Headquarters III Corps, Fort Hood Directorate of Public Works (DPW)
Technical Exhibit “C”
AD015813P/AD015793P
REPAIR AREAS B AND D DRAINAGE AT NFH
SPECIFICATIONS
July 3, 2017
Contract No. W91151-17-C-XXXX
Directorate of Public Works Engineering Division
US Army, III Corps 4612 Engineer Dr.
Fort Hood, TX 76544
DPW Specification Jan 11, 2016
DPWSPECS TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 32 01.00 10 1 JAN PROJECT SCHEDULE
01 33 00 1 JAN SUBMITTAL PROCEDURES
01 35 13 1 JAN SPECIAL PROJECT PROCEDURES
01 35 23.00 40 1 JAN OWNER SAFETY REQUIREMENTS
01 35 29 1 JAN SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
01 45 01.00 20 1 JAN QUALITY CONTROL (QC)
01 57 20.00 10 1 JAN ENVIRONMENTAL PROTECTION
01 77 00 1 JAN CLOSEOUT PROCEDURES
01 78 23 1 JAN OPERATION AND MAINTENANCE DATA
01 80 00 1 JAN UTILITIES
DIVISION 02 - EXISTING CONDITIONS
02 41 00 10/14 DEMOLITION
MASTER TABLE OF CONTENTS Page 1
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
DIVISION 32 - EXTERIOR IMPROMENTS
32 12 10 32 12 16 32 13 13.06 32 92 19
BITUMINOUS TACK AND PRIME COATS
HOT-MIX ASPHALT (HMA) FOR ROADS
PORTLAND CEMENT CONCRETE PAVEMENT
SEEDING
DIVISION 33 - UTILITIES
33 01 10.15 33 05 27 33 11 00 33 11 00.11 33 11 00.15 33 11 23 33 12 16.11 33 12 19 33 40 00 33 71 01
DISINFECTING PIPELINES
TRACER WIRE
PIPING AND ACCESSORIES
POLYVINYLE CHLORIDE PIPE
DUCTILE IRON PIPE AND FITTING
NATURAL GAS AND LIQUID PETROLEUM PIPING
GATE VALVES
FIRE HYDRANTS
STORM DRAINAGE UTILITIES
OVERHEAD TRASMISSION AND DISTRIBUTION
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 140 PAGES
01 32 01.00 10 SD-01 Preconstruction Submittals
3.4.2 GInitial Project Schedule
3.4.1 GProgram Project Schedule
3.4.3 GPeriodic Schedule Update
01 35 13 SD-01 Preconstruction Submittals
1.4.7 GSupport Subcontractor Awards
1.4.2 GDigging And Water Use Permits
1.5.3 GStorm Water Prevention Pollution
Plan (SWPPP)
1.5.6 GWater Use Permit
1.4.1 GFort Hood Airfield Access
1.5.4 GTraffic Control Plan
1.5.5 GArmy Radiation Permit
1.5.8 GUtility Metering Permit
GRange Passes
1.5.10.1 GAT Level I Training
1.4.9.4 GOPSEC Training
01 35 23.00 40 SD-01 Preconstruction Submittals
1.3.1 GContractor's Health and Safety
Plan
SD-06 Test Reports
1.14Gas Protection
SD-07 Certificates
1.3.2Protection Plan
1.11License Certificates
01 35 29 SD-01 Preconstruction Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 140 PAGES
01 35 29 GActivity Hazard Analysis
1.13 GCrane Critical Lift Plan
GCrane Operators
GConfined Space Entry Permit
SD-06 Test Reports
Accident Reports
1.11.1Regulatory Citations and
Violations
01 45 01.00 20 SD-01 Preconstruction Submittals
3.1 G3-Key Personal
GQuality Control Plan (QCP)
01 57 20.00 10 SD-01 Preconstruction Submittals
3.4.1Air Permits
3.8.1 GEnvironmental Manager
SD-11 Closeout Submittals
Contractor Hazardous Material
Inventory and Consumption Log
3.4.1 GAir Permits
Refrigerant Equipment Service
Log
Emissions Inventory
Questionnaire for New Sources
3.4.2Emission Inventory
3.9.2Recycle Weight Tickets
3.9.3Construction Waste Tickets
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 140 PAGES
01 77 00 SD-10 Operation and Maintenance
Data
GEquipment/Product Warranty List
SD-11 Closeout Submittals
GCertification of EPA Designated
Items
GForm DD1354 (and Appendix D where applicable)
GVideos
GFinal Operation and Maintenance
Manuals
GFinal Record Drawings
GInventory of Contractor Furnished and Installed Equipment
02 41 00 SD-01 Preconstruction Submittals
GDemolition Plan
GUtility Cut and Cap Plan
SD-07 Certificates
Asbestos and Lead Based Paint
Notification Forms submitted to
Texas Department of State Health
Services
FIO
SD-11 Closeout Submittals
Receipts
FIO
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 140 PAGES
02 82 00 SD-03 Product Data
