FB428401930003

MLWR17-1041, Repair BE Covered Storage, B-2817, Kunsan AB

Notice to Offerors: Funds are not presently available for this project. No aw ard w ill be made under this solicitation until funds are available.

The Government reserves the right to cancel this solicitation, either before or after the closing date. See FAR 52.232-18.

"THIS IS A NON-WORK PLAN TASK ORDER FOR THE FOLLOWING MATOC CONTRACTORS ONLY”

W91QVN-14-D-0031, -0032, -0033, -0035, -0036, -0037, -0038, -0039, -0040, -0041, -0044, -0045, -0046, -0047, -0048, -0049 and -0050

OFFERORS MUST COMPLY WITH THE FOLLOWING:

A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend site visit. See site visit Clause FAR 52.236-27. Offerors are required to have a valid Korean Identif ication card w hen attending the site visit orientation.

B. SUBMISSION OF PROPOSAL:

1. The PROPOSAL shall be submitted by 1300 hours on the closing date of RFP through https://w w w .fbo.gov/

2. Section K: Offerors must complete all portions of Section K and submit it through https://w w w .fbo.gov/ by 13:00 hours on the closing date of RFP.

ROBERT, KAIN B. SSG (063) 470-4920

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

21-Sep-2016

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________120 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________04 Oct 2016 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO KUNSAN, UNIT #2112

APO AP 96264-2112

UNITED STATES OF AMERICA (THE)

W90VN7

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W90VN7-16-R-0076 35

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN7-16-R-0076

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Repair BE Covered Storage

FFP

Repair BE Covered Storage, B-2817, project MLWR17-1041 in accordance with the Technical Specifications.

FOB: Destination

PURCHASE REQUEST NUMBER: FB428401930003

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

War Hazard

FFP

Estimated Cost for War Hazard Losses is Zero (0).

PURCHASE REQUEST NUMBER: FB428401930003

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

TECHNICAL SPECIFICATIONS

FOR

MLWR17-1041

REPAIR BE COVERED STROAGE, B-2817

(Non-Work Plan of Task Order MATOC)

8TH CIVIL ENGINEER SQUADRON

KUNSAN AIR BASE, KOREA

15 JUNE 2016

DETAILED-SPECIFICATION

The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea”, dated Jan 2014, located on the 411th CSB Web Page, https://www.usfk.mil/usfk/hot-topic.contract.with.usfk.697. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader software.

INDEX

SECTION NO TITLE

DIVISION 01 - GENERAL REQUIREMENTS

013000 Administrative Requirements 013300 Submittal Procedures 013526 Government Safety Requirements 013529 Heath and Emergency Response Procedures for Contaminated Sites 014200 Sources for Reference Publications 014500 Quality Control 015000 Temporary Construction Facilities 015720 Environment Protection 015800 Project Identification 017800 Closeout Submittals 017823 Operation and Maintenance Data

DIVISION 02 – EXIST CONDITIONS

024100 Demolition and Deconstruction 028100 Transportation and Disposal of Hazardous Material

DIVISION 03- CONCRETE

031113 Structure Cast-In-Place Concrete Forming 031500 Concrete Accessories

DIVISION 05 – METALS

050523 Welding, Structural 055013 Miscellaneous Metal Fabrications

DIVISION 06 –WOOD, PLASTICS AND COMPOSITES

062000 Rough Carpentry

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

072116 Mineral Fiber Insulation 074113 Metal Roof Panels 074213 Metal Wall Panels 076000 Flashing and Sheet Metal 079200 Joint Sealing

DIVISION -08- OPENING

081113 Steel Door and Frame 083323 Overhead Coiling Doors 087100 Door Hardware

DIVISION 09 - FINISHES

099000 Paint and Coating

NOTE: Wherever "Special Clause" or "Special Provisions" appears in OM&A sections substitute "clauses and/or special provisions of this contract."

DIVISION 1 GENERAL REQUIREMENTS

SECTION 1A STATEMENT OF WORK

INDEX

1A-1 DESCRIPTION OF WORK

1A-2 PRINCIPAL FEATURES

1A-3 PERFORMANCE PERIOD

1A-4 LIST OF DRAWINGS

1A-5 GENERAL CONDITIONS

1A-6 CONTRACT DATA REQUIEMENTS LIST (CDRL)

1A-1. DESCRIPTION OF WORK: The work under project MLWR17-1041, Repair BE Covered Storage, B-2817, consists of furnishing all labor, equipment, materials, transportation and supervision necessary to perform all the work as shown on the drawings and indicated herein.

