F3J3CE8243A001

THIS IS WORK PLAN MATOC RFP FOR THE FOLLOWING CONTRACTORS ONLY:

CONTRACT NO.: W91QVN-18-D-0100, -0102, -0103, -0104, -0105, -0107, -0109, -0111, -0112, -0134, -0135, -0136, -0137.

OFFERORS MUST COMPLY WITH THE FOLLOWING:

A. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit clause in Section L for the schedule.

B. Submission of Proposals

(1) Proposal packet: It shall be submitted by 1400 Hrs on the closing date of RFP through FBO.

a. Priciing Proposal

b. Offer Breakdow n

c. Design Data

d. Documents to establish the offeror's eligibility for aw ard under this LCS program.

e. Completion of Section K (5152.204-4032)

C. If the contractor is unable to submit the proposal in response to this RFP, the contractor shall submit a "No-Offer Letter" by date and time specif ied in this solicitation.

MR. PAK, SIN-NAM 031-661-5761

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

01-Nov-2018

(RFP)

(IFB)

X

CALL:

REPAIR ROOFS FOR B622 & 2421, OSAN AB

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________90 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________27 Nov 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

RCO OSAN, UNIT #2039

APO AP 96278-2039

UNITED STATES

W90VN6

PAGE OF PAGES

1 OF

CODE W90VN6

(Title, identifying no., date):

12B. CALENDAR DAYS

02:00 PM (hour)

Sealed envelopes containing offers

411TH CSB, KOREA - RCO OSAN

POC: MR.PAK, SIN NAM

011-82-31-661-5761

SINNAM.PAK2.LN@MAIL.MIL

APO AP 96278-2039

UNITED STATES

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

SMYU 19-1042L

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: 011-82-31-661-5761 FAX: 011-82-31-661-3261

W90VN619R0008 58

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W90VN619R0008

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job Repair Roof for B622 and 2421

FFP

FOB: Destination

PURCHASE REQUEST NUMBER: F3J3CE8243A001

PSC CD: Z1BZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Lot War Hazard

FFP

Estimated Cost for War Hazard Losses is Zero (0).

FOB: Destination

PSC CD: Z1BZ

NET AMT

Notice to Offerors Regarding Logistics Cost Sharing (LCS) Program

This solicitation is conducted under the LCS program and will result in a contract between the Government of the Republic of Korea (ROK) and the contractor. ROK will directly pay the contractor. No appropriated funds of the United States (US) shall be obligated for payment due under this contract.

In accordance with the International Agreement between the US and ROK, titled “Amendment to the Implementing Agreement between the United States Forces Korea and the Republic of Korea Ministry of National Defense Concerning Logistics Cost Sharing” (hereinafter “International Agreement”), signed by the parties on 14 October 2015:

"The parties hereby agree that all LCS work must be accomplished in the ROK or its territorial waters and that all equipment and supplies that are to be acquired with ROK Government funds shall be manufactured in the ROK, and all LCS service work shall be carried out by Korean contractor(s), the Korea Railroad Corporation, or the ROK military. The term ‘Korean contractor(s)’ is defined as an entity, that, including its parent, is a domestic corporation under the Korean Tax Act and whose domestic status is recorded in the Certified Copy of Register or its successor document. A parent is defined as an entity that holds more than 50/100 of the total issued and outstanding shares in another company, as reflected in the Stock Change Certificate.”

See Section L, Instructions to Offerors, for submission requirements related to LCS solicitations.

Availability of Funds

“Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available.”

Therefore, please specify the validation date of your quote such as “This proposal is good until __________ or this proposal is valid for ___________ days.

Section C - Descriptions and Specifications

SOW

TECHNICAL PROVISIONS - I

STATEMENT OF WORK

SMYU 19-1042L

REPAIR ROOFS FOR B622 & 2421

OSAN AB, ROK

1. DESCRIPTION: The work to be performed for completion of this project shall be as described in general below.

1.1. The contractor shall provide all labor, tools, equipment, supplies, and any other resources necessary to accomplish the scope of work contained herein and as included in the drawings and specifications.

1.2. All work shall be completed IAW drawings and specifications.

2. PRINCIPLE FEATURES: This project is K-work (repair) and also includes the following principle features:

2.1. ARCHITECTURAL WORKS: All works shall be in accordance with the attached particular specifications and contract drawings.

BLDG 622

2.1.1 Provide double steel pipe scaffolding around the buildings including fabricating and dismantling.

2.1.2 Repair/patch the deteriorated/damaged metal flashing, roof panel, fascia & soffit before applying the coating system.

