W90VN624R0009-0001.pdf

PDF 142 KB Posted

Attached to
Install and assemble the heavy- duty expandable conveyor system
Solicitation number
W90VN624R0009
Issued by

About this file

This document is an amendment to Solicitation W90VN624R0009 for the installation and assembly of a heavy-duty expandable conveyor system at the Joint Military Mail Terminal (JMMT) in Incheon Airport, Korea. The key details are:

The amendment updates the Statement of Work, drawing diagram, and extends the solicitation response deadline from 22-Feb-2024 to 22-Apr-2024. The contractor shall provide all personnel, equipment, and materials to install and assemble the new conveyor system, as well as remove and dispose of the old system in accordance with Republic of Korea guidance. The contractor must ensure all materials meet the contract specifications and are new, standard products. Delivery and installation shall occur between 0800-1500 Monday to Friday, with possible escort required. Government acceptance is required prior to full payment after final installation. The warranty period is one year from final acceptance.

View the file

Other files

File Type Posted
JMMT Conveyor Specifications FINAL.pptx PPTX presentation
W90VN6-24-R-0009.pdf PDF
JMMT Conveyor System Specifications diagram.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

411TH CSB, KOREA - RCO OSAN

POC: MR. TRAN, PON V.

DSN: 315-757-6011

PON.V.TRAN.CIV@ARMY.MIL

APO AP 96278-2039

UNITED STATES

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this modification is updating the SOW, draw ling diagram and closing date.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Apr-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W90VN624R0009

X 9B. DATED (SEE ITEM 11)

22-Jan-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Apr-2024

CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO OSAN, UNIT #2039

APO AP 96278-2039

UNITED STATES

W90VN6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W90VN6

FACILITY CODECODE

EMAIL:TEL:

W90VN624R0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 22-Feb-2024 01:00 PM to 22-Apr-2024 01:00 PM.

SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

The contractor shall provide all personnel, equipment and materials to install and assemble the conveyor system with Auto Bar Code Scanner at the Joint Military Mail Terminal (JMMT) in Incheon Airport. The contractor shall remove and dispose of the old conveyor system.

To:

The contractor shall provide all personnel, equipment and materials to install and assemble the conveyor system at the Joint Military Mail Terminal (JMMT) in Incheon Airport. The contractor shall remove and dispose of the old conveyor system.

The following have been modified:

SOW

STATEMENT OF WORK

CONVEYER SYSTEM at Joint Military Mail Terminal (JMMT) in Incheon Airport

1. General: The contractor shall provide all personnel, equipment and materials to install and assemble the conveyor system with Auto Bar Code Scanner at the Joint Military Mail Terminal (JMMT) in Incheon Airport. The contractor shall remove and dispose of the old conveyor system in accordance with the Republic of Korea guidance.

2. Scope of work: Conveyer System with Auto Bar Code Scanner Delivery & Installation.

3. Material Compliance: The contractor shall be responsible to ensure all materials used in performance of this contract meet the specifications and requirements of this contract.

All material(s) shall be new and standard product of a manufacture who is regularly engaged in the manufacturing of such products.

W90VN624R0009

4. Delivery: The contractor shall deliver the conveyor system with Auto Bar Code Scanner to JMMT in Incheon Airport, Korea.

5. Contractor shall dismantle and dispose of old conveyor system from JMMT in Incheon Airport, Korea.

6. Hours of Operation: Delivery and Installation can be made from 0800 - 1500 (Monday to Friday).

7. Contractor Access: Escort may be required on delivery day.

8. Government Acceptance:

A. Upon Government acceptance of contractor submittals, the contractor shall deliver the conveyor system. with Auto Bar Code Scanner.

B. POCs are Ms. Lourene Gonzales, Chief DAFC, 315-722-6123

9. Contractor Payment: Once cargo securing items are delivered and installed, payment will be paid in full after Government acceptance.

10. Warranty Conditions:

A. Extent of Contractor Obligations: The contractor warranty shall extend to all defects discovered during the warranty period, but not to include damage cause by the Government.

B. Deficiencies: Warranty will read that the contractor will repair or replace and defective items at the expense of the contractor.

C. Duration of Warranty: The duration of contractor warranty shall continue for a period of one (1) year from date of final acceptance of the work.

11. See attached diagram for additional specification and drawing.

(End of Summary of Changes)