISINFECTING PIPELINES

TRACER WIRE

PIPING AND ACCESSORIES

POLYVINYLE CHLORIDE PIPE

DUCTILE IRON PIPE AND FITTING

NATURAL GAS AND LIQUID PETROLEUM PIPING

GATE VALVES

FIRE HYDRANTS

STORM DRAINAGE UTILITIES

OVERHEAD TRASMISSION AND DISTRIBUTION

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 140 PAGES

01 32 01.00 10 SD-01 Preconstruction Submittals

3.4.2 GInitial Project Schedule

3.4.1 GProgram Project Schedule

3.4.3 GPeriodic Schedule Update

01 35 13 SD-01 Preconstruction Submittals

1.4.7 GSupport Subcontractor Awards

1.4.2 GDigging And Water Use Permits

1.5.3 GStorm Water Prevention Pollution

Plan (SWPPP)

1.5.6 GWater Use Permit

1.4.1 GFort Hood Airfield Access

1.5.4 GTraffic Control Plan

1.5.5 GArmy Radiation Permit

1.5.8 GUtility Metering Permit

GRange Passes

1.5.10.1 GAT Level I Training

1.4.9.4 GOPSEC Training

01 35 23.00 40 SD-01 Preconstruction Submittals

1.3.1 GContractor's Health and Safety

Plan

SD-06 Test Reports

1.14Gas Protection

SD-07 Certificates

1.3.2Protection Plan

1.11License Certificates

01 35 29 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 140 PAGES

01 35 29 GActivity Hazard Analysis

1.13 GCrane Critical Lift Plan

GCrane Operators

GConfined Space Entry Permit

SD-06 Test Reports

Accident Reports

1.11.1Regulatory Citations and

Violations

01 45 01.00 20 SD-01 Preconstruction Submittals

3.1 G3-Key Personal

GQuality Control Plan (QCP)

01 57 20.00 10 SD-01 Preconstruction Submittals

3.4.1Air Permits

3.8.1 GEnvironmental Manager

SD-11 Closeout Submittals

Contractor Hazardous Material

Inventory and Consumption Log

3.4.1 GAir Permits

Refrigerant Equipment Service

Log

Emissions Inventory

Questionnaire for New Sources

3.4.2Emission Inventory

3.9.2Recycle Weight Tickets

3.9.3Construction Waste Tickets

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 140 PAGES

01 77 00 SD-10 Operation and Maintenance

Data

GEquipment/Product Warranty List

SD-11 Closeout Submittals

GCertification of EPA Designated

Items

GForm DD1354 (and Appendix D where applicable)

GVideos

GFinal Operation and Maintenance

Manuals

GFinal Record Drawings

GInventory of Contractor Furnished and Installed Equipment

02 41 00 SD-01 Preconstruction Submittals

GDemolition Plan

GUtility Cut and Cap Plan

SD-07 Certificates

Asbestos and Lead Based Paint

Notification Forms submitted to

Texas Department of State Health

Services

FIO

SD-11 Closeout Submittals

Receipts

FIO

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 140 PAGES

02 82 00 SD-03 Product Data

1.3.8Material Safety Data Sheets

(MSDS) for all materials proposed for transport to the project site

FIO

SD-06 Test Reports

1.5.5Air sampling results

FIO

3.3.3.2Asbestos disposal quantity report

3.2.7.3Clearance sampling

GAsbestos Survey Report showing quantities and locations

SD-07 Certificates

1.3.9Asbestos hazard abatement plan

FIO

1.3.10Testing laboratory

Private qualified person

1.5.4Contractor's license

1.5.2Competent person

1.5.3Worker's license

1.3.11Landfill approval

1.3.3Employee training

Medical certification requirements

1.3.11Waste shipment records

1.3.6Respiratory Protection Program

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 140 PAGES

02 82 00 1.3.11Delivery tickets

1.3.4Notifications

Notifications to Texas

Department of State Health

Services; G

SD-11 Closeout Submittals

1.3.4Notifications

1.3.4Permits and licenses

02 82 18.00 20 SD-06 Test Reports

1.5.4Air sampling results

3.2.8.2Clearance sampling

SD-07 Certificates

1.3.9Mold remediation plan

Private qualified person documentation (Mold assessors, remediators)