2.1.3 Remove all scale, dirt, any other contaminants and apply metal primer to all rusted area to prepare for applying acrylic fluid-applied water proofing coating system.

2.1.4 Apply one coat of base coat to the substrate especially on the vertical seams, horizontal laps, roof penetrations, joints, and exposed mechanical fasteners.

2.1.5 Lay out fabrics into the wet base coat and apply a second coat of base coat immediately applied over the top to saturate the fabrics fully (The base coat shall only be applied by manufacture’s recommended/approved tools like brushes - unapproved rolling and/or spraying are strictly prohibited).

2.1.6 Apply 2 coats of finish coat entirely according to the manufacture’s standard procedure of the acrylic fluid-applied water proofing coating system.

2.1.7 Apply new paint/coating on exterior metal surface like flashing, rain gutters and downspouts. All colors of exposed surface/part shall comply with the Osan AB Architectural Compatibility Plan (Osan AB ACB).

2.1.8 Remove all construction debris originated from the project and clean up the job site.

2.1.9 The contractor shall be responsible to repair all damages to existing areas caused by the project and to match condition to adjacent areas.

BLDG 2421

2.1.1 Provide double steel pipe scaffolding around the building for temporary works including fabricating and dismantling.

2.1.2 Remove existing built-up roof sheet, wood nailer/cant, flashing, etc… and rigid insulations from the existing concrete roof slab entirely.

2.1.3 Clean and prepare the concrete roof slab surface by removing loose/flaking particles, grease, laitance, dust, dirt and other contaminant to apply TPO (Thermoplastic Polyolefin) sheet roofing system.

2.1.4 Install poly-isocyanurate board rigid insulation with vapor barrier, wood nailer/cant/blockings on the concrete roof slab (There shall be air spaces between the rigid insulations and wooden materials to protect contraction and expansion problems).

2.1.5 Install TPO sheet membrane over the rigid insulation board by hot air welded machine using the Mechanically Attached Application Method.

2.1.6 Replace existing metal flashing, drip edge, wood nailer/cant/blockings, rain gutters and downspouts with new ones.

2.1.7 Remove/reinstall existing mechanical/electrical stuff if necessary and any damages caused by this project shall be repaired or replaced to match existing condition to adjacent areas by the contractor.

2.1.8 Remove all construction debris originated from the project and clean up the job site completely.

TECHNICAL PROVISIONS - II

SPECIAL INSTRUCTIONS

1. SPECIAL REQUIREMENTS :

1.1. Government provides 30% of concept design for the contract and contractor shall accomplish and submit 100% design submittals (MATOC WORK PLAN). Following documents shall be submitted for government technical evaluation.

1.1.1. Design Data to be submitted for technical evaluation (Technical Evaluation Factor)

1.1.1.1. Submittal Drawings (Sub-Factor #1): It shall be consist of roof plan, front/side elevation, joint details, exterior finish schedule for B622 and roof plan, front/side elevation, section/roof edge/gutter/ridge/side lab details, exterior finish schedule for B2421. The finish schedule in the drawing shall clearly show all materials such as MPI approved paint/coating, acrylic fluid applied waterproofing materials, TPO roofing system using the finish schedule table categorized according to surface area, base material, FSC (Federal Standard Colors) number, surface preparation method, primer/first coat, intermediate coat, top coat, coating system DFT (Dry Film Thickness), MPI numbers/gloss levels in top rows and the targeted area such as roof, exterior wall, door/frame, trims in first column on left side.

1.1.1.2. Test Reports (Sub-Factor #2): The reports shall show if the acrylic fluid-applied water proofing coating materials meet the ASTM D 6083 and the TPO roof system meet the

ASTM D 6878.

Also the reports shall show if both system comply with class A fire rating as per ASTM E

108/UL790

or FM 4470 class 1.

*The test reports shall be signed by authorized official of certified independent testing laboratory and clearly specify the coating materials product name, manufacturer’s name on the report and POC contact info.

(Note) Ownership of Construction Drawings: The Government shall take full ownership of the drawings and design data submitted with the proposal and after contract award.

1.2. Taking part in the site visit orientation is strongly recommended. The site orientation will allow the offerors to check the actual field conditions to prepare proper proposals and more visibility in providing an offer breakdown which meets the requirements. Therefore no any modification requested by contractor will be allowed due to the differing site conditions or government design deficiencies during contract performance period.

