Updated as of 15 Nov 2012:
Updated Milestones for C3IDM
Anticipated Event Completion Date
| Release RFI | 08/02/2011 | ||||
| Market Research Completed | 11/22/2011 | ||||
| Issue Draft Request for Proposal (DRFP) | 11/09/2011 | ||||
| Issue 2nd Draft RFP | 05/09/2012 | ||||
| Issue 3rd Draft RFP | 08/04/2012 | ||||
| Synopsis Posted to ASFI/Fed Biz Opps | 05/14/2012 | ||||
| Issue Final RFP | 09/30/2012 | ||||
| Receive Proposals | 01/18/2013 | ||||
| Award | 02/04/2014 | ||||
| Debriefs Complete | 02/18/2014 |
Updated Date for C3IDM Solicitation
| Proposal Due Date/Time – no later than | 01/18/2013, 1400 hours (2 pm) (CT) | |
| OCI information in L.6 – no later than | 12/04/2012, 1400 hours (2 pm) (CT) | |
| Past Performance Volume – no later than | 01/04/2013, 1400 hours (2 pm) (CT) | |
| Last Day for Submission of Questions | 11/26/2012, 1400 hours (2 pm) (CT) | |
| Posting of Q&As and Amended RFP | 12/07/2012, 1400 hours (2 pm) (CT) |