1.5.3Contractor's license

Responsible person

1.3.4Notifications

1.3.4Notifications

SD-11 Closeout Submittals

1.3.4Notifications

1.3.4Notifications

02 82 33.13 20 SD-03 Product Data

1.6.4Vacuum Filters

1.6.1Respirators

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 140 PAGES

02 82 33.13 20 SD-06 Test Reports

1.5.2.3sampling results

1.5.2.3Occupational and Environmental

Assessment Data Report

SD-07 Certificates

1.5.1.1 GQualifications of CP

1.5.1.3Testing Laboratory

3.1.1.1Occupant Notification

1.5.1.2 GTraining Certification

GNotification of the

Commencement of LBP Hazard

Abatement activities

1.5.1.4 GThird Party Consultant

Qualifications

1.5.3lead-based paint/paint with lead removal/control plan

1.5.2.6Respiratory Protection Program

1.5.2.7Hazard Communication Program approved hazardous waste treatment, storage, or disposal facility

1.5.2.8Lead Waste Management Plan

3.5.1.1Clearance Certification

SD-11 Closeout Submittals

3.5.2.1hazardous waste manifest

03 30 00 SD-02 Shop Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 140 PAGES

03 30 00 1.4.2.1 GReinforcing steel

SD-05 Design Data

2.3.1 Gmix design

SD-06 Test Reports

3.12.2.2Compressive strength tests

FIO

3.12.2.1Slump Tests

SD-07 Certificates

2.5.1Reinforcing Bars

FIO

04 01 41 SD-03 Product Data

Cleaning and Restoration

Methods

04 20 00 SD-03 Product Data

Shop Drawings

Reinforcing Steel

1.5.1Local/Regional Materials

Masonry Blends being used; to include each type of rock included in blend

Environmental Data

Brick

2.2Concrete Masonry Units (CMU)

2.5Water-Repellant Admixture

SD-04 Samples

2.2Concrete Masonry Units (CMU)