1.3. Contract performance period is 90 calendar days after notice to proceed (NTP) except for the temporary airfield construction waiver (TACW), risk assessment (RA) and unexpected base operation or exercise period.

1.4. Time on target of the site release date will be discussed with user at the pre-con meeting after award.

1.5. This is the ROK LCS funded project. So, all of the construction materials used in this project shall be local ones and shall comply with the specification in this contract package since ROK LCS funds shall not to be used to purchase off-shore end products.

1.6. Final Site Adapted Drawing (100% Design Submittals): The awarded contractor shall complete and submit final site adapted drawings submittals in accordance with the actual field condition and design analysis. Some contract drawings provided by Government might not match the existing field condition and requirements specified in the project. Therefore the final site adapted drawing submittals shall reflect on the actual field conditions and requirements specified in the project accurately and meet the Government’s design intent and achieves the desired quality end-products. The contractor shall be responsible for its own design, work quality, full compliance with the solicitation and its accepted proposal, and shall be liable for its faults. The contractor shall complete and submit the 100% design submittals package in 21 calendar days after receipt of notice to proceed (NTP). The 100% design submittals package shall not be reproductions of contract drawing and must be approved by the Government prior to commence of any construction.

Submittal Drawing: Roof plan, Front/Side elevation, Details, Exterior finish schedule.

Design Analysis: N/A

2. SECURITY REQUIRMENTS: (a) Contractor’s personnel or any representative of the contractor entering installation/base shall abide by all security regulations imposed by Installation Commander or Base Commander at all times and shall be subject to security checks. Contractor’s personnel and property shall be subject to search and seizure upon entering the confines of the installation/base, while on, and upon leaving confines of the installation/base. (b) Escort Privileges: The contractor shall be responsible for adhering to the escorting privileges on base passes for the Program Manager (PM), Contract Manager (CM), CQC System Manager (CQCSM), Site Safety Health Officer (SSHO) with a limitation of three persons and one vehicle access per base pass. It is the contractor’s responsibility to ensure that the escorting official has full control over all escorted individuals at all times. Any individual found on the installations unescorted will be removed from the installation or base and the escort officials escorting privileges will be immediately withdrawn. Any individual removed from these installations/bases will not be authorized further access to these installations/bases and may further be subject to other Government actions. (c) Return Post/Base Passes: On the contract completion date, the contractor shall turn in all passes to the sponsor that were issued for the contract and final payment will not be made until such items are returned.

TECHNICAL PROVISIONS - III

TECHNICAL DETAIL SPECIFICATOIN

1. GENERAL: This project shall comply with the “Standard Technical Specifications and Standard Detail Drawings for OMA Projects, Korea” dated 30 November 2015 issued by the Department of the Army, Installation Management Agency, Korea Region Office. The most current specifications (OMA Specification 2014, Revision-1) and standard drawings are available at the Engineering Flight, 51st Civil Engineer Squadron, Osan AB, Unit 2129, APO AP 96278-2129 and also are located on the Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx

2. OTHER APPLICABLE PARTICULAR SPECIFICATIONS OR GUIDES: The project shall comply with the “Osan AB Architectural Compatibility Plan (Osan AB ACP)” dated 01 January 2009 by the 51st Civil Engineer Squadron (51 CES), and the attached particular specification “SECTION 07141 ACRYLIC FLUID-APPLIED WATERPROOFING” and “SECTION 07540 THERMOPLASTIC POLYOLEFINE

SHEET ROOFING (TPO)”.

PARTICULAR SPECIFICATION

SECTION 07141

ACRYLIC FLUID-APPLIED WATERPROOFING

PART 1 GENERAL

This specification covers a liquid-applied water-dispersed 100 percent acrylic elastomeric latex coating used for roof waterproofing. This specification also covers a water-repellent coating applied to concrete or masonry wall surfaces.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)

ASTM B 117 Standard Practice for Operating Salt Spray (Fog) Apparatus

ASTM C 794 Standard Test Method for Adhesion-in-Peel of Elastomeric Joint Sealants

ASTM D 471 Standard Test Method for Rubber Property - Effect of Liquids E1-1999

ASTM D 522 Rev A Standard Test Method for Mandrel Bend Test of Attached Organic Coatings

ASTM D 523 Standard Test Method for Specular Gloss

ASTM D 562 Standard Test Method for Consistency of Paints Measuring Krebs Unit (KU) Viscosity Using a Stormer-Type Viscometer

