Questions and answers

Question: Could we take windows and recover it after works?

Answer: Windows can be removed and replaced for purpose of moving to second and third floors.

Question: Could you support Folk Lift for deliver from Container to Building?

Answer: the containers will be moved to the building parking lot prior to installation.