1A-2. PRINCIPAL FEATURES: The description of the work is includes the principal features only. This general outline does not in anyway limit the responsibility of the contractor from performing all work indicated herein and on the drawings.

1. Architectural Work

1.1. Replace existing metal siding panels with new #24 gauge protected metal siding panels as shown on the construction drawings.

1.2. Install new wall insulation with new 4” thick fiber glass insulation including aluminum foil/vapor barrier and chicken wire as shown on the construction drawings.

1.3. Replace existing metal flashing with new 24gauge protected metal as shown on the construction drawings

1.4. Install new gutter and downspout with accessories including concrete splash block as shown on the construction drawings

1.5. Clean by sandblasting and apply one coat of primer (TT-P-86, Type 1) and two (2) coats of oil paint (TT-P-105, Federal Standard Color No. 20099) to the all structural steel members’ surfaces of building 2817 as shown on the construction drawings.

1.6. Repair existing concrete floor at damaged area as required.

1.7. Remove existing steel revetment at east side of B-2817.

1.8. Install scaffolding in accordance with safety manual to remove and install wall siding, gutter, downspout and other works to entire building.

1.9. Restore any damaged materials caused by this work to its original condition.

1.10. Remove and dispose of all construction rubbish and debris, off Kunsan Air Base, at the contractor’s own expense, in strict accordance with existing Korean/U.S.

Environmental Laws and Regulations.

1.11. Contractors shall submit the report on the weight of Construction and Demolition (C&D) debris diverted and the weight of C&D debris disposed to COR in accordance with section 3.3.2 and 3.8.1.4. of the AFI 32-7042, data on the weight of C&D debris diverted and the weight of C&D debris disposed must be documented and reported.

All C&D debris disposal contracts must be reviewed to ensure this requirement is being met. This information must be reported to 8th Civil Engineering Squadron Environmental Flight (8CES/ CEAN). The contractor could obtain the data from landfill and /or recycling company.

1A-3 PERFORMANCE PERIOD: 120 Days

3.1 Highly recommend the contractor shall be attended site orientation hosted by 8 CES before applying for bid.

3.2 Contractor shall attend pre-construction conference prior to notice to proceed (NTP) being issued and needs to submit construction schedule prior to pre-construction conference.

1A-4. LIST OF DRAWINGS

ITEM NO TITLE SHT NO

C-1 LOACTION MAP 1 OF 5

A-1 NEW FLOOR PLAN 2 OF 5

A-2 ELEVATIONS 3 OF 5

A-3 SECTIONS AND DETAILS 4 OF 5

A-4 WALL SECTION AND DETAILS 5 OF 5

A1-5. GENERAL CONDITIONS

1. SPECIFICATIONS: The project shall comply with the MLWR 17-1041, Repair BE Covered Storage, B- 2817, Kunsan AB, Korea, Contract (100%) Submittal Specifications shall comply with the “Standard Technical Specifications for O&MA (Operation & Maintenance Army) Projects, Korea dated 24 January 2014”, “Standard Detail drawings for O&MA Project Korea dated 01 October 2003” are available on the 411th CSB Web Page, https://www.usfk.mil/usfk/hot-topic.contract.with.usfk.697 or the specification electronic files are available at the 8th Civil Engineering Squadron, Kunsan Air.

2. ALERTS: During military alerts or special operations, anticipated not to exceed forty (40) working days per year of contract duration, the contractor may be denied access to the base or the work areas. When the contractor is prohibited from access to the base or worksite for one (1) day or less per month, no adjustment in the contract time will be made. When the contractor is prohibited access for more than one (1) day per month, an adjustment to the contractor’s schedule will be made by the Contracting Officer (KO).

