0011667599
THIS IS A "WORK PLAN" TASK ORDER FOR THE FOLLOWING MATOC CONTRACTORS ONLY.
ONLY Proposals for this requirements are being solicited from the MATOC contractors for the follow ing MATOC contracts issued by 411th
Contracting Support Brigade (CSB).
Proposals from offerors other than these MATOC Contractors w ill not be considered for aw ard, Contract Number: W91QVN-18-D-0080, 0082, 0084, 0085, 0089, 0091, 0092, 0115, and 0116.
A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend site visit. See site visit Clause
FAR52.236-27 in Section L. Offerors are required to have a valid Korean Identif ication card w hen attending the site visit orientation.
B.SUBMISSION OF PROPOSAL: See section L for details. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit the "No-offer letter" by date and time specif ied in this solicitation.
C.BASIS OF AWARD: See Section M of this solicitation.
MS. YIM, MI-SUK 315-763-5691
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
06-Jul-2021
(RFP)
(IFB)
X
CALL:
Repair B&G Storage Shed, B# S372, S373 & S374, Cp Carroll
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________150 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________20 Jul 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
RCO DAEGU, UNIT #15682
APO AP 96218-5682
UNITED STATES
W90VN9
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
HS-00608-0J
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W90VN921R0059 27
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued)
(Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W90VN921R0059
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Work Class: K (Work Plan)
FFP
The Contractor shall provide all necessary resources for this requirement and perform Project No. HS-00608-0J, Repair B&G storage shed, Building No. S-372, S-373 and S-374 at Camp Carroll (Work Plan) in accordance with the Statement of
Work (SOW), Specification, Drawings, Terms and Conditions of this contract contained herein.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011667599
PSC CD: Z2GD
NET AMT
0002 1 Job Work Class: L (Work Plan)
FFP
The Contractor shall provide all necessary resources for this requirement and perform Project No. HS-00608-0J, Repair B&G storage shed, Building No. S-372, S-373 and S-374 at Camp Carroll (Work Plan) in accordance with the Statement of
Work (SOW), Specification, Drawings, Terms and Conditions of this contract contained herein.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011667599
PSC CD: Z2GD
Estimated War Hazard Losses
FFP
is Zero (0)
FOB: Destination
Section C - Descriptions and Specifications
SOW
SPECIFICATIONS
FOR
REPAIR B&G STORAGE SHED,
BLDG. NO. S-372, S-373 & S-374
(WORK PLAN)
CAMP CARROLL
PROJECT NO. HS-00608-0J
TABLE OF CONTENTS
1. Technical Provisions - I: Statement of Work
2. Technical Provisions - II: Technical Detail Specifications
3. Technical Provisions - III: Special Conditions
4. Appendix "A": List of Applicable Contract Drawings
TECHNICAL PROVISIONS - I
STATEMENT OF WORK
PROJECT NO TITLE LOCATION
HS-00608-0J Repair B&G Storage Shed, Bldg. No. S-372, S-373 & S-374 Camp Carroll
(Work Plan)
DESCRIPTION: The work to be performed shall be in accordance with all drawings and specifications provided under this contract.
a. Work by Contractor:
(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and specifications.
(2) The contractor shall repair B&G storage shed, Bldg. No. S-372, S-373 & S-374, Camp Carroll in accordance with the specifications and drawings.
b. Work by In-House Labor: Not applicable to this project.
c. Work by Troop Labor: Not applicable to this project.
(3) Performance Period: Shall be 150 calendar days after Notice to Proceed (NTP) is issued at the Post Award Conference (PAC). There will also be a Pre-Construction Conference (PCC) upon government’s acceptance of the 100% drawing package and respective design analysis.
PRINCIPAL FEATURES: This project shall include the following:
Work Plan Special Requirement
1. The structural design of the architectural sector shall be carried out as a Work Plan.
2. It is highly recommended for the contractor to attend the site orientation conducted by contracting office and DPW to get a clear understanding of the site overview which could impact design and construction.
3. The contractor shall submit concept drawings, including scope of work to the Design branch via
411th Contracting Support Brigade (CSB) included with their proposal. The concept drawing will be reviewed for its acceptability during the technical evaluation stage.
4. The contractor shall submit 50% (30 calendar days after the PAC) and 100% (50 calendar days after the PAC) structural drawings and structural analysis with bill of material and quantities for approval prior to commencing construction unless otherwise at government’s discretion such as demolition.
5. The contractor shall consider that the proposed site layout plan may change depending on the site conditions and therefore, attendance at site survey during the solicitation phase is encouraged.