ASTM D 624 Standard Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomer

ASTM D 722 Standard Test Method for Grease Resistance of Paper

ASTM D 903 Standard Test Method for Peel or Stripping Strength of Adhesive Bonds

ASTM D 1475 Standard Test Method for Density of Liquid Coatings, Inks, and Related products

ASTM D 1640 Standard Test Method for Drying, Curing, or Film Formation of Organic Coatings at Room Temperature

ASTM D 1644 Standard Test Method for Nonvolatile Content of Varnishes

ASTM D 1653 Standard Test Method for Water Vapor Transmission of Organic Coated Films E1-1999 R

ASTM D 1712 Standard Practice for Resistance of Plastics to Sulfide Staining

ASTM D 1729 Standard Practice for Visual Appraisal of Colors and Color Differences of Diffusely-Illuminated Opaque Materials

ASTM D 2196 Standard Test Methods for Rheological Properties of Non- Newtonian Materials by Rotational (Brookfield) Viscometer

ASTM D 2244 Standard Test Method for Calculation of Color Differences from Instrumentally Measured Color Coordinates

ASTM D 2370 Standard Test Method for Tensile Properties of Organic Coatings

ASTM D 2697 Standard Test Method for Volume Nonvolatile Matter in Clear of Pigmented Coatings R

ASTM D 3359 Standard Test Method for Measuring Adhesion by Tape Test

ASTM D 3776 Standard Test Method for Mass Per Unit Area (Weight) of Fabric

ASTM D 3786 Hydraulic Bursting Strength of Knitted Goods

ASTM D 4214 Standard Test Method for Evaluating the Degree of Chalking of Exterior Paint Films

ASTM D 4798 Standard Test Method for Accelerated Weathering Test Conditions and Procedures for Bitumen Materials (Xenon-Arc Method)

ASTM D 5035 Standard Test Method for Breaking Force and Elongation of Textile Fabrics (Strip Method)

ASTM D 5201 Standard Practice for Calculating Formulation Physical Constants of Paints and Coatings

ASTM D 5733 Standard Test Method for Tearing Strength of Nonwoven Fabrics by the Trapezoid Procedure

ASTM D 6083 Standard Specification for Liquid Applied Acrylic Coating Used in Roofing

ASTM E 96 Standard Test Method for Water Vapor Transmission of Materials

ASTM E 108 Standard Test Methods for Fire Tests of Roof Coverings

ASTM E 514 Standard Test Method for Water Penetration and Leakage Through Masonry.

ASTM G 7 Standard Practice for Atmospheric Environmental Exposure Testing of Nonmetallic Materials

ASTM G 21 Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi

ASTM G 154 Standard Practice for Operating Florescent Light Apparatus for UV Exposure of Nonmetallic Materials

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01330

SUBMITTAL PROCEDURES:

SD-02 Shop Drawings Roofing System; G.

Drawings showing details, flashing details, fastening patterns where applicable for insulation, and expansion joint details.

Detail showing construction of water cutoffs to be used at membrane terminations at the end of a day's work to seal the roofing system from water intrusion.

SD-03 Product Data

Coating System; G.

Application; G.

Manufacturer's instructions for preparing and applying the membrane, flashings, seams, insulation, nailers and other accessories.

Material Safety Data Sheets (MSDS); All materials required to have MSDS.

SD-06 Test Reports: G.

Report signed by authorized official of a certified independent testing laboratory verifying conformance of properties as per ASTM D 6083 and class A fire rating as per

ASTM E 108/UL 790.

SD-07 Certificates

Applicator's Qualifications; G.

A copy of approved applicator letter and/or certificate as issued by the manufacturer of the elastomeric acrylic coating system.

1.3 DELIVERY, STORAGE, AND HANDLING

Deliver waterproofing materials in manufacturer's original, unopened containers, with labels intact and legible. Containers of materials covered by a referenced specification number shall bear the specification number, type, and class of the contents. Deliver materials in sufficient quantity to continue work without interruption. Store and protect materials in accordance with manufacturer's instructions, and use within their indicated shelf life. Materials shall be stored in an area specifically designated for that purpose, in accordance with manufacturer's recommendations, where temperatures will not be less than 10 degrees C (50 degrees F) or higher than 38 degrees C (100 degrees F). When hazardous materials are involved, adhere to special precautions of the manufacturer, unless precautions conflict with local, state, and federal regulations. Promptly remove from the site materials or incomplete work adversely affected by exposure to moisture or freezing. Store materials on pallets and cover from top to bottom with canvas tarpaulins.