3. DAILY REPORTING: The contractor Project Manager shall be responsible to report to the COR or Government project inspector at 0800 during normal work days, or at 1700 during night shifts . The contractor project manager shall provide the COR or Government project inspector with a daily report detailing the work which is being accomplished at the worksite. Failure on the project manager’s part to report to the COR or Government project inspector will result in a letter being forwarded to the KO recommending appropriate action by the KO for the contractor’s lack of coordinating the daily work report.

4. NOTIFICATION OF INSPECTIONS: Prior to starting work at the work site, the contractor shall inform the COR of the actual date that the contractor intends to start work. The contractor shall also give the COR or project inspector no less than a seven (7) work day notice prior to each concrete placement, asphalt placement field test, protective coating, or any other work deemed necessary by the COR or project inspector. The contractor shall also give at least a seven (7) work day written notification of the pre-final and final inspections to the COR. The Construction Management Element of the 8th Civil Engineering Squadron is located in building #705, Kunsan Air Base, Korea; base phone extension is 782-6197 or commercial (063) 470-6197

5. CLOSE-OUT/TURNOVER MATERIALS: The contractor shall be responsible for providing the following materials as part of final turnover to the U.S. Government: AS-built drawings shall be submitted to COR for review and acceptance in electronic format utilizing AutoCAD 2010 or higher and submitted on CD/DVD format (3 copies). Operations and Maintenance (O&M) training shall be provided to U.S. Government personnel on new mechanical systems NLT (7) work days, not counting weekends, prior to final acceptance. O&M Manuals shall be submitted in both electronic and hard copy format (3 copies each) (7) work days prior to final acceptance.

Turnover of all new facility keys and salvageable material (if any) shall be submitted to COR or project inspector.

Contractor shall prepare DD form 1354 (Transfer and Acceptance of DOD Real Property) with type and quantity of construction material installed. When all materials have been turned over, the COR or project inspector will notify the KO so that the final payment may be released. Up to fifteen (15%) percent of the total contract amount may be withheld pending complete turnover of material stated in this paragraph

6. AIR FORCE MATERIALS: All salvageable materials removed from the worksite shall remain the property of the U.S. Government. All other such materials shall be disposed of by the contractor IAW AF regulations, upon coordination with the COR or project inspector. Applicable AF regulations include AFI 32-7001 (Environmental Management), AFPAM 32-7043 (Hazardous Waste Management Guide), AFI 32-1052 (Facility Asbestos Management), AFI 32-7042 (Waste Management), UFC 4-451-10N (Hazardous Waste Storage, and UFC 1-900-01 (Methods for the Reduction, Reuse, and Recycling of Demolition Waste) and their source reference documents.

Unclear or conflicting information between these documents can be clarified via RFI from the contractor to 8

CES/CENMC.

7. CONTRACTOR’S EQUIPMENT: All contractor equipment used in the performance of this contract shall be subject to a functional and safety inspection(s) at any time by the COR or project inspector IAW U.S. Air Force Safety Regulations and EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual. Any equipment found not to be functional or safe shall be immediately repaired, replaced, or removed from the worksite by the contractor. Additionally, the contractor will provide the COR or construction inspector a listing of all equipment to be used on site prior to the start of work, NLT (10) days after NTP. Applicable U.S. Air Force Safety Regulations include UFC 3-560-01 (Electrical Safety, O&M; with Change 4), AFI 32-1064 (Electrical Safe Practices), AFI 91-302 (Air Force Occupational and Environmental Safety, Fire Protection, and Health Standards) and AFPAM 91-210 (Contract Safety... although this is more for our use in setting up contracts than for the contractor in executing them) and their source reference documents. Unclear or conflicting information between these documents can be clarified via RFI from the contractor to 8 CES/CEPMC.

8. MATERIAL COMPLIANCE: The contractor shall be responsible to ensure that all materials used in the performances of the contract meet the specifications and requirements of this contract. Material(s) not meeting the specifications or not approved on AF Form 3000, Material Approval Submittal (or shall not be transported to the worksite. The COR or project inspector will be the approving authority for all materials used in the performance of this contract. All material(s) shall be new and the standard product of a manufacturer who is regularly engaged in the manufacturing of such products. Any materials used in the performance of this contract not approved on an AF Form 3000 shall be removed and replaced, at the expense of the contractor, and not the U.S. Government unless the government determines that the item does meet the specifications in the contract.

