MLWR17-1021R1,_DD_1391_(Draft).doc

DOC document 523 KB Posted

Attached to
Renovate MiddleSouth Side bay at AMXS Bldg 2852
Solicitation number
W90VN7-19-R-0002
Issued by

About this file

Construction DATA: More drawing shall be provided

View the file

Other files

File Type Posted
Cancellation_Notice.pdf PDF
Solicitation_W90VN7-19-R-0002_Amendment.pdf PDF
4_MLWR17-1021,_Combined_Drawings-pdf.pdf PDF
W90VN7-19-R-0002.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. COMPONENT

AIR FORCE

FY 2019 MILITARY CONSTRUCTION PROJECT DATA
2. DATE

13 JUL 2018

3. INSTALLATION AND LOCATION

KUNSAN AIR BASE, KOREA (PACAF)

4. PROJECT TITLE:

RENOVATE MIDDLE/SOUTH BAY AT AMXS BLDG 2852

5. PROGRAM ELEMENT

2.21.76

6. CATEGORY CODE

215-522

7. PROJECT NUMBER

SRM

MLWR17-1021

8. PROJECT COST ($000)

EEIC 522 – 1,200

9. COST ESTIMATES

ITEM
U/M
QUANTITY
UNIT

COST

COST

($000)

Renovate AMXS Building 2852

Architectural Work

Mechanical Work

Electrical Work

ACM Removal & Misc Work

Total Direct Cost

Contractor’s Overhead & Profit, 15%

Total Funded Cost

Unfunded Cost (Planning & A-E Design, 10%)

SF

LS

9,000
50.00

640.0 (450.0)

(285.0)

(225.0)

( 83.5) 1,043.5 156.5 1,200.0 120.0

10. DESCRIPTION OF PROPOSED CONSTRUCTION

Renovate middle and south side bays of existing Aircraft Maintenance Squadron (AMXS) building 2852. South side bay work includes removal work; replacement of metal roof and siding with new; replacement of deteriorated interior finishes such as floor tile, walls and ceiling at admin area; new floor coating at shop and storage area; replacement of metal sliding doors with new roll-up doors, exterior metal and interior wood doors with new including frames, and new windows; total renovation of latrine area and paint work; replacement of heating, ventilating, and air conditioning (HVAC) system and plumbing system, replacement of lighting fixtures, fire alarm/detection/mass notification system, receptacles, switches and wiring with conduit. Middle bay work includes removal work; replacement of metal roof and siding with new, construction of additional office area and a secure room, paint all interior including repair of damaged walls, new floor coating at shop and storage area; replacement of damaged exterior metal and interior wood doors with new including frames; and installation of a heat pump at additional admin area and sprinkler system. Also includes asbestos removal work, upgrade of power system including new transformer, overhead secondary lines with new underground lines and panel boards, and other necessary support to complete the project.

11. REQUIREMENT: N/A

PROJECT: Renovate Middle/South Bay at AMXS building 2852.

REQUIREMENT: This project is necessary to repair old and deteriorated AMXS building to support the TSP mission. This project is required to provide an adequate, safe and comfortable working environment for the assigned working personnel and follow-on forces. Unsuitable working environment will decrease the quality of work as well as the quality of life for the assigned working personnel as well as the customers visiting this facility.

CURRENT SITUATION: The existing AMXS facility, built in 1969, is old and deteriorated due to age and general wear and tear. Due to lack of maintenance and repair, the interior finishes of two bays are worn out and should be replaced with new ones. Old and deteriorated electrical, heating, ventilating, and air conditioning (HVAC) and plumbing systems causes problems and it also looks unsightly for the assigned working personnel as well as the follow-on forces using this facility. Therefore total renovation is necessary to provide an adequate and functioning working environment as well as for the quality of life.

DD Form 1391c, DEC 76 (E-Form)

PREVIOUS EDITION IS OBSOLETE IN THE USAF

PAGE NO. 1

UNTIL EXHAUSTED

1. COMPONENT

AIR FORCE

FY 2019 MILITARY CONSTRUCTION PROJECT DATA
2. DATE

13 JUL 2018

3. INSTALLATION AND LOCATION

KUNSAN AIR BASE, KOREA (PACAF)

4. PROJECT TITLE

RENOVATE MIDDLE/SOUTH BAY AT AMXS BLDG 2852

5. PROJECT NUMBER

SRM

MLWR17-1021

IMPACT IF NOT PROVIDED: Without this project, AMXS activities will continue to degrade due to lack of an adequate and functional facility. Furthermore, the quality of life for the assigned working personnel as well as the follow-on forces using this facility will be decreased.

ADDITIONAL: The total programmed amount of this project does not exceed the 70% of total replacement cost ($1,200,000/$5,085,910 = 23.6%).

PAGE NO. 2

UNTIL EXHAUSTED

1. COMPONENT

AIR FORCE

FY 2019 MILITARY CONSTRUCTION PROJECT DATA
2. DATE

13 JUL 2018

3. INSTALLATION AND LOCATION

KUNSAN AIR BASE, KOREA (PACAF)

4. PROJECT TITLE

RENOVATE MIDDLE/SOUTH BAY AT AMXS BLDG 2852

5. PROJECT NUMBER

LOCATION MAP

Scale: 1” = 400’-0”

Using Agency (8 AMXS/MXA)/Date

Safety Manager (8 FW/SEW)/Date

Fire Department (8 CES/CEF)/Date

Airfield Management (8 OSS/OSAA)/Date

Environmental (8 CES/CEIE)/Date

Engineering Flight (8 CES/CEN)/Date

PAGE NO. 3

UNTIL EXHAUSTED

1. COMPONENT

AIR FORCE

FY 2019 MILITARY CONSTRUCTION PROJECT DATA
2. DATE

13 JUL 2018

3. INSTALLATION AND LOCATION

KUNSAN AIR BASE, KOREA (PACAF)

4. PROJECT TITLE

RENOVATE MIDDLE/SOUTH BAY AT AMXS BLDG 2852

5. PROJECT NUMBER

PAGE NO. 4

UNTIL EXHAUSTED

1. COMPONENT

AIR FORCE

FY 2019 MILITARY CONSTRUCTION PROJECT DATA
2. DATE

13 JUL 2018

3. INSTALLATION AND LOCATION

KUNSAN AIR BASE, KOREA (PACAF)

4. PROJECT TITLE

RENOVATE MIDDLE/SOUTH BAY AT AMXS BLDG 2852

5. PROJECT NUMBER

PAGE NO. 5

UNTIL EXHAUSTED

APPROVED

8TH CES/CEN

SHAUN D. HYLAND-MOORE, Capt, USAF