1.4 JOB CONDITIONS

Do not apply elastomeric acrylic coating system components when the ambient and/or surface temperature is below 10 degrees C (50 degrees F) or above 43 degrees C (110 degrees F), if any surface moisture is present, when the dew point is within 3 degrees C (5 degrees F) of the surface temperature, or when there is a possibility of temperatures falling below 0 degrees C (32 degrees F) within a 24 hour period. Do not apply if weather conditions will not permit complete cure before rain, dew, fog or freezing temperatures occur. Do not spray apply if the wind velocity exceeds 16 kilometer per hour (10 MPH) without taking appropriate precautions to eliminate over-spray. Take all measures necessary to protect unrelated surfaces from coating over-sprays or spillage. Furnish all scaffolding and the necessary equipment to complete the work. Scaffolding shall comply with all requirements as to safety. Provide drop cloths and other forms of protection necessary to protect all adjoining surfaces to render them completely free of overspray and splashes. Any surfaces that have been damaged or splattered shall be cleaned, restored, or replaced. If sealant is applied prior to sealer, a test must be conducted prior to installation to verify compatibility of the sealer and sealant. For interior application, provide ventilation or forced air circulation during and after interior application of sealer until any odor is no longer evident.

1.5 WARRANTY

Upon completion of the roof coating system, a final inspection shall take place to determine the dry mil thickness of the fluid applied acrylic membrane and to verify that the system meets the manufacturer's requirements and project specifications for warranty.

The contractor shall notify all interested parties in advance of said inspection. Upon acceptance, deliver to the COR a copy of the fully executed 10-year for materials and 2-year for labor warranty.

PART 2 PRODUCTS

2.1 ROOF WATERPROOFING SYSTEM MATERIALS

A seamless, fluid applied 100 percent acrylic membrane system designed for application over asphalt built-up roofing, concrete, metal, roof tile, or composite shingle substrates.

2.1.1 Reinforcement Fabric

Non-woven, stitch bonded polyester fabric for reinforcement of joints, horizontal seams, non-crimped vertical seams, damaged areas, roof terminations and flashings, skylights and other openings, vents, conduits, HVAC equipment and other protrusions. Polyester fabric shall meet or exceed the following physical properties:

A. Weight: 3 oz / per square yard (102 grams/m2)

B. Tensile Strength (ASTM D 5034): 33 kg (length), 20 kg (width)

C. Elongation @ Break (ASTM 5034): 23 percent (length), 64 percent (width)

D. Mullen Bursting Strength (ASTM D 3786): 130 lbs per square inch

E. Tearing Strength (Trapezoid, ASTM D 3787): 15 lbf (length), 20 lbf (width)

F. Breaking Force (1" cut strip, ASTM D 5035): 30 lbf (length), 15 lbf (width)

2.1.2 Fluid-Applied Base Coat (Primer or Foundation Coat)

100 percent pure acrylic co-polymer internally plasticized to maintain elastomeric properties, designed for adding film build prior to application of the intermediate and finish coats.

2.1.3 Fluid-Applied Intermediate Coat and Finish Coat

100 percent pure acrylic co-polymer in the specified finish color internally plasticized to maintain elastomeric properties, designed to provide a permanently flexible, weather-resistant topcoat. Coating material and coating shall meet or exceed all properties specified in ASTM D 6083, Table 1, Liquid Property Requirements, and Table 2, Film Physical Property Requirements for Acrylic Roof Coatings, as verified by a certified independent testing agency.

TABLE 1

Liquid Property Requirements

Physical Property ASTM Designation Requirements

Viscosity Viscosity D 562 85 to 141 KU Viscosity D 2196 12,000 to 85,000 cps Volume Solids D 2697 greater than 50 percent Weight Solids D 1644 greater than 60 percent

TABLE 2

Film Physical Property Requirements for Acrylic Roof Coatings

Physical Property ASTM Designation Requirements Viscosity Initial Percent Elongation (break)

D 2370 minimum 100 percent @23 degree C (73 degree F)

Initial Tensile Strength (minimum stress)

D 2370 minimum 200 psi (1.38 MPa) @23 degree C (73 degree F)

Final Percent Elongation (break) after accelerated weathering 1000 Hrs.