6. The contractor shall submit and get approval of shop drawings and detail drawings for construction.
Schedule #I, Construction (L): All work shall be in accordance with the attached drawings and
A. Civil Work
1. Construct asphalt concrete pavement, base course and subbase course.
2. Construct Portland cement concrete pavement including base course.
B. Architectural Work
Bldg. #372
1. Install new floor concrete slab with reinforcing bar including joint and necessary accessories.
2. Install new metal roofing system, steel trusses and steel frame including necessary accessories.
3. Install new protected metal wall, metal support and including necessary accessories.
4. Paint all interior and exterior surfaces with sealant work.
Bldg. #373
Bldg. #374
Schedule #II, Repair (K): All work shall be in accordance with the attached drawings and
A. Civil Work
1. Remove existing building components, (Bldg. #372, #373 & #374).
2. Remove existing gravel pavement.
3. Remove existing trees, shrubs, branches and roots.
4. Replace existing chain link fence (Type FE-6, H=2,400) and double swing gate (W=6,000, H=2,400) including necessary accessories with new.
5. Replace existing concrete open ditch (W=400, W=500) with new.
6. Restore existing stone wall including chain link fence with new same as exist.
7. Provide earth works including excavation, compaction and other necessary related tasks at government’s discretion.
8. Sod with top soil and solid sodding.
B. Architectural Work
Bldg. #372
1. Provide new floor concrete slab with reinforcing bar including joint and necessary accessories.
2. Provide new reinforced concrete footings for roof support columns including necessary accessories.
3. Replace existing wood column structure with new steel columns, rafter beams, girder beams and support frame including necessary accessories.
4. Replace existing metal roof and wood frame with new including protected metal roofing system, steel trusses, steel frame and necessary accessories.
5. Replace existing metal wall with new including protected metal wall metal support and necessary accessories.
6. Provide new metal rain gutters, downspouts and splash blocks.
7. Replace existing sign with new.
8. Paint all interior and exterior surfaces with sealant work.
Bldg. #373
2. Replace existing reinforced concrete footings with new including necessary accessories for roof support columns
3. Replace existing steel column structure with new steel columns, rafter beams, girder beams and
4. Replace existing metal roof system with new including protected metal roofing system, steel trusses, steel frame and necessary accessories.
5. Replace existing metal wall with new including protected metal wall, metal support and necessary
Bldg. #374
2. Replace existing reinforced concrete footings with new including necessary accessories for roof support columns
3. Replace existing steel column structure with new steel columns, rafter beams, girder beams and
4. Replace existing metal roof system with new including protected metal roofing system, steel trusses, steel frame and necessary accessories.
5. Replace existing metal wall with new including protected metal wall, metal support and necessary
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management
Command. The most current specifications are available (for referral purposes only) on the USFK’s
Web Page http://www.usfk.mil/Resources/Contracting-with-USFK. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed
Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL
CONDITIONS" which is incorporated into the contract.
2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours must be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR). Please note that there will be an exception for night shift when working on the fire alarm system.
3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed by the Government to require inspection.
4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.
5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten
(10) working days prior to the starting of work. The request shall be submitted to the COR for approval.
6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.
7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, and other equipment necessary for proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, and any other items, as required by law.
8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the
COR. Equipment not completely safe or functional shall be repaired and accepted by the government before work is started.
9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings any changes in such work which constitute any change from the original contract drawings per government’s approval. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “
As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.
10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after
Notice to Proceed dependent on Government’s direction if such material is not yet determined.
11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.
12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.
13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting
Officer approval. Make request fourteen (14) calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, associated level of work shall be lighted in a manner approved by the Contracting Officer.
Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.
14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor additional cost. These additional incurred costs are contractor’s responsibility. The Contractor shall reflect these costs in the preparation of their proposal.
15. SAFETY: The safety plan must be approved before any work can be performed on this contract.
Hard hats, suitable work boots and other necessary personnel protective gear per safety regulations are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and Fire and Emergency Service (POC: Fire Communication office, DSN:
768-4120) prior to entering confined spaces (i.e. manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.
16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to provide information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.
17. WARRANTY: The contractor shall be responsible for resolution on any defect/ failure on the contract during the one (1) year warranty period. The contractor shall provide services or/and repair and replacement to the satisfaction of the government. The one (1) year warranty starts the day after final inspection approval from the authorized government personnel.
18. ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.