1.3.8Material Safety Data Sheets
(MSDS) for all materials proposed for transport to the project site
FIO
SD-06 Test Reports
1.5.5Air sampling results
FIO
3.3.3.2Asbestos disposal quantity report
3.2.7.3Clearance sampling
GAsbestos Survey Report showing quantities and locations
SD-07 Certificates
1.3.9Asbestos hazard abatement plan
FIO
1.3.10Testing laboratory
Private qualified person
1.5.4Contractor's license
1.5.2Competent person
1.5.3Worker's license
1.3.11Landfill approval
1.3.3Employee training
Medical certification requirements
1.3.11Waste shipment records
1.3.6Respiratory Protection Program
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 140 PAGES
02 82 00 1.3.11Delivery tickets
1.3.4Notifications
Notifications to Texas
Department of State Health
Services; G
SD-11 Closeout Submittals
1.3.4Notifications
1.3.4Permits and licenses
02 82 18.00 20 SD-06 Test Reports
1.5.4Air sampling results
3.2.8.2Clearance sampling
SD-07 Certificates
1.3.9Mold remediation plan
Private qualified person documentation (Mold assessors, remediators)
1.5.3Contractor's license
Responsible person
1.3.4Notifications
1.3.4Notifications
SD-11 Closeout Submittals
1.3.4Notifications
1.3.4Notifications
02 82 33.13 20 SD-03 Product Data
1.6.4Vacuum Filters
1.6.1Respirators
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 140 PAGES
02 82 33.13 20 SD-06 Test Reports
1.5.2.3sampling results
1.5.2.3Occupational and Environmental
Assessment Data Report
SD-07 Certificates
1.5.1.1 GQualifications of CP
1.5.1.3Testing Laboratory
3.1.1.1Occupant Notification
1.5.1.2 GTraining Certification
GNotification of the
Commencement of LBP Hazard
Abatement activities
1.5.1.4 GThird Party Consultant
Qualifications
1.5.3lead-based paint/paint with lead removal/control plan
1.5.2.6Respiratory Protection Program
1.5.2.7Hazard Communication Program approved hazardous waste treatment, storage, or disposal facility
1.5.2.8Lead Waste Management Plan
3.5.1.1Clearance Certification
SD-11 Closeout Submittals
3.5.2.1hazardous waste manifest
03 30 00 SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 140 PAGES
03 30 00 1.4.2.1 GReinforcing steel
SD-05 Design Data
2.3.1 Gmix design
SD-06 Test Reports
3.12.2.2Compressive strength tests
FIO
3.12.2.1Slump Tests
SD-07 Certificates
2.5.1Reinforcing Bars
FIO
04 01 41 SD-03 Product Data
Cleaning and Restoration
Methods
04 20 00 SD-03 Product Data
Shop Drawings
Reinforcing Steel
1.5.1Local/Regional Materials
Masonry Blends being used; to include each type of rock included in blend
Environmental Data
Brick
2.2Concrete Masonry Units (CMU)
2.5Water-Repellant Admixture
SD-04 Samples
2.2Concrete Masonry Units (CMU)
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 140 PAGES
04 20 00 2.1Clay or Shale Brick
SD-08 Manufacturer’s Instructions
2.4.2Masonry Cement
05 12 00 SD-02 Shop Drawings
Fabrication drawings; G
SD-06 Test Reports
2.2Bolts, nuts, and washers
SD-07 Certificates
2.1Steel
2.5Galvanizing
1.4AISC Quality Certification
AISC Fabrication Plant Quality
Certification
05 40 00 SD-02 Shop Drawings
1.5.1Framing Components
SD-03 Product Data
2.1studs,joists
SD-05 Design Data
1.5.2Metal framing calculations
3.1.1Welds
05 50 00 SD-02 Shop Drawings
2.20steel stairs
2.22structural steel door frames
2.9Floor gratings and roof walkways
2.12Handrails
2.13Ladders
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 140 PAGES
05 50 00 3.14Roof hatch
SD-03 Product Data
2.9Floor gratings and roof walkways
2.12Handrails
2.13Ladders
2.20Steel stairs
2.22Structural steel door frames
3.14Roof hatch
06 20 00 SD-03 Product Data
Cabinetry hardware
SD-04 Samples
Cabinetry and couter top
Moldings
2.3Fascias and Trim
07 21 17 SD-03 Product Data
3.3.1Insulation
Vapor retarder
SD-08 Manufacturer’s Instructions
3.3.1Insulation
07 24 00 SD-03 Product Data