9. CONTRACTOR-FURNISHED MATERIAL AND CONTRACTOR-FURNISHED EQUIPMENT

(CFM/CFE): All CFM/CFE, including construction equipment, will not be permitted to enter Kunsan Air Base unless each item is approved on a DD Form 1149, Requisition and Invoice/Shipping Document. The contractor shall be responsible to notify the COR or project manager at least three (3) work days prior to the arrival of, or removal of, any CFM/CFE at Kunsan Air Base. DD Form 1149 is available on open source internet (http://www.dcma.mil/dcman/NPP/files/dd1149.pdf).

10. CONTRACTOR’S TEMPORARY FACILITES: Erection of any facility by the contractor shall be coordinated with the COR or project inspector. An approved U.S. Government Real Estate Permit from the Base Civil Engineer (BCE) shall be in the contractor’s possession before erection of any facility. Any contractor erected facility shall be removed and the area cleaned within seven (7) calendar days in normal installation access areas and

(5) duty days in installation restricted areas after completion of the contract requirements and prior to final invoice payment.

11. Air Force (AF) FORM 103, BASE CIVIL ENGINEERING WORK CLEARANCE REQUEST:

Prior to starting any work, The contractor shall be responsible to have a valid AF Form 103, Base Civil Engineering Work Clearance Request (dig permit) in his possession. No work shall be performed under this contract without a valid AF Form 103 in the contract’s possession. Request for a Base Civil Engineering Work Clearance Request shall be submitted to the COR or project inspector a minimum of ten (10) calendar days prior to starting any work under the terms of this contract.

12. SAFETY: AFOSHSTD91-501 (Air Force Occupational and Environmental Safety, Fire Protection, and Health Standard) shall be complied with. All AFOSH standards shall be complied with as applicable. The contractor shall also comply with applicable sections of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual.

13. FIRE PROTECTION: The contractor shall comply with the provisions of the Base Fire Protection program, 607 AOGI (Air Operations Group Instruction) 32-2001. The contractor shall provide suitable fire extinguishers at any material storage area constructed by the contractor as well as at the work site(s). The contractor shall ensure that all contractor employees understand that there will be no smoking inside or within 50 feet of any U.S. Government facility, at any time, during performance of work under this contract. The COR or project inspector will identify to the contractor the designated smoking area(s) for the contractor’s employees prior to starting any work. The contractor shall ensure that all contractor employees are aware of the designated smoking area(s) and shall ensure that all contractor employees use the designated smoking area. Any contractor employee found smoking in any U.S.

Government facility, at any time, will be removed from the work site by the COR or project inspector. The COR or project inspector will notify the KO of the removal of any contractor employee for violation of the “no smoking” policy.

14. BURNING/WELDING OPERATIONS: The contractor shall be responsible to obtain a burning/ welding permit prior to any burning or welding operation. The contractor shall notify the COR or project inspector not less than five (5) work days prior to such operations and shall return the permit to the U.S. Government inspector at the completion of the permit period. Contractor shall provide fire watch during all open flame/ welding work.

15. VERIFICATION OF ACTUALITIES: (FAR Clause 52.236-2 Site Visit)

16. HOUSEKEEPING: (FAR Clause 52.236-12 Cleaning Up / 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvement & 52.236-13 Accident Prevention)

17. BASE ACCESS: The contractor shall be required to obtain base access to Kunsan Air Base to perform the requirements of this contract. The contractor shall be responsible to submit a base access request letter no later than five (5) calendar days prior to start this contract. It shall be the responsibility of the contractor to prepare the necessary base access paperwork IAW USFKregulation 190-7, Installation Access Control, and submit it to the COR or project inspector. USFK regulation 190-7 is available on open source internet (http://8tharmy.korea.army.mil/g1_AG/Programs_Policy/PublicationsRecords/Regu lations/USFK/USFK%20Reg%20190-7%20Installation%20Access%20Control2013.pdf

18. REPAIR WORK: It shall be the contractor’s responsibility to repair all areas of patch work to match existing areas. This work shall include all areas inside of the facility as well as any other areas that the contractor may have damaged during the performance of work under the terms of this contract.