D 2370 minimum 100 percent @23 degree C (73 degree F)

Presence D 1653 maximum 50 perms (17.2 x 10 - 10 kg/s.m2.Pa)

Water Swelling D 471 maximum 20 percent (mass)

Accelerated Weathering 1000 hours

D 4798 No cracking or checking

Adhesion C 794 or D 903 minimum 2.0 pli (350 N/m) wet

Fungi Resistance G 21 Zero Rating Tear Resistance D 624 >60 lbf/in. (21 kN/m) Low Temperature Flexibility after 1000 hours accelerated weathering

D 522 minimum pass 1/2 in.

mandrel -18 degree C (-degree F)

2.1.4 Fluid-Applied Encapsulation Coat

100 percent pure acrylic co-polymer, low viscosity, designed to saturate through and encapsulate the Reinforcement Fabric on detail areas as well as the body of the roof. It also penetrates into and seals the existing substrate, while blocking asphaltic bleed-through.

2.1.5 Reinforcement Tape for Metal Roof Surface

Self-adhesive, butyl-backed fabric for use as an alternative to reinforcement fabric in reinforcing joints, horizontal seams, non-crimped vertical seams, damaged areas, roof terminations and flashings, skylights and other openings, vents, conduits, HVAC equipment and other protrusions.

2.1.6 Acrylic Mastic

Single package, high tensile acrylic mastic for use in reinforcing crimped vertical seams, and as an alternative to reinforcement fabric or reinforcement tape on other seams and detail areas. Also used for encapsulating and sealing fastener screws of metal roof.

2.1.7 Concrete Repair Material

High strength acrylic polymer concrete renovation and repair material shall be applied, blended with portland cement at the jobsite. It is for use in repairing damaged mortar, filling voids and resurfacing spalled concrete surfaces.

2.1.8 Fluid-Applied Metal Primer

Single package, acrylic metal primer shall be applied to provide corrosion protection, flash rust resistance and enhanced adhesion over steel, aluminum and galvanized metal roof surfaces.

2.2 ROOFING SYSTEM

The roofing system shall have a Class A fire rating on a noncombustible deck when tested according to the procedures outlined in ASTM E 108.

2.3 WATER REPELLENT COATING MATERIALS

2.3.1 Clear Water repellent sealer

Water repellent sealer shall be a water-based, clear blend of reactive silane with a silicone emulsion designed to provide invisible water-repellency and protection from the intrusion of chloride salts, airborne pollution and de- icing chemicals over vertical and horizontal concrete, masonry and brick surfaces. Product is supplied in either a pre-diluted 5 percent solids by volume concentration, or in concentrate form that is diluted at the jobsite to achieve the specified solids, and shall meet the following minimum requirements:

A. Solids by volume: 5 to 10 percent (+/-2) [ASTM D 5201]

B. Viscosity: 1,000 to 1,500 cps at 24 degree C (75 degree F) [ASTM D 2196]

C. Dry time: 15 to 20 minutes at 24 degree C (75 degree F), 50 percent R.H. [ASTM D 1640]

D. Cure time: 1 to 2 hours at 24 degree C (75 degree F), 50 percent R.H. [ASTM D 1640]

E. Temperature Limits for Service Conditions: -56 degree C to 93 degree C (-70 degree F to 200 degree F)

F. Resistance to Accelerated Weathering: Treated specimen shall show no deleterious effects, no surface checking, cracking or delamination after 3,000 hours of testing in accordance with ASTM G 154 in a QUV cabinet.

G. Resistance to Wind Driven Rain: After 40 hours of continuous testing, treated precast concrete panel shall show no apparent moisture penetration into the substrate. Test conducted in a pressurized test chamber producing 12.7 cm (5 inch) of water pressure, equivalent to 100 mph wind pressure (161 km/hr) as per ASTM E 154.

H. Resistance to Salt Spray: Treated sample shall show no deleterious effects, no surface checking, cracking or delamination following 500 hours of continuous exposure.

Testing shall be in accordance with ASTM B 117 in a Harshaw Salt Spray Cabinet. Test specimens shall be treated cement asbestos board or equal.

I. Resistance to Sulfide Staining: No discoloration after 15 minutes immersion in saturated hydrogen sulfide gas solution when tested in accordance with ASTM D 1712. Compare with control specimen not exposed to hydrogen sulfide gas solution.

J. Resistance to Chemical Reagents: Specimen shall exhibit none or slight color change and no softening or deterioration after 7 days immersion in the following chemicals:

ammonium hydroxide - 10 percent; sodium hydroxide - 10 percent; mineral spirits, KB value 38. Inspection is compared to specimen not exposed to chemical reagents.

K. Verification of Minimum 5-Year Exposure to Appropriate Climate: Sealer shall have been in