2.2Sheathing board
Vapor Barrier
2.6Thermal insulation
Adhesive
2.5Mechanical Fasteners
2.12Accessories
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 140 PAGES
07 24 00 2.7Base coat
2.8Portland cement
2.9Reinforcing fabric
2.10Finish coat
2.13Joint Sealant
Sealant Primer
2.14Bond breaker
2.15Backer Rod
Insulation Board
Warranty
FIO
SD-04 Samples
Sample Boards
SD-07 Certificates
1.4.1Qualifications of EIFS
Manufacturer
1.4.2Qualification of EIFS Installer
Qualification of Sealant
Applicator
SD-08 Manufacturer’s Instructions
3.3Installation
SD-10 Operation and Maintenance
Data
EIFS
07 41 13 SD-02 Shop Drawings
Flashing and Accessories
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 140 PAGES
07 41 13 Gutter/Downspout Assembly
SD-03 Product Data
Roof panels
FACTORY-APPLIED COLOR
FINISH
2.4Accessories
Fasteners
SD-04 Samples
GRoof Panels
SD-06 Test Reports
2.6.2Fire Rating Test Report
2.2Factory Finish and Color
Performance Requirements
SD-08 Manufacturer’s Instructions
INSTALLATION MANUAL
07 55 00 SD-03 Product Data
2.2Insulation Board
Membrane Roofing
Fasteners
Sheet Metal Design Materials
Caulking
Contractors Qualifications
2-Roof Vents
Scuppers and Curbs Designs
Parapet Wall Flashing Designs
Fascia Designs and Colors
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 140 PAGES
07 55 00 SD-04 Samples
GMembrane Roofing
2.2Insulation Board
Fasteners
Fascia
2-Way Roof Vent
SD-08 Manufacturer’s Instructions
Installation
SD-11 Closeout Submittals
Manufacturers Final Inspection
Quality Verification Report
07 57 14 SD-03 Product Data
Polyurethane foam
SD-07 Certificates
GQualification of Manufacturer
GQualification of Applicator
07 60 00 SD-02 Shop Drawings
3.1.27 GFlashing at roof penetrations
07 84 00 SD-03 Product Data
2.1Firestopping Materials
07 92 00 SD-03 Product Data
2.1Sealants
2.4Backstops
08 11 13 SD-03 Product Data
2.1Doors
Frames
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 140 PAGES
08 11 13 2.2Accessories
Weatherstripping
08 11 16 SD-02 Shop Drawings
2.1Doors and frames
SD-08 Manufacturer’s Instructions
2.1Doors and frames
08 14 00 SD-03 Product Data
2.1Doors
2.1.7Fire resistance rating
08 33 23 SD-02 Shop Drawings
2.1Overhead Coiling Doors
1.6Counterbalancing Mechanism
2.3Counterbalancing Mechanism
1.6Manual Door Operators
2.4Manual Door Operators
1.6Electric Door Operators
2.5Electric Door Operators
2.1.4Bottom Bar
1.5Guides
2.3.1Mounting Brackets
2.1.10Overhead Drum
1.6Hood
1.6Painting
1.5Installation Drawings
SD-03 Product Data
2.1Overhead Coiling Doors
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 140 PAGES
08 33 23 2.2Hardware
1.6Counterbalancing Mechanism
2.3Counterbalancing Mechanism
1.6Manual Door Operators
2.4Manual Door Operators
1.6Electric Door Operators
2.5Electric Door Operators
2.6Fire-Rated Door Assembly
SD-05 Design Data
2.1Overhead Coiling Doors
2.2Hardware
1.6Counterbalancing Mechanism
2.3Counterbalancing Mechanism
1.6Manual Door Operators
2.4Manual Door Operators
1.6Electric Door Operators
2.5Electric Door Operators
1.2Fire-Rated Door
SD-10 Operation and Maintenance
Data
1.5Operation and Maintenance
Manuals
1.6Overhead Coiling Door
Assemblies
1.6Materials
1.6Devices
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 140 PAGES
08 33 23 1.6Procedures
1.6Manufacture's Brochures
1.6Parts Lists
3.3.2Cleaning
08 34 19.10 20 SD-02 Shop Drawings
2.1Rolling service doors
Rolling fire doors
SD-03 Product Data
2.1Rolling service doors
2.4.2Motors
2.4.3Controls
SD-08 Manufacturer’s Instructions
2.1Rolling service doors
SD-10 Operation and Maintenance
Data
2.1Rolling service doors
08 36 13 SD-02 Shop Drawings
2.2 GDoors
SD-03 Product Data
2.2 GDoors
2.6 GElectric operators
SD-08 Manufacturer’s Instructions
2.2Doors
SD-10 Operation and Maintenance
Data
2.2 GDoors