19. CONTRACTOR’S RESPONSIBILITIES: It shall be the responsibility of the contractor to have full control of all contractor personnel during the performance of work under the terms of the contract. The contractor shall be responsible to ensure that no contractor personnel receive any instructions for addition/deletion of work from any Government personnel including the COR or project inspector. Any instructions for additional work shall only be issued by the KO. The contractor shall be responsible for any cost incurred for any additional work, which is not identified in the contract documents to include the specifications or on the contract drawings. The contractor shall be responsible to inform the COR or project inspector of any request form any Government personnel for additional work. The contractor shall provide the COR or project inspector with name and office of the individual requesting the additional work and the type of additional work being requested. The COR or project inspector will take the necessary actions to inform the KO to prevent such situation.

20. PROGRESS SCHEDULE: The contractor shall prepare and submit the AF Form 3064, Contract Progress Schedule no later than ten (10) calendar days after notice to proceed is issued. The contractor shall submit three (3) copies of the AF Form 3064 for approval by the COR or project inspector and KO.

21. DRAWING SUBMITTALS: All drawings shall be submitted prior to the start of any work. Any additional drawings (As-built, field changes, etc.) shall be submitted to the COR or project inspector no later than ten (45) calendar days prior to contract completion for delivery orders with period of performances (PoP) less than 180 days and (60) days prior to contract completion delivery orders with PoP’s greater than 180 days. If submittal cannot be submitted within the timeframe the contractor must notify the COR or project inspector in writing why he/she cannot meet the requirement.

22. UTILITY OUTAGES/ROAD CLOSURES: The Contractor shall be the responsibility of the contractor to request, in writing, to the COR or project inspector, a minimum of thirty (30) calendar days in advance for any water outage, electrical outage, or road closure. The contractor shall provide a requested date and estimated time for the water outage, electrical outage, or road closure. The COR or project inspector will be responsible for determining the impact of the water outage, electrical outage, or road closure. The COR or project inspector will also be responsible for the processing of the contractor’s request for a water outage, electrical outage, or road closure. The contractor shall have written approval from the COR or project inspector before any water outage, electrical outage, or road closure.

23. ASBESTOS CONTAINING MATERIALS: No asbestos containing materials (ACM) shall be used under this contract. ACM is any material containing more than 1% asbestos by weight, either along or mixed with other fibrous on non-fibrous materials.

24. OZONE DEPLETING SUBSTANCES: No Class I ODS shall be used in the performance of this contract, nor be provided as a part of the equipment. This prohibition shall prevail over any other provision, specification, drawings or referenced documents.

25. MATERIAL SAFETY DATA SHEETS (MSDS): It shall be the responsibility of the contractor to furnish Material Safety Data Sheets (MSDS), in English and Korean, for all hazardous material(s) used under the terms and conditions of this contract. The type of materials that the contractor shall submit MSDSs for include, but is not limited to, paint, primer, lacquer, stain, joint compound, caulking, exterior insulation systems, emergency exit lights, cleaning fluids, oil, etc., and any other type of product deemed necessary by the Contracting Officer’s Representative (COR) or project inspector, required by U.S. Government Environment Laws and Regulations, or Korean Environmental Laws and Regulations.

a) SUBMITTAL REQUIRMENTS:

(1) The contractor shall be responsible to process these Material Safety Data Sheets (MSDS) on an AF Form 3000, Material Approval Submittal. The AF Form 3000 shall be submitted to the COR or project inspector no later than fifteen (15) calendar days after the Notice to Proceed (NTP) is issued by the Contracting Officer (KO). The contractor shall submit four (4) copies of the AF Form 3000 with carbon paper. The contractor shall submit the AF Form 3000 to the COR or project inspector for review prior to submitting the AF Form 3000 with carbon paper. It will be the responsibility of the COR or project inspector to verify the AF Form 3000 to ensure that all hazardous materials are submitted in the proper format.

(2) It shall be the responsibility of the contractor to list each type of hazardous material on the AF Form 3000. The contractor shall also be responsible to list the quantity, unit of measure (i.e.: each, liter, gallon, etc.), and size of container(s). It will be the responsibility of the COR or project inspector to verify these quantities and containers prior to initialing off on the AF Form 3000.