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 140 PAGES

04 20 00 2.1Clay or Shale Brick

SD-08 Manufacturer’s Instructions

2.4.2Masonry Cement

05 12 00 SD-02 Shop Drawings

Fabrication drawings; G

SD-06 Test Reports

2.2Bolts, nuts, and washers

SD-07 Certificates

2.1Steel

2.5Galvanizing

1.4AISC Quality Certification

AISC Fabrication Plant Quality

Certification

05 40 00 SD-02 Shop Drawings

1.5.1Framing Components

SD-03 Product Data

2.1studs,joists

SD-05 Design Data

1.5.2Metal framing calculations

3.1.1Welds

05 50 00 SD-02 Shop Drawings

2.20steel stairs

2.22structural steel door frames

2.9Floor gratings and roof walkways

2.12Handrails

2.13Ladders

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 140 PAGES

05 50 00 3.14Roof hatch

SD-03 Product Data

2.9Floor gratings and roof walkways

2.12Handrails

2.13Ladders

2.20Steel stairs

2.22Structural steel door frames

3.14Roof hatch

06 20 00 SD-03 Product Data

Cabinetry hardware

SD-04 Samples

Cabinetry and couter top

Moldings

2.3Fascias and Trim

07 21 17 SD-03 Product Data

3.3.1Insulation

Vapor retarder

SD-08 Manufacturer’s Instructions

3.3.1Insulation

07 24 00 SD-03 Product Data

2.2Sheathing board

Vapor Barrier

2.6Thermal insulation

Adhesive

2.5Mechanical Fasteners

2.12Accessories

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 140 PAGES

07 24 00 2.7Base coat

2.8Portland cement

2.9Reinforcing fabric

2.10Finish coat

2.13Joint Sealant

Sealant Primer

2.14Bond breaker

2.15Backer Rod

Insulation Board

Warranty

FIO

SD-04 Samples

Sample Boards

SD-07 Certificates

1.4.1Qualifications of EIFS

Manufacturer

1.4.2Qualification of EIFS Installer

Qualification of Sealant

Applicator

SD-08 Manufacturer’s Instructions

3.3Installation

SD-10 Operation and Maintenance

Data

EIFS

07 41 13 SD-02 Shop Drawings

Flashing and Accessories

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 140 PAGES

07 41 13 Gutter/Downspout Assembly

SD-03 Product Data

Roof panels

FACTORY-APPLIED COLOR

FINISH

2.4Accessories

Fasteners

SD-04 Samples

GRoof Panels

SD-06 Test Reports

2.6.2Fire Rating Test Report

2.2Factory Finish and Color

Performance Requirements

SD-08 Manufacturer’s Instructions

INSTALLATION MANUAL

07 55 00 SD-03 Product Data

2.2Insulation Board

Membrane Roofing

Fasteners

Sheet Metal Design Materials

Caulking

Contractors Qualifications

2-Roof Vents

Scuppers and Curbs Designs

Parapet Wall Flashing Designs

Fascia Designs and Colors

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 140 PAGES

07 55 00 SD-04 Samples

GMembrane Roofing

2.2Insulation Board

Fasteners

Fascia

2-Way Roof Vent

SD-08 Manufacturer’s Instructions

Installation

SD-11 Closeout Submittals

Manufacturers Final Inspection

Quality Verification Report

07 57 14 SD-03 Product Data

Polyurethane foam

SD-07 Certificates

GQualification of Manufacturer

GQualification of Applicator

07 60 00 SD-02 Shop Drawings

3.1.27 GFlashing at roof penetrations

07 84 00 SD-03 Product Data

2.1Firestopping Materials

07 92 00 SD-03 Product Data

2.1Sealants

2.4Backstops

08 11 13 SD-03 Product Data

2.1Doors

Frames

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 140 PAGES

08 11 13 2.2Accessories

Weatherstripping

08 11 16 SD-02 Shop Drawings

2.1Doors and frames

SD-08 Manufacturer’s Instructions

2.1Doors and frames

08 14 00 SD-03 Product Data

2.1Doors

2.1.7Fire resistance rating

08 33 23 SD-02 Shop Drawings

2.1Overhead Coiling Doors

1.6Counterbalancing Mechanism

2.3Counterbalancing Mechanism

1.6Manual Door Operators

2.4Manual Door Operators

1.6Electric Door Operators

2.5Electric Door Operators

2.1.4Bottom Bar

1.5Guides

2.3.1Mounting Brackets

2.1.10Overhead Drum

1.6Hood

1.6Painting

1.5Installation Drawings

SD-03 Product Data

2.1Overhead Coiling Doors

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 140 PAGES

08 33 23 2.2Hardware

1.6Counterbalancing Mechanism

2.3Counterbalancing Mechanism

1.6Manual Door Operators

2.4Manual Door Operators

1.6Electric Door Operators

2.5Electric Door Operators

2.6Fire-Rated Door Assembly

SD-05 Design Data

2.1Overhead Coiling Doors

2.2Hardware

1.6Counterbalancing Mechanism

2.3Counterbalancing Mechanism

1.6Manual Door Operators

2.4Manual Door Operators

1.6Electric Door Operators

2.5Electric Door Operators

1.2Fire-Rated Door

SD-10 Operation and Maintenance

Data

1.5Operation and Maintenance

Manuals

1.6Overhead Coiling Door

Assemblies

1.6Materials

1.6Devices

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 140 PAGES

08 33 23 1.6Procedures

1.6Manufacture's Brochures

1.6Parts Lists

3.3.2Cleaning

08 34 19.10 20 SD-02 Shop Drawings

2.1Rolling service doors

Rolling fire doors

SD-03 Product Data

2.1Rolling service doors

2.4.2Motors

2.4.3Controls

SD-08 Manufacturer’s Instructions

2.1Rolling service doors

SD-10 Operation and Maintenance

Data

2.1Rolling service doors

08 36 13 SD-02 Shop Drawings

2.2 GDoors

SD-03 Product Data

2.2 GDoors

2.6 GElectric operators

SD-08 Manufacturer’s Instructions

2.2Doors

SD-10 Operation and Maintenance

Data

2.2 GDoors

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 140 PAGES

08 36 19 SD-02 Shop Drawings

2.2 GDoors

SD-03 Product Data

2.2 GDoors

2.4.1 GMotors

2.4.2 GControls

SD-08 Manufacturer’s Instructions

2.2Doors

SD-10 Operation and Maintenance

Data

2.2 GDoors

08 51 13.00 20 SD-02 Shop Drawings

2.1Windows

Fabrication Drawings

SD-03 Product Data

2.1Windows

2.2.5.1Hardware

2.2.2Weatherstripping

2.2.5Accessories

SD-05 Design Data

Structural calculations for deflection

08 60 45 SD-02 Shop Drawings

3.2Shop Drawings

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 140 PAGES

08 60 45 2.1[SKYLIGHTS][ AND

][TRANSLUCENT PANELS]