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 140 PAGES
08 36 19 SD-02 Shop Drawings
2.2 GDoors
SD-03 Product Data
2.2 GDoors
2.4.1 GMotors
2.4.2 GControls
SD-08 Manufacturer’s Instructions
2.2Doors
SD-10 Operation and Maintenance
Data
2.2 GDoors
08 51 13.00 20 SD-02 Shop Drawings
2.1Windows
Fabrication Drawings
SD-03 Product Data
2.1Windows
2.2.5.1Hardware
2.2.2Weatherstripping
2.2.5Accessories
SD-05 Design Data
Structural calculations for deflection
08 60 45 SD-02 Shop Drawings
3.2Shop Drawings
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 140 PAGES
08 60 45 2.1[SKYLIGHTS][ AND
][TRANSLUCENT PANELS]
1.6Warranty
SD-06 Test Reports
2.1Test Reports
SD-07 Certificates
2.5Systems
1.4Qualifications
08 71 00 SD-02 Shop Drawings
2.3.6Keying system
SD-03 Product Data
2.3Hardware items
SD-11 Closeout Submittals
1.3Key Bitting
08 81 00 SD-02 Shop Drawings
Installation
SD-03 Product Data
Insulating Glass
1.3Glazing Accessories
SD-07 Certificates
Insulating Glass
Laminated Glass
08 91 00 SD-02 Shop Drawings
1.4Wall louvers
1.5Wall louvers
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 140 PAGES
08 91 00 2.2Metal Wall Louvers
09 29 00 SD-03 Product Data
Cementitious backer units
2.1.1Gypsum Board
2.1.7Accessories
SD-08 Manufacturer’s Instructions
Material Safety Data Sheets
09 30 00 SD-03 Product Data
2.1Tile
Adhesive
SD-04 Samples
2.1Tile
2.3Grout
09 51 00 SD-03 Product Data
Acoustical Ceiling Systems
SD-07 Certificates
Acoustic Ceiling Tiles and
Suspension System
09 65 00 SD-03 Product Data
Resilient Flooring and
Accessories
2.4Adhesives
SD-08 Manufacturer’s Instructions
3.2Surface Preparation
Installation
09 68 00 SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 140 PAGES
09 68 00 2.1Carpet
3.4Installation
SD-04 Samples
2.1Carpet
SD-07 Certificates
2.1Carpet
09 90 00 SD-03 Product Data
Coating
SD-08 Manufacturer’s Instructions
1.6.2Manufacturer's Material Safety
Data Sheets
10 14 02 SD-03 Product Data
1.3Interior Signage
10 21 13 SD-02 Shop Drawings
GInstallation Drawings
Fabrication Drawings
SD-03 Product Data
2.6Colors And Finishes
2.2Partition Panels and Doors
2.1.3Anchoring Devices and
Fasteners
2.1.5Hardware and Fittings
10 22 13 SD-03 Product Data
1.4Wire mesh partitions
10 26 13 SD-03 Product Data
2.2Corner Guards
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 140 PAGES
10 28 13 SD-03 Product Data
Finishes
Accessory Items
10 44 16 SD-03 Product Data
2.1Fire Extinguishers
Accessories
Cabinets
Wall Brackets
Replacement Parts
SD-07 Certificates
2.1Fire Extinguishers
2.1Manufacturer's Warranty with
Inspection Tag
11 68 13 SD-02 Shop Drawings
Configuration
1.5.5Shop Drawings
Fall Height
SD-03 Product Data
2.2Equipment
1.3.4Equipment Identification
1.6Delivery, Storage and Handling
1.5.1Manufacturer Qualification
2.1Materials
SD-04 Samples
2.1.5Color
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 140 PAGES
11 68 13 2.1.3Recycled Plastic
Wood Finishes
SD-07 Certificates
2.1Materials
1.5.1Manufacturer Qualification
1.5.2Installer Qualification
1.5.3Manufacturer's Representative
Substitution
SD-10 Operation and Maintenance
Data
1.8Maintenance Instructions
12 24 13 SD-03 Product Data
2.1Window Shades
1.3Hardware
SD-08 Manufacturer’s Instructions
2.1Window Shades
13 34 19 SD-01 Preconstruction Submittals
1.6.2Manufacturer's Qualifications
SD-02 Shop Drawings
Shop and Detail Drawings
SD-05 Design Data descriptive and technical literature building design analysis
21 12 00 SD-02 Shop Drawings
1.4.4 GStandpipe system
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 140 PAGES
21 12 00 SD-03 Product Data
2.1.1 GPipe and fittings
2.1.1 GMechanical couplings
2.1.2 GPipe hangers and supports
2.1.3 GValves
2.1.9 GFire department connections
2.1.10 GAlarm valves
2.1.11 GWater motor alarms