(3) After verification of all hazardous materials by the COR or project inspector and the contractor, the COR or project inspector will then be responsible to process this AF Form 3000. After receiving approval for all hazardous materials, it will be the responsibility of the COR or project inspector to provide the KO and contractor with a copy of the signed AF Form 3000 for the official files.

(4) After receiving approval of all hazardous materials required under the terms and conditions of this contract, the contractor shall be responsible to process these Material Safety Data Sheets (MSDS) through the HazMart Pharmacy located in building #823, military telephone DSN 782-5247, commercial telephone (063) 470-5247. The HazMart Pharmacy will be responsible to issue a bar code for each hazardous material that shall be affixed to each container by the contractor. The contractor shall be responsible to post an approved copy of the AF Form 3000 at the worksite storage area as well as keep a signed copy by AF Form 3000 in the contractor’s field office.

(5) It shall be the responsibility of the contractor to provide the COR with a new AF Form 3000 for any additional hazardous materials brought onto Kunsan Air Base throughout the term of the contract. This shall include any new materials as well as any additional quantities over and above the originally quantities.

(a) HAZARDOUS MATERIALS STORAGE: The contractor shall be responsible to store all hazardous materials in an approved storage container or storage area. This storage container may be either a metal or wood locker which is capable of being secured when not in use as well as at the end of each workday. The contractor shall be responsible to provide an approved storage location for large quantities of hazardous materials which can also be secured when not in use as well as at the end of each workday. The contractor shall be responsible to keep an approved AF Form 3000 on the inside of the door to the storage container and also keep a copy of the approved AF Form 3000 posted at the storage area

(b) DISPOSAL REQUIREMENTS FOR HAZARDOUS MATERIALS: The contractor shall be the responsibility of the contractor to remove and dispose of any remaining hazardous materials upon completion of the contract to include the removal of hazardous materials from the worksite as well as the contractor’s field office area. The contractor shall be responsible to dispose of these remaining hazardous materials, off the installation, at the contractor’s own expense, in strict accordance with existing Korean Environmental Laws and Regulations. The contractor shall be responsible to notify the COR or project inspector prior to disposing of any hazardous materials off the installation to ensure that all hazardous materials are properly handled and disposed of correctly. After use of final disposal of all hazardous materials, it will be the responsibility of the COR or project inspector to notify the HazMart Pharmacy of the final disposition of the hazardous material in order for the HazMart Pharmacy to update the AF-EMIS database.

(c) HAZARDOUS MATERIAL SPILLS: In the event that the contractor accidentally spills any hazardous materials at the worksite, the contractor shall be the responsibility of the contractor to immediately notify 8 CES/CEAN, Environmental section located in Building #705, military telephone DSN 782-6239/6240, commercial telephone (063) 470-2312/6337. The contractor shall be responsible to identify the location of the spilled material, the quantity of spilled material, and the type of spilled material. The contractor shall also be responsible to notify the COR or project inspector. The contractor shall not under any conditions, remove and dispose of any spilled hazardous material(s) without prior approval of 8 CES/CEAN.

26. DISPOSAL REQUIRMENTS: The contractor shall be responsible to designate, in writing, to the COR or project inspector the exact location(s) for the disposal of the steel revetment, soil, and concrete. The contractor shall also be responsible to provide the COR or project inspector with a copy of the license for the disposal location(s) issued by the Korean Government. The contractor shall be responsible to accompany the COR or project inspector on a site visit of the disposal location(s) prior to the removal and disposal of any steel revetment, soil, or concrete.

The COR or project inspector will be responsible to complete a DD Form 1901, Plant Visit Request/Report for each of the disposal locations. The COR or project inspector will be responsible to provide the KO with a copy of the DD Form 1901 identifying any discrepancies which may not conform to the contract requirements. It will be the responsibility of the KO to review this DD Form 1901 and to determine any corrective actions that the contractor shall be responsible to comply with. The contractor shall also be responsible to notify the COR immediately in the event that the disposal location(s) are no longer licensed or capable of disposing of the steel revetment, soil, or concrete in accordance with AFI 32-7042 (Waste Management).