18.1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
18.2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within
30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil
18.3. For contractors that do not require CAC, but require access to a DoD facility or installation.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures
(provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
18.4. iWATCH TRAINING. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
19. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;
Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;
Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;
Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;
20. CONTAMINATION FIND CLAUSE: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.
21. INADVERDENT FIND CLAUSE: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 12, Para 12-3 J)
22. FUEL TANK AND LINES: If applicable, when underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS)
Ch. 9, Para 9-3.b. (5))
23. Non-PCB TRANSFORMER CERTIFICATION: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB transformer certification to COR for each to be installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.
24. CONTRACTING MANPOWER REPORTING
24.1 (CMR) Requirement: The Office of the Assistant Secretary of the Army (Manpower & Reserve
Affairs) operates and maintains a secure Army data collection site where the Contractor will report
ALL Contractor manpower (including sub-contractor manpower) required for performance of this contract. The Contractor is required to completely fill in all the CMR information in the format using the following web address: https://cmra.army.mil. However, before the Contractor can begin reporting
CMR data in this website, he or she must first register as a User. In order to register, the Contractor must have a Cage Code.
24.2 How to Obtain Cage Code for Korean Company: If you are a Korean company needing a Cage
Code, at Telephone #82-2-2079-4639, FAX 82-2-773-7587, EMAIL CAGEKR@dapa.go.kr , Address: The
Standard Planning Team of the Standard Management Bureau Defense Acquisition Program Division
(23 Yongsangogyogil), #2-15 Yongsan 2 ga dong, Yongsan-gu, Seoul (140-841), Republic of Korea.
24.3 CMR Reporting: The information required to be reported in the CMR website includes: (1)
Contracting Office, Contracting Officer, Contracting Officer’s Technical Representative (COTR) or
Contracting Officer’s Representative (COR); (2) Contract Number, including Task and Delivery Order
Number(s); (3) Beginning and Ending dates covered by reporting period; (4) Contractor Name, Address, Phone Number, E-Mail Address, Identity of Contractor Employee entering data; (5) Estimated
Direct Labor Hours (including sub-Contractors’ hours); (7) Total Payments (including sub-Contractors’ payments); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor
(and separate Predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational Title associated with the Unit Identification Code (UIC) for the Army
Requiring Activity reporting this information (the Army Requiring Activity (RA) is responsible for providing the Contractor with its UIC for purposes of reporting this information); (11) Locations where
Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest City and Country when in an overseas location, using standardized nomenclature provided on website); (12) Presence of Deployment or Contingency Contract language; and (13) Number of
Contractor and sub-Contractor employees deployed in theater this reporting period (by Country).
As part of its submission in response to a solicitation or a modification request which includes a contract line item number (CLIN) for this CMR reporting requirement, the Contractor shall also provide the estimated total cost (if any) incurred to comply with this reporting requirement on the associated CMR CLIN. Reporting period will be the period of performance not to exceed 12 months ending September 30 of each Government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s systems to the secure website without the need for separate data entries for each required data element at the website. The specific formats for the XML direct transfer may be downloaded from the website.
CMR reporting is a requirement mandated by the Department of Army. Failure of the Contractor to comply with this requirement will be noted as Past Performance information about the Contractor to be used on future procurements for the same or similar services.
Section F - Deliveries or Performance
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the
Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days after Notice to Proceed (NTP) is issued.
* The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
AUG 2020
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services--
Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications-
Commercial Items. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the
Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.
(a) Definitions. As used in this provision-
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause
52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or
Equipment.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM)
(https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."
(d) Representations. The Offeror represents that--
(1) It [] will, [] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds
"will" in paragraph (d)(1) of this section; and
(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--
It [] does, [] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.
(e) Disclosures.
(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as
OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered
(include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as
OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered
(include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(End of provision)
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES--REPRESENTATION (OCT
2020)
(a) Definitions. As used in this provision, “covered telecommunications equipment or services” and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain
Telecommunications and Video Surveillance Services or Equipment.
(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM)
(https://www.sam.gov) for entities excluded from receiving federal awards for “covered telecommunications equipment or services”.
(c) Representations.
(1) The Offeror represents that it [ ___ ] does, [ ___ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.
(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
https://www.sam.gov/
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 50 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting
Officer determines that the reduction would be to the advantage of the Government.
(End of clause)
Section J - List of Documents, Exhibits and Other Attachments
DRAWINGS
APPENDIX "A"
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the
Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/Contracting-with-USFK), all of which form a part of the specifications.