2.1.12 GPressure switch
2.1.13 GWaterflow detector
2.1.14 GFire hose cabinets
2.1.15 GValve tamper switch
2.1.17 GBackflow preventer
2.2.1 GBuried Pipe and fittings
SD-06 Test Reports
3.8.1 GPreliminary tests
3.8.2 GAcceptance tests
SD-07 Certificates
1.6.1 GQualifications of installer
SD-10 Operation and Maintenance
Data
2.1.10 GAlarm valves
2.1.17 GBackflow preventer
SD-11 Closeout Submittals
1.6.2 GSystem as-built drawings
21 13 00.00 20 SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 140 PAGES
21 13 00.00 20 1.4Sprinkler heads and piping system layout
1.4.8Electrical wiring diagrams
SD-03 Product Data
2.2Piping
2.2.4Alarm valves
2.2.8Valves
2.2.5Water motor alarms
2.2.2Sprinkler heads
2.2.7Pipe hangers and supports
2.2.6Flow switch
2.2.13Fire department connections
2.2.14Excess pressure pump
2.2.1Mechanical couplings
2.2.9Backflow Preventer
SD-05 Design Data
1.4Sprinkler system design
SD-06 Test Reports
3.2.1Preliminary tests
SD-07 Certificates
1.6.1Qualifications of installer
SD-10 Operation and Maintenance
Data
2.2.4Alarm valves
2.2.14Excess pressure pump
2.2.9Backflow preventer
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 140 PAGES
21 13 00.00 20 SD-11 Closeout Submittals
1.4.9As-built drawings
21 13 00.00 40 SD-01 Preconstruction Submittals
1.2 GRecord of Existing Conditions
SD-02 Shop Drawings
2.2.3 GSupporting Elements
2.2.4 GFire-Department Connections
2.2.9.1 GFire Alarm System
2.2.8 GSprinkler Heads
2.2.9 GValves
SD-03 Product Data
2.2.1 GUnderground Piping Materials
2.2.2 GAboveground Piping Materials
2.2.9 GValves
2.2.4 GFire-Department Connections
2.2.5 GRiser Alarm Equipment
2.2.6.1 GAir Compressor
2.2.7 GStandpipe Equipment and Fire
Hose Cabinet Stations
2.2.8 GSprinkler Heads
2.3 GMaterials
2.2.3 GSupporting Elements
2.1 GEquipment and Performance
Data
SD-05 Design Data
Part 2 GDesign Analysis and Calculations
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 140 PAGES
21 13 00.00 40 SD-06 Test Reports
3.3.6 GPressure Tests
3.3.3 GSystem Operating Tests
3.3.3 GAir Tests
3.3.3 GValve-Operating Tests
3.3.3 GDrainage Tests
21 13 16.00 20 SD-02 Shop Drawings
1.3.8Sprinkler heads and piping system layout
1.3.8Electrical wiring diagrams
SD-03 Product Data
2.1Piping
2.1.10Valves
2.1.5Water motor alarms
2.1.2Sprinkler heads
2.1.9Pipe hangers and supports
2.1.14Fire department connections
2.1.7Low air pressure supervisory switch
2.1.4Dry pipe valves
2.1.8Air compressor
2.1.1Mechanical couplings
2.1.10.1Backflow Preventers
2.1.6Pressure Switch
SD-05 Design Data
1.3Sprinkler system design
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 140 PAGES
21 13 16.00 20 SD-06 Test Reports
3.2.1Preliminary tests
SD-07 Certificates
1.5.1Qualifications of installer
SD-10 Operation and Maintenance
Data
2.1.4Dry pipe valves
2.1.8Air compressor
SD-11 Closeout Submittals
1.3.9As-built drawings of each system
21 13 18.00 10 SD-02 Shop Drawings
1.4.3 GShop Drawings
3.8As-Built Drawings
SD-03 Product Data
1.4.1 GFire Protection Specialist
1.4.2Installer Qualifications
1.4.1List of Submittals
2.1 GMaterials and Equipment
1.6Spare Parts
3.9 GOnSite Training
SD-05 Design Data
3.3.1Sway Bracing
1.2.1.2 GHydraulic Calculations
2.13.4.1 GStorage Batteries
SD-06 Test Reports
3.7 GPreliminary Tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 140 PAGES
21 13 18.00 10 3.8Final Acceptance Tests
SD-07 Certificates
3.2 GInspection by Fire Protection
Specialist
SD-10 Operation and Maintenance
Data
3.9 GOperating and Maintenance
Instructions
21 13 20.00 20 SD-02 Shop Drawings
1.3.1.1 GFire extinguishing system
SD-03 Product Data
2.19.1 GPipe, fittings, and mechanical
couplings
2.1.3 G[Deluge] [Pre-action] valves
2.19.5 GValves
2.11.1 GWater motor alarms
2.1.1 GSprinkler heads
2.16 GMonitor nozzles
2.17 GHose and nozzles