1.6Warranty

SD-06 Test Reports

2.1Test Reports

SD-07 Certificates

2.5Systems

1.4Qualifications

08 71 00 SD-02 Shop Drawings

2.3.6Keying system

SD-03 Product Data

2.3Hardware items

SD-11 Closeout Submittals

1.3Key Bitting

08 81 00 SD-02 Shop Drawings

Installation

SD-03 Product Data

Insulating Glass

1.3Glazing Accessories

SD-07 Certificates

Insulating Glass

Laminated Glass

08 91 00 SD-02 Shop Drawings

1.4Wall louvers

1.5Wall louvers

SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 140 PAGES

08 91 00 2.2Metal Wall Louvers

09 29 00 SD-03 Product Data

Cementitious backer units

2.1.1Gypsum Board

2.1.7Accessories

SD-08 Manufacturer’s Instructions

Material Safety Data Sheets

09 30 00 SD-03 Product Data

2.1Tile

Adhesive

SD-04 Samples

2.1Tile

2.3Grout

09 51 00 SD-03 Product Data

Acoustical Ceiling Systems

SD-07 Certificates

Acoustic Ceiling Tiles and

Suspension System

09 65 00 SD-03 Product Data

Resilient Flooring and

Accessories

2.4Adhesives

SD-08 Manufacturer’s Instructions

3.2Surface Preparation

Installation

09 68 00 SD-03 Product Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 140 PAGES

09 68 00 2.1Carpet

3.4Installation

SD-04 Samples

2.1Carpet

SD-07 Certificates

2.1Carpet

09 90 00 SD-03 Product Data

Coating

SD-08 Manufacturer’s Instructions

1.6.2Manufacturer's Material Safety

Data Sheets

10 14 02 SD-03 Product Data

1.3Interior Signage

10 21 13 SD-02 Shop Drawings

GInstallation Drawings

Fabrication Drawings

SD-03 Product Data

2.6Colors And Finishes

2.2Partition Panels and Doors

2.1.3Anchoring Devices and

Fasteners

2.1.5Hardware and Fittings

10 22 13 SD-03 Product Data

1.4Wire mesh partitions

10 26 13 SD-03 Product Data

2.2Corner Guards

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 140 PAGES

10 28 13 SD-03 Product Data

Finishes

Accessory Items

10 44 16 SD-03 Product Data

2.1Fire Extinguishers

Accessories

Cabinets

Wall Brackets

Replacement Parts

SD-07 Certificates

2.1Fire Extinguishers

2.1Manufacturer's Warranty with

Inspection Tag

11 68 13 SD-02 Shop Drawings

Configuration

1.5.5Shop Drawings

Fall Height

SD-03 Product Data

2.2Equipment

1.3.4Equipment Identification

1.6Delivery, Storage and Handling

1.5.1Manufacturer Qualification

2.1Materials

SD-04 Samples

2.1.5Color

SD-06 Test Reports

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 140 PAGES

11 68 13 2.1.3Recycled Plastic

Wood Finishes

SD-07 Certificates

2.1Materials

1.5.1Manufacturer Qualification

1.5.2Installer Qualification

1.5.3Manufacturer's Representative

Substitution

SD-10 Operation and Maintenance

Data

1.8Maintenance Instructions

12 24 13 SD-03 Product Data

2.1Window Shades

1.3Hardware

SD-08 Manufacturer’s Instructions

2.1Window Shades

13 34 19 SD-01 Preconstruction Submittals

1.6.2Manufacturer's Qualifications

SD-02 Shop Drawings

Shop and Detail Drawings

SD-05 Design Data descriptive and technical literature building design analysis

21 12 00 SD-02 Shop Drawings

1.4.4 GStandpipe system

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 140 PAGES

21 12 00 SD-03 Product Data

2.1.1 GPipe and fittings

2.1.1 GMechanical couplings

2.1.2 GPipe hangers and supports

2.1.3 GValves

2.1.9 GFire department connections

2.1.10 GAlarm valves

2.1.11 GWater motor alarms

2.1.12 GPressure switch

2.1.13 GWaterflow detector

2.1.14 GFire hose cabinets

2.1.15 GValve tamper switch

2.1.17 GBackflow preventer

2.2.1 GBuried Pipe and fittings

SD-06 Test Reports

3.8.1 GPreliminary tests

3.8.2 GAcceptance tests

SD-07 Certificates

1.6.1 GQualifications of installer

SD-10 Operation and Maintenance

Data

2.1.10 GAlarm valves

2.1.17 GBackflow preventer

SD-11 Closeout Submittals

1.6.2 GSystem as-built drawings

21 13 00.00 20 SD-02 Shop Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 140 PAGES

