TE L PRS
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Exhibit L
PERFORMANCE REQUIREMENTS SUMMARY
Performance Requirements Summary (PRS) Table. The PRS that follows provides the following information.
Required Service. Lists the contract requirements which are considered necessary for acceptable contract performance. The absence of any contract requirement from this table does not relieve the Contractor of compliance with all of the contract requirements.
Paragraph Number. Contains the standards that each contract requirement shall meet or exceed.
Standards. Brief description of the standards for the respective “Required Service”.
Acceptable Level of Performance (ALP). Sets forth the maximum allowable deviation from perfect performance for each listed service. Allowable Level of Performance that may occur before the Contractor will receive less than 100% of the maximum payment for the listed service.
Method of Surveillance. Sets forth the primary surveillance methods that the Government will use to evaluate the Contractor’s performance in meeting the contract requirements. Definition of the lot used as the basis for surveillance or for payment computation purposes is also included in this column.
Task Value Percent. Sets forth the percentage of the contract price (the proportion of the required service to the total contract price of the respective contract line items (CLINS)) that each required service represents.
PERFORMANCE REQUIREMENTS SUMMARY TABLE
| REQUIRED SERVICE |
| PARA. NO. |
| STANDARD |
| ALP |
| METHOD OF SURVEILLANCE |
| TASK VALUE PERCENTAGE |
| Refuse Work in Cantonment |
| 5.1. |
| All required service is performed IAW the approved schedule. |
| 5% |
| Random Sample By Schedule |
(Lot is quantity of BLDG’s per month)*** 30%
| Compost Work in Cantonment |
| 5.2. |
| All required service is performed IAW the approved schedule. |
| 2.5% |
| Random Sample By Schedule |
(Lot is 100% of containers randomized by number of service days per month) 10%
| Special Events |
| 5.1.8. & 5.2.4 |
| All required service is performed in support of the event |
| 0% |
| 100% |
(Lot is number of events) 5%
| Compost Center Operation |
| 5.3. |
| No vehicles containing unauthorized waste; all organic waste chipped, screened and stockpiled; production of AAA compost |
| 0% |
| 100% |
(Lot is number of operating days) 20%
| Grease Trap Collection and Disposal |
| 5.4. |
| All required service is performed IAW the approved schedule. |
| 4% |
| Random Sample By Schedule |
(Lot is quantity of services) 10%
| Landfill Operations |
| 5.5. |
| All required service is performed daily. |
| 0% |
| (Lot is number of operating days of the week) |
| 25% |
Formula for calculating deduction from contract payment based on PRS table (for each required service:
(Quantity of Samples that are Defective)/(Total Quantity of Samples) x 100% = X %
(X% - ALP) x (Task Value Percent) x (Total Contract Cost) = Total Deduction for the Month