2.19.4 GPipe hangers and supports
2.11.3.1 GPressure switch
2.19.11 GFire department inlet connections
2.12 GTank mounted air compressor
2.12 GAir pressure regulating device
2.3.1 GAir compressor
2.11.4 Gtrouble alarm
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 140 PAGES
21 13 20.00 20 2.2 GDetection devices
2.2.2.1 GStorage batteries
2.11.2 GAlarm bells
2.11.2 GAlarm horns
2.2.1.3 GAnnunciator panel
2.18 GFoam hydrants
2.15.3 GAFFF concentrate storage tanks
2.14 GProportioning equipment
2.13 GAFFF concentrate
2.19.3 GStrainers
2.5 GManual release stations
2.19.12 GBackflow preventers
2.2.1 GControl panel
2.2.2.2 GBattery charger
SD-05 Design Data
1.3.1.2 GHydraulic calculations
1.3.1.2 GPressure discharge graphs or
tables
1.3.1.2 GBattery standby power
requirements calculations
1.3.1.2 GSystem surge analysis
SD-06 Test Reports
2.7 G2-wire smoke detectors
3.8.1 GPreliminary tests
3.8.2 GAcceptance tests
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 140 PAGES
21 13 20.00 20 2.14.1 Gdiaphragm pressure proportioning tanks
SD-07 Certificates
1.5.1 GQualifications of installer
1.3.1.3 GAFFF containment and disposal
plan
2.19.12 GBackflow preventers
SD-10 Operation and Maintenance
Data
2.1.3 G[Deluge] [Pre-action] valves
2.12 GTank mounted air compressor
2.14 GProportioning equipment
2.2.1 GControl panel
2.15.3 GAFFF concentrate storage tanks
2.16 GMonitor nozzles
1.3.1.1 Gfire extinguishing system
SD-11 Closeout Submittals
1.3.1.4 GAs-built drawings for the fire
extinguishing system
21 13 24.00 10 SD-02 Shop Drawings
1.4.3 GDetail Drawings
1.4.1As-built Drawings
SD-03 Product Data
2.1 GMaterials and Equipment
1.5Spare Parts
1.2 GAFFF System
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 140 PAGES
21 13 24.00 10 1.4.2 GInstaller's Qualifications
3.6.4 GPost-discharge Test
Requirements
SD-06 Test Reports
3.6.4Test Reports
SD-07 Certificates
2.1 GMaterials and Equipment
SD-10 Operation and Maintenance
Data
3.8 GOperation and Maintenance
Manuals
21 13 26.00 40 SD-01 Preconstruction Submittals
Part 2 GMaterial, Equipment, and Fixture
Lists
1.4 GRecord of Existing Conditions
SD-02 Shop Drawings
Part 2 GConnection Diagrams
Part 2 GControl Diagrams
1.4 GInstallation Drawings
SD-03 Product Data
Part 2 GEquipment and Performance
Data
Part 2 GEquipment Foundation Data
Part 2 GPiping Materials
2.3.7 GAboveground Piping Systems
Part 2 GValves
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 140 PAGES
21 13 26.00 40 2.3.5 GDetection Systems
Part 2 GAlarms
Part 2 GSprinkler Heads
Part 2 GSupporting Elements
SD-04 Samples
3.1.3 GManufacturer's Standard Color
Charts
SD-05 Design Data
Part 2 GDesign Analysis and Calculations
SD-06 Test Reports
3.2 GPressure Tests
3.2 GSystem Tests
3.2 GOperating Tests
SD-07 Certificates
1.3 GListing of Product Installations
Part 2 GPiping Materials
2.3.7 GAboveground Piping Systems
Part 2 GValves
2.3.5 GDetection Systems
Part 2 GAlarms
Part 2 GAir Compressor
Part 2 GSprinkler Heads
Part 2 GSupporting Elements
SD-10 Operation and Maintenance
Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 140 PAGES
21 13 26.00 40 3.4.1 GOperation and Maintenance
Manuals
21 21 01.00 10 SD-02 Shop Drawings
1.3Piping layout
1.3.1Electrical wiring diagrams
SD-03 Product Data
Storage cylinders
Discharge head
Manifolds
2.9Discharge alarm
2.3Pipe and fittings
2.4.3Pipe hangers and supports
2.6Actuating stations
2.6.3Pressure switch
2.6.5Control panel
2.7.1Smoke detectors
2.7.2Heat activated detectors
2.9.2Alarm horns
2.9.3Visual alarms
2.11Dampers
Main and reserve switch
2.9Warning signs
2.6.6.1Storage batteries
2.6.6.2Battery charger
SD-05 Design Data
1.3.2System calculations
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 140 PAGES
21 21 01.00 10 2.6.6.1Calculations substantiating battery capacity