21 13 00.00 20 1.4Sprinkler heads and piping system layout

1.4.8Electrical wiring diagrams

SD-03 Product Data

2.2Piping

2.2.4Alarm valves

2.2.8Valves

2.2.5Water motor alarms

2.2.2Sprinkler heads

2.2.7Pipe hangers and supports

2.2.6Flow switch

2.2.13Fire department connections

2.2.14Excess pressure pump

2.2.1Mechanical couplings

2.2.9Backflow Preventer

SD-05 Design Data

1.4Sprinkler system design

SD-06 Test Reports

3.2.1Preliminary tests

SD-07 Certificates

1.6.1Qualifications of installer

SD-10 Operation and Maintenance

Data

2.2.4Alarm valves

2.2.14Excess pressure pump

2.2.9Backflow preventer

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 140 PAGES

21 13 00.00 20 SD-11 Closeout Submittals

1.4.9As-built drawings

21 13 00.00 40 SD-01 Preconstruction Submittals

1.2 GRecord of Existing Conditions

SD-02 Shop Drawings

2.2.3 GSupporting Elements

2.2.4 GFire-Department Connections

2.2.9.1 GFire Alarm System

2.2.8 GSprinkler Heads

2.2.9 GValves

SD-03 Product Data

2.2.1 GUnderground Piping Materials

2.2.2 GAboveground Piping Materials

2.2.9 GValves

2.2.4 GFire-Department Connections

2.2.5 GRiser Alarm Equipment

2.2.6.1 GAir Compressor

2.2.7 GStandpipe Equipment and Fire

Hose Cabinet Stations

2.2.8 GSprinkler Heads

2.3 GMaterials

2.2.3 GSupporting Elements

2.1 GEquipment and Performance

Data

SD-05 Design Data

Part 2 GDesign Analysis and Calculations

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 140 PAGES

21 13 00.00 40 SD-06 Test Reports

3.3.6 GPressure Tests

3.3.3 GSystem Operating Tests

3.3.3 GAir Tests

3.3.3 GValve-Operating Tests

3.3.3 GDrainage Tests

21 13 16.00 20 SD-02 Shop Drawings

1.3.8Sprinkler heads and piping system layout

1.3.8Electrical wiring diagrams

SD-03 Product Data

2.1Piping

2.1.10Valves

2.1.5Water motor alarms

2.1.2Sprinkler heads

2.1.9Pipe hangers and supports

2.1.14Fire department connections

2.1.7Low air pressure supervisory switch

2.1.4Dry pipe valves

2.1.8Air compressor

2.1.1Mechanical couplings

2.1.10.1Backflow Preventers

2.1.6Pressure Switch

SD-05 Design Data

1.3Sprinkler system design

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 140 PAGES

21 13 16.00 20 SD-06 Test Reports

3.2.1Preliminary tests

SD-07 Certificates

1.5.1Qualifications of installer

SD-10 Operation and Maintenance

Data

2.1.4Dry pipe valves

2.1.8Air compressor

SD-11 Closeout Submittals

1.3.9As-built drawings of each system

21 13 18.00 10 SD-02 Shop Drawings

1.4.3 GShop Drawings

3.8As-Built Drawings

SD-03 Product Data

1.4.1 GFire Protection Specialist

1.4.2Installer Qualifications

1.4.1List of Submittals

2.1 GMaterials and Equipment

1.6Spare Parts

3.9 GOnSite Training

SD-05 Design Data

3.3.1Sway Bracing

1.2.1.2 GHydraulic Calculations

2.13.4.1 GStorage Batteries

SD-06 Test Reports

3.7 GPreliminary Tests

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 140 PAGES

21 13 18.00 10 3.8Final Acceptance Tests

SD-07 Certificates

3.2 GInspection by Fire Protection

Specialist

SD-10 Operation and Maintenance

Data

3.9 GOperating and Maintenance

Instructions

21 13 20.00 20 SD-02 Shop Drawings

1.3.1.1 GFire extinguishing system

SD-03 Product Data

2.19.1 GPipe, fittings, and mechanical

couplings

2.1.3 G[Deluge] [Pre-action] valves

2.19.5 GValves

2.11.1 GWater motor alarms

2.1.1 GSprinkler heads

2.16 GMonitor nozzles

2.17 GHose and nozzles

2.19.4 GPipe hangers and supports

2.11.3.1 GPressure switch

2.19.11 GFire department inlet connections

2.12 GTank mounted air compressor

2.12 GAir pressure regulating device

2.3.1 GAir compressor

2.11.4 Gtrouble alarm

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 140 PAGES

21 13 20.00 20 2.2 GDetection devices

2.2.2.1 GStorage batteries

2.11.2 GAlarm bells

2.11.2 GAlarm horns