Drawing No. Ref. No. Sheet No. Description Date
D-21-16 R-1 1 of 1 Title Sheet 23 Jun 21
“ C-01 1 of 25 Location Plan “
“ C-02 2 of 25 Removal Plan “
“ C-03 3 of 25 Site Layout Plan “
“ C-04 4 of 25 Typical Sections (1 of 2)
“ C-05 5 of 25 Typical Sections (2 of 2) “
“ C-06 6 of 25 Ac Pavement and Concrete Ditch Details “
“ AE-01 7 of 25 Existing Floor Plan and Section, Bldg. #372, Bldg. #373, Bldg. #374, General Notes and Demolition Notes “
“ AE-02 8 of 25 Scope of Work and Notes “
“ AE-03 9 of 25 New Floor Plan, Roof Plan, and
Elevations, Bldg. #372 “
“ AE-04 10 of 25 New Floor Plan, Roof Plan, and
Elevations, Bldg. #373 “
“ AE-05 11 of 25 New Floor Plan, Roof Plan, and
Elevations, Bldg. #374 “
“ AE-06 12 of 25 Building Section, Bldg. #372 “
“ AE-07 13 of 25 Building Section, Bldg. #373 “
D-21-16 AE-08 14 of 25 Building Section, Bldg. #374 23 Jun 21
“ AE-09 15 of 25 Roof Detail-1, Detail-2, Fall Protection Detail and Notes “
“ AE-10 16 of 25 Gutter Details, Conc. Splash block, Exterior Finish Schedule and Note “
“ SF-01 17 of 25 Structural General Notes “
“ SF-02 18 of 25 Standard Hook, Typical Beam Details, Beam & Girder Joint Detail, and Notes “
“ SF-03 19 of 25 Typical Concrete Detail and
Design Criteria and Notes “
“ SF-04 20 of 25 Typical Steel Details “
“ SF-05 21 of 25 Floor Plan, Roof Plan, Section and Legend “
“ SF-06 22 of 25 Section, Bldg. #374, Footing Detail, F1 and Enlarged Detail “
“ SF-07 23 of 25 Enlarged Plan & Detail (Typ.) “
“ SF-08 24 of 25 Enlarged Plan & Detail “
“ SF-09 25 of 25 Typical Concrete Slab Detail (Typ.) “
Section K - Representations, Certifications and Other Statements of Offerors
52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)
(a) The offeror certifies that --
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –
(i) Those prices,
(ii) The intention to submit an offer, or
(iii) The methods of factors used to calculate the prices offered:
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --
(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or
(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs
(a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of Provision)
5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS
(a) SUBCONTRACTING:
If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or
ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.
(b) AFFILIATED OFFERORS:
(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.
(2) Each offeror shall furnish, below, the following information:
(i) Whether the offeror has any affiliates;
(ii) The names and addresses of all affiliates of the offeror; and
(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.
AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)
(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):
Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.
(d) STANDARDS OF CONDUCT CERTIFICATION:
This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.
(i) Name ______________________________________________
Former rank/grade ____________________________________
Last US Government position ___________________________
(ii) Name ______________________________________________
(iii) Name ______________________________________________
Firm ____________________________________________________
Name _____________________________________________________
Signature __________________________________________________
Title _____________________________________________________
Date of Execution ____________________________________________
(e) TAXES:
(1) References:
(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _____ No _____
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. 10% _____
Input VAT on transportation leased/rented for this contract.10% _____
Input VAT on equipment leased/rented for this contract. 10% _____
Input VAT on services purchased for this contract. 10% _____
Output VAT on total contract amount. 10% _____
(iv) Special Excise (Petroleum) Tax:
No. of U/P
Liters w/o Tax Tax/Unit Total Tax Amount
Regular Gasoline ________ (L) ________ w________ w_____________
Premium Gasoline ________ (L) ________ w________ w_____________
Diesel ________ (L) ________ w________ w_____________
Other ________ (L) ________ w________ w_____________
(v) Education Tax.
(3) Name of the oil company from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.
Signed (Chop)
(f) CERTIFICATIONS AND REPRESENTATIONS
By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.
The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.
Section L - Instructions, Conditions and Notices to Bidders
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions
Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for--
Date/Time: 13 July 2021 / 10:30 hrs
Location: In front of Bldg. 373, Camp Carroll
Technical POC: Yi, TongKi (Email: tongki.yi2.ln@mail.mil, DSN: 763-5370)
INSTRUCTIONS TO OFFEROR
a. Site Visit: Offerors who intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit Clause FAR 52.236-27. Offerors are required to have a valid Korean Identification card when attending the site visit orientation.
b. Offeror(s) are cautioned to follow the detailed instructions fully and carefully, as the Government reserves the right to make award based on initial offers received, without discussions of such offers.
c. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.