1.3.2Open-area smoke detectors calculations
SD-06 Test Reports
3.5.1Preliminary tests
SD-07 Certificates
1.5.1Qualifications of installer
SD-10 Operation and Maintenance
Data
Discharge head
2.6.5Control panel
21 21 03.00 10 SD-02 Shop Drawings
1.4.3 GInstallation Drawings
SD-03 Product Data
1.4Similar Services
2.1 GStandard Products
3.2 GPreliminary Tests
3.3 GFinal Acceptance Tests
3.4Field Training
SD-06 Test Reports
3.2Preliminary Tests
3.3Final Acceptance Tests
SD-07 Certificates
1.4.2 GInstallation Technician
1.4.3 GInstallation Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 140 PAGES
21 21 03.00 10 SD-10 Operation and Maintenance
Data
3.4Operation and Maintenance
Instructions
21 30 00 SD-01 Preconstruction Submittals
1.3Fire Pump Installation Related
Submittals
1.7.1 GFire Protection Specialist
SD-02 Shop Drawings
3.3.1 GInstallation Drawings
3.11.2 GAs-Built Drawings
3.3.2 GPiping Layout
3.3.2 GPump Room
SD-03 Product Data
2.1 GCatalog Data
1.6Spare Parts
3.8.2Preliminary Tests
3.8 GField Tests
1.7.6 GManufacturer's Representative
3.11.1 GField Training
3.8.3Army Final Acceptance Test
Navy Formal Inspection and
Tests
SD-06 Test Reports
3.8.2Preliminary Tests
3.8.3Army Final Acceptance Test
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 140 PAGES
21 30 00 SD-07 Certificates
1.7.1Fire Protection Specialist
1.7.2Qualifications of Welders
1.7.3Qualifications of Installer
1.7.4Preliminary Test Certification
1.7.5Final Test Certification
SD-10 Operation and Maintenance
Data
3.11.1Operating and Maintenance
Instructions
2.17Flow Meter
22 00 00 SD-03 Product Data
2.4Fixtures
2.4.1Flush valve water closets
2.4.2Flush valve urinals
Flush tank water closets
2.4.4Wall hung lavatories
2.4.5Countertop lavatories
2.4.6Kitchen sinks
Service sinks
2.4.8Drinking-water coolers
Plastic shower stalls
Plastic bathtub liners
Plastic bathtub wall surrounds
2.10Water heaters
2.12Pumps
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 140 PAGES
22 00 00 Backflow prevention assemblies
2.6.2Shower Faucets
Swimming Pool [and Spa
]Suction Fittings
Pool Water Pump safety vacuum release system
3.4Vibration-Absorbing Features
SD-06 Test Reports
3.8Tests, Flushing and Disinfection
3.8.1.1Test of Backflow Prevention
Assemblies
SD-07 Certificates
Materials and Equipment
SD-10 Operation and Maintenance
Data
3.8.1Plumbing System
22 05 48.00 20 SD-02 Shop Drawings
2.7Inertia bases
2.6Machinery bases
2.6Platforms
2.6Rails
2.6Saddles
SD-03 Product Data
2.3Isolators
2.8Flexible connectors
2.9Flexible duct connectors
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 140 PAGES
22 05 48.00 20 2.11Pipe guides
2.10Seismic snubbers
3.1.3Vertical stops
2.12Thrust restraints
2.7Inertia bases
2.6Machinery bases
3.1.13Machinery foundations and subbases
2.6Platforms
2.6Rails
2.6Saddles
1.4.2Machinery manufacturer's sound data
SD-05 Design Data
2.7Inertia bases
2.6Machinery bases
2.6Platforms
2.6Rails
2.6Saddles
1.4.3machinery
1.4.4machinery over 300 pounds
SD-06 Test Reports
2.10Seismic snubbers
3.2.3.1Equipment vibration tests
3.2.3.2Equipment sound level tests
2.4Protected spring isolators
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 140 PAGES
22 05 48.00 20 SD-08 Manufacturer’s Instructions
3.1.1Vibration and noise isolation components
2.13Seismic protection components
22 07 19.00 40 SD-03 Product Data
2.3Adhesives
2.3Coatings
Insulating Cement
2.3Insulation Materials
2.3Jacketing
2.3Tape
SD-08 Manufacturer’s Instructions
1.2Installation Manual
22 14 29.00 40 SD-03 Product Data
2.1Manufacturer's Catalog Data
2.2.1Pump Performance Curve
2.2.1Pump and Motor Specifications
1.5Spare Parts
1.5Special Tools
2.2Wet-Pit Sump Pumps
2.3Submersible Pumps
2.3Accessories
SD-06 Test Reports
3.2.2Hydrostatic Leak
3.2.2Static Heads
3.2.2Pump Flow Capacity
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 39 OF 140 PAGES
22 14 29.00 40 SD-07 Certificates
Manufacturer's Certification of
Bearing Life
SD-08 Manufacturer’s Instructions
2.1Manufacturer's Installation
Instructions
2.1Vibration Specifications
22 15 14.00 40 SD-03 Product Data
1.4Equipment and Performance
Data
Underground Piping Materials
2.1Aboveground Piping Materials
2.2Piping Specialties
2.5Supporting Elements
Air Compressors
2.3Valves
3.1.1Accessories
2.4Miscellaneous Materials
3.1.5Vibration Isolation
SD-06 Test Reports
3.2.1Hydrostatic Testing
3.2Compressed Air Systems Testing
3.2.1Valve-Operating Tests
3.2.1Drainage Tests
3.2.1Pneumatic Testing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 40 OF 140 PAGES
22 15 14.00 40 SD-10 Operation and Maintenance
Data
1.5Operation and Maintenance
Manuals
22 31 00 SD-02 Shop Drawings
3.2Installation
SD-03 Product Data
2.2Softening Equipment
1.4Spare Parts
3.3.2Field Instructions
SD-06 Test Reports
2.2Softening Equipment
3.4.2Piping
SD-10 Operation and Maintenance
Data
3.3.2Operating and Maintenance
Instructions
23 00 00 SD-03 Product Data
2.8.1.1Metallic Flexible Duct
Insulated Nonmetallic Flexible
Duct Runouts
Duct Connectors
2.8.2Duct Access Doors
2.8.3Fire Dampers
2.8.4Manual Balancing Dampers
Automatic Smoke-Fire Dampers
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 41 OF 140 PAGES
23 00 00 Automatic Smoke Dampers
2.8.8Sound Attenuation Equipment
2.8.8.2Acoustical Duct Liner
2.8.9.1Diffusers
Registers and Grilles
2.8.10Louvers
2.8.11Air Vents, Penthouses, and
Goosenecks
2.9.1.1Centrifugal Fans
2.9.1.2In-Line Centrifugal Fans
2.9.1.3Axial Flow Fans
2.9.1.4Panel Type Power Wall
Ventilators
2.9.1.5Centrifugal Type Power Wall
Ventilators
2.9.1.6Centrifugal Type Power Roof
Ventilators
2.9.1.7Propeller Type Power Roof
Ventilators
2.9.1.8Air-Curtain Fans
2.9.1.9Ceiling Exhaust Fans
2.10Air Handling Units
2.11.1Room Fan-Coil Units
Coil Induction Units
2.11.2.1Constant Volume, Single Duct
Terminal Units
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 42 OF 140 PAGES
23 00 00 2.11.2.2Variable Volume, Single Duct
Terminal Units
2.11.2.3Variable Volume, Single Duct, Fan-Powered Terminal Units
Dual Duct Terminal Units
Ceiling Induction Terminal Units
2.11.2.5Reheat Units
2.11.3Unit Ventilators
2.12Energy Recovery Devices
1.4.5Test Procedures
Diagrams
SD-06 Test Reports
3.11Performance Tests
3.9Damper Acceptance Test
SD-08 Manufacturer’s Instructions
3.2Manufacturer's Installation
Instructions
3.13.2Operation and Maintenance
Training
SD-10 Operation and Maintenance
Data
3.13.1Operation and Maintenance
Manuals
2.8.3Fire Dampers
2.8.4Manual Balancing Dampers
Automatic Smoke-Fire Dampers
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 43 OF 140 PAGES
23 00 00 Automatic Smoke Dampers
2.9.1.1Centrifugal Fans
2.9.1.2In-Line Centrifugal Fans
2.9.1.3Axial Flow Fans
2.9.1.4Panel Type Power Wall
Ventilators
2.9.1.5Centrifugal Type Power Wall
Ventilators
2.9.1.6Centrifugal Type Power Roof
Ventilators
2.9.1.7Propeller Type Power Roof
Ventilators
2.9.1.8Air-Curtain Fans
2.9.1.9Ceiling Exhaust Fans
2.10Air Handling Units
2.11.1Room Fan-Coil Units
Coil Induction Units
2.11.2.1Constant Volume, Single Duct
Terminal Units
2.11.2.2Variable Volume, Single Duct
Terminal Units
2.11.2.3Variable Volume, Single Duct, Fan-Powered Terminal Units
Dual Duct Terminal Units
Ceiling Induction Terminal Units
2.11.2.5Reheat Units
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 44 OF 140 PAGES
23 00 00 2.11.3Unit Ventilators
2.12Energy Recovery Devices
23 01 30.41 SD-01 Preconstruction Submittals
3.2.1Record of Existing Conditions
3.2.2Coordination Plan
1.4.1NADCA Firm
1.4.1NADCA Team Assistants
1.4.1NADCA Air System Cleaning
Specialist (ASCS)
1.4.1NADCA Supervisor…