2.2.1.3 GAnnunciator panel

2.18 GFoam hydrants

2.15.3 GAFFF concentrate storage tanks

2.14 GProportioning equipment

2.13 GAFFF concentrate

2.19.3 GStrainers

2.5 GManual release stations

2.19.12 GBackflow preventers

2.2.1 GControl panel

2.2.2.2 GBattery charger

SD-05 Design Data

1.3.1.2 GHydraulic calculations

1.3.1.2 GPressure discharge graphs or

tables

1.3.1.2 GBattery standby power

requirements calculations

1.3.1.2 GSystem surge analysis

SD-06 Test Reports

2.7 G2-wire smoke detectors

3.8.1 GPreliminary tests

3.8.2 GAcceptance tests

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 140 PAGES

21 13 20.00 20 2.14.1 Gdiaphragm pressure proportioning tanks

SD-07 Certificates

1.5.1 GQualifications of installer

1.3.1.3 GAFFF containment and disposal

plan

2.19.12 GBackflow preventers

SD-10 Operation and Maintenance

Data

2.1.3 G[Deluge] [Pre-action] valves

2.12 GTank mounted air compressor

2.14 GProportioning equipment

2.2.1 GControl panel

2.15.3 GAFFF concentrate storage tanks

2.16 GMonitor nozzles

1.3.1.1 Gfire extinguishing system

SD-11 Closeout Submittals

1.3.1.4 GAs-built drawings for the fire

extinguishing system

21 13 24.00 10 SD-02 Shop Drawings

1.4.3 GDetail Drawings

1.4.1As-built Drawings

SD-03 Product Data

2.1 GMaterials and Equipment

1.5Spare Parts

1.2 GAFFF System

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 140 PAGES

21 13 24.00 10 1.4.2 GInstaller's Qualifications

3.6.4 GPost-discharge Test

Requirements

SD-06 Test Reports

3.6.4Test Reports

SD-07 Certificates

2.1 GMaterials and Equipment

SD-10 Operation and Maintenance

Data

3.8 GOperation and Maintenance

Manuals

21 13 26.00 40 SD-01 Preconstruction Submittals

Part 2 GMaterial, Equipment, and Fixture

Lists

1.4 GRecord of Existing Conditions

SD-02 Shop Drawings

Part 2 GConnection Diagrams

Part 2 GControl Diagrams

1.4 GInstallation Drawings

SD-03 Product Data

Part 2 GEquipment and Performance

Data

Part 2 GEquipment Foundation Data

Part 2 GPiping Materials

2.3.7 GAboveground Piping Systems

Part 2 GValves

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 140 PAGES

21 13 26.00 40 2.3.5 GDetection Systems

Part 2 GAlarms

Part 2 GSprinkler Heads

Part 2 GSupporting Elements

SD-04 Samples

3.1.3 GManufacturer's Standard Color

Charts

SD-05 Design Data

Part 2 GDesign Analysis and Calculations

SD-06 Test Reports

3.2 GPressure Tests

3.2 GSystem Tests

3.2 GOperating Tests

SD-07 Certificates

1.3 GListing of Product Installations

Part 2 GPiping Materials

2.3.7 GAboveground Piping Systems

Part 2 GValves

2.3.5 GDetection Systems

Part 2 GAlarms

Part 2 GAir Compressor

Part 2 GSprinkler Heads

Part 2 GSupporting Elements

SD-10 Operation and Maintenance

Data

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 140 PAGES

21 13 26.00 40 3.4.1 GOperation and Maintenance

Manuals

21 21 01.00 10 SD-02 Shop Drawings

1.3Piping layout

1.3.1Electrical wiring diagrams

SD-03 Product Data

Storage cylinders

Discharge head

Manifolds

2.9Discharge alarm

2.3Pipe and fittings

2.4.3Pipe hangers and supports

2.6Actuating stations

2.6.3Pressure switch

2.6.5Control panel

2.7.1Smoke detectors

2.7.2Heat activated detectors

2.9.2Alarm horns

2.9.3Visual alarms

2.11Dampers

Main and reserve switch

2.9Warning signs

2.6.6.1Storage batteries

2.6.6.2Battery charger

SD-05 Design Data

1.3.2System calculations

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 140 PAGES

21 21 01.00 10 2.6.6.1Calculations substantiating battery capacity

1.3.2Open-area smoke detectors calculations

SD-06 Test Reports

3.5.1Preliminary tests

SD-07 Certificates

1.5.1Qualifications of installer

SD-10 Operation and Maintenance

Data

Discharge head

2.6.5Control panel

21 21 03.00 10 SD-02 Shop Drawings

1.4.3 GInstallation Drawings

SD-03 Product Data

1.4Similar Services

2.1 GStandard Products

3.2 GPreliminary Tests

3.3 GFinal Acceptance Tests

3.4Field Training

SD-06 Test Reports

3.2Preliminary Tests

3.3Final Acceptance Tests

SD-07 Certificates

1.4.2 GInstallation Technician

1.4.3 GInstallation Drawings

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 140 PAGES

21 21 03.00 10 SD-10 Operation and Maintenance

Data

3.4Operation and Maintenance

Instructions

21 30 00 SD-01 Preconstruction Submittals

1.3Fire Pump Installation Related

Submittals

1.7.1 GFire Protection Specialist

SD-02 Shop Drawings

3.3.1 GInstallation Drawings

3.11.2 GAs-Built Drawings

3.3.2 GPiping Layout

3.3.2 GPump Room

SD-03 Product Data

2.1 GCatalog Data

1.6Spare Parts

3.8.2Preliminary Tests

3.8 GField Tests

1.7.6 GManufacturer's Representative

3.11.1 GField Training

3.8.3Army Final Acceptance Test

Navy Formal Inspection and

Tests

SD-06 Test Reports

3.8.2Preliminary Tests

3.8.3Army Final Acceptance Test

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 140 PAGES

21 30 00 SD-07 Certificates

1.7.1Fire Protection Specialist

1.7.2Qualifications of Welders

1.7.3Qualifications of Installer

1.7.4Preliminary Test Certification

1.7.5Final Test Certification

SD-10 Operation and Maintenance

Data

3.11.1Operating and Maintenance

Instructions

2.17Flow Meter

22 00 00 SD-03 Product Data

2.4Fixtures

2.4.1Flush valve water closets

2.4.2Flush valve urinals

Flush tank water closets

2.4.4Wall hung lavatories

2.4.5Countertop lavatories

2.4.6Kitchen sinks

Service sinks

2.4.8Drinking-water coolers

Plastic shower stalls

Plastic bathtub liners

Plastic bathtub wall surrounds

2.10Water heaters

2.12Pumps

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 140 PAGES

22 00 00 Backflow prevention assemblies

2.6.2Shower Faucets

Swimming Pool [and Spa

]Suction Fittings

Pool Water Pump safety vacuum release system

3.4Vibration-Absorbing Features

SD-06 Test Reports

3.8Tests, Flushing and Disinfection

3.8.1.1Test of Backflow Prevention

Assemblies

SD-07 Certificates

Materials and Equipment

SD-10 Operation and Maintenance

Data

3.8.1Plumbing System

22 05 48.00 20 SD-02 Shop Drawings

2.7Inertia bases

2.6Machinery bases

2.6Platforms

2.6Rails

2.6Saddles

SD-03 Product Data

2.3Isolators

2.8Flexible connectors

2.9Flexible duct connectors

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 140 PAGES

22 05 48.00 20 2.11Pipe guides

2.10Seismic snubbers

3.1.3Vertical stops

2.12Thrust restraints

2.7Inertia bases

2.6Machinery bases

3.1.13Machinery foundations and subbases

2.6Platforms

2.6Rails

2.6Saddles

1.4.2Machinery manufacturer's sound data

SD-05 Design Data

2.7Inertia bases

2.6Machinery bases

2.6Platforms

2.6Rails

2.6Saddles

1.4.3machinery

1.4.4machinery over 300 pounds

SD-06 Test Reports

2.10Seismic snubbers

3.2.3.1Equipment vibration tests

3.2.3.2Equipment sound level tests

2.4Protected spring isolators

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 140 PAGES

22 05 48.00 20 SD-08 Manufacturer’s Instructions

3.1.1Vibration and noise isolation components

2.13Seismic protection components

22 07 19.00 40 SD-03 Product Data

2.3Adhesives

2.3Coatings

Insulating Cement

2.3Insulation Materials

2.3Jacketing

2.3Tape

SD-08 Manufacturer’s Instructions

1.2Installation Manual

22 14 29.00 40 SD-03 Product Data

2.1Manufacturer's Catalog Data

2.2.1Pump Performance Curve

2.2.1Pump and Motor Specifications

1.5Spare Parts

1.5Special Tools

2.2Wet-Pit Sump Pumps

2.3Submersible Pumps

2.3Accessories

SD-06 Test Reports

3.2.2Hydrostatic Leak

3.2.2Static Heads

3.2.2Pump Flow Capacity

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 39 OF 140 PAGES

22 14 29.00 40 SD-07 Certificates

Manufacturer's Certification of

Bearing Life

SD-08 Manufacturer’s Instructions

2.1Manufacturer's Installation

Instructions

2.1Vibration Specifications

22 15 14.00 40 SD-03 Product Data

1.4Equipment and Performance

Data

Underground Piping Materials

2.1Aboveground Piping Materials

2.2Piping Specialties

2.5Supporting Elements

Air Compressors

2.3Valves

3.1.1Accessories

2.4Miscellaneous Materials

3.1.5Vibration Isolation

SD-06 Test Reports

3.2.1Hydrostatic Testing

3.2Compressed Air Systems Testing

3.2.1Valve-Operating Tests

3.2.1Drainage Tests

3.2.1Pneumatic Testing

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 40 OF 140 PAGES

22 15 14.00 40 SD-10 Operation and Maintenance

Data

1.5Operation and Maintenance

Manuals

22 31 00 SD-02 Shop Drawings

3.2Installation

SD-03 Product Data

2.2Softening Equipment

1.4Spare Parts

3.3.2Field Instructions

SD-06 Test Reports

2.2Softening Equipment

3.4.2Piping

SD-10 Operation and Maintenance

Data

3.3.2Operating and Maintenance

Instructions

23 00 00 SD-03 Product Data

2.8.1.1Metallic Flexible Duct

Insulated Nonmetallic Flexible

Duct Runouts

Duct Connectors

2.8.2Duct Access Doors

2.8.3Fire Dampers

2.8.4Manual Balancing Dampers

Automatic Smoke-Fire Dampers

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 41 OF 140 PAGES

23 00 00 Automatic Smoke Dampers

2.8.8Sound Attenuation Equipment

2.8.8.2Acoustical Duct Liner

2.8.9.1Diffusers

Registers and Grilles

2.8.10Louvers

2.8.11Air Vents, Penthouses, and

Goosenecks

2.9.1.1Centrifugal Fans

2.9.1.2In-Line Centrifugal Fans

2.9.1.3Axial Flow Fans

2.9.1.4Panel Type Power Wall

Ventilators

2.9.1.5Centrifugal Type Power Wall

Ventilators

2.9.1.6Centrifugal Type Power Roof

Ventilators

2.9.1.7Propeller Type Power Roof

Ventilators

2.9.1.8Air-Curtain Fans

2.9.1.9Ceiling Exhaust Fans

2.10Air Handling Units

2.11.1Room Fan-Coil Units

Coil Induction Units

2.11.2.1Constant Volume, Single Duct

Terminal Units

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 42 OF 140 PAGES

23 00 00 2.11.2.2Variable Volume, Single Duct

Terminal Units

2.11.2.3Variable Volume, Single Duct, Fan-Powered Terminal Units

Dual Duct Terminal Units

Ceiling Induction Terminal Units

2.11.2.5Reheat Units

2.11.3Unit Ventilators

2.12Energy Recovery Devices

1.4.5Test Procedures

Diagrams

SD-06 Test Reports

3.11Performance Tests

3.9Damper Acceptance Test

SD-08 Manufacturer’s Instructions

3.2Manufacturer's Installation

Instructions

3.13.2Operation and Maintenance

Training

SD-10 Operation and Maintenance

Data

3.13.1Operation and Maintenance

Manuals

2.8.3Fire Dampers

2.8.4Manual Balancing Dampers

Automatic Smoke-Fire Dampers

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 43 OF 140 PAGES

23 00 00 Automatic Smoke Dampers

2.9.1.1Centrifugal Fans

2.9.1.2In-Line Centrifugal Fans

2.9.1.3Axial Flow Fans

2.9.1.4Panel Type Power Wall

Ventilators

2.9.1.5Centrifugal Type Power Wall

Ventilators

2.9.1.6Centrifugal Type Power Roof

Ventilators

2.9.1.7Propeller Type Power Roof

Ventilators

2.9.1.8Air-Curtain Fans

2.9.1.9Ceiling Exhaust Fans

2.10Air Handling Units

2.11.1Room Fan-Coil Units

Coil Induction Units

2.11.2.1Constant Volume, Single Duct

Terminal Units

2.11.2.2Variable Volume, Single Duct

Terminal Units

2.11.2.3Variable Volume, Single Duct, Fan-Powered Terminal Units

Dual Duct Terminal Units

Ceiling Induction Terminal Units

2.11.2.5Reheat Units

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 44 OF 140 PAGES

23 00 00 2.11.3Unit Ventilators

2.12Energy Recovery Devices

23 01 30.41 SD-01 Preconstruction Submittals

3.2.1Record of Existing Conditions

3.2.2Coordination Plan

1.4.1NADCA Firm

1.4.1NADCA Team Assistants

1.4.1NADCA Air System Cleaning

Specialist (ASCS)

1.4.1NADCA Supervisor…