27. ESCORT PRIVILEGE: Personnel of the Contractor or any representative of the contractor entering Kunsan AB shall abide by all security regulations imposed by Installation Commander at all times and shall be subject to security checks. Contractor personnel and property shall be subject to search and seizure upon entering the confines of the installation, while on, and upon leaving the confines of Kunsan AB.

a. Escort Privileges: The Contractor shall be responsible to obtain escorting privileges on base passes for the Contract Manager (CM), Quality Control (QC) Manager, Safety Manager with a limit of three (3) persons and one

(1) vehicle pass per base pass. It is the Contractor’s responsibility to ensure that the escorting official has full control over all escorted individuals at all times. Any individual found on the installations unescorted will be removed from the installation and the escort official’s escorting privileges will be immediately withdrawn. Any individual removed from these installations will not be authorized further access to these installations.

b. Return Post Passes: On the contract completion date, the contractor shall turn in all passes that were issued for this contract to the sponsor and final payment will not be processed until such items are returned.

1A-6. Contract Data Requirements List (CDRL)

Provide the data as indicated below to the COR. All reports, submittals, logs, and information provided to the Government shall be electronic and compatible with Microsoft Office 2007™ such as Excel™, Word™, and others. “Compatible” means the document can be opened using the appropriate Microsoft Office™ component without any discernible effect on the text (e.g.,loss of data) or the formatting of the document:

Item No.

Description Format Frequency Paragraph Reference

The Written Notification of Pre-final and Final Inspection

Contractor’s Format (one copy)

A minimum of 7 work days in advance for inspection

General Condition Para. 4.

002 As-Built Drawings

Contractor’s Format (one hard copy and three CD copies)

Prior to final acceptance

General Condition Para. 5.

List of Equipment to Be Used on Site

Contractor’s Format (one copy)

NLT (10) days after

NTP

General Condition Para. 7.

004 Progress Schedule AF Form 3064 (three copies)

NLT (10) calendar days after NTP

General Condition Para. 20.

Utility Outage/Road Closures Request

Contractor’s Format (one copy)

A minimum of 30 calendar days in advance for outage

General Condition Para. 22.

006 Material Approval Submittal AF Form (four copies)

NLT 15 calendar days after NTP

General Condition Para. 25. a. 1.

Approved by: __//signed/cjc/15 Jun 2016//__ CHRISTIAN J. CLARK, 1st Lt, USAF

Chief of Design

Date: 15 Jun 2016 Telephone: 782-5163

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 N/A N/A N/A Government 0002 N/A N/A N/A Government

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC

0001 130 dys. ADC 1 8 CES/CEACF

MR. KIM YONG HYUN

8 CES/CEX

KUNSAN AIR BASE KOREA

APO AP 96264

KOREA (THE REPUBLIC OF)

782-6266

F2L3CE

0002 N/A N/A N/A N/A

Section G - Contract Administration Data

Section I - Contract Clauses

CLAUSES INCORPORATED BY FULL TEXT

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 120 days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $100.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

52.211-13 TIME EXTENSIONS (SEP 2000)

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

52.232-18 AVAILABILITY OF FUNDS (APR 1984)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least twenty-five (25) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this contract. References in the specifications to equipment, material, articles, or patented processes by trade name, make, or catalog number, shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications, unless otherwise specifically provided in this contract.

(b) The Contractor shall obtain the Contracting Officer's approval of the machinery and mechanical and other equipment to be incorporated into the work. When requesting approval, the Contractor shall furnish to the Contracting Officer the name of the manufacturer, the model number, and other information concerning the performance, capacity, nature, and rating of the machinery and mechanical and other equipment. When required by this contract or by the Contracting Officer, the Contractor shall also obtain the Contracting Officer's approval of the material or articles which the Contractor contemplates incorporating into the work. When requesting approval, the Contractor shall provide full information concerning the material or articles. When directed to do so, the Contractor shall submit samples for approval at the Contractor's expense, with all shipping charges prepaid. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection.

(c) All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS (APR 1984)

(a) The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

(b) The Contractor shall protect from damage all existing improvements and utilities

(1) at or near the work site, and

(2) on adjacent property of a third party, the locations of which are made known to or should be known by the

Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

52.236-12 CLEANING UP (APR 1984)

The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer.

52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer's notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed.

52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not--

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the

Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may (1) by contract or otherwise, replace or correct the work and charge the cost to the Contractor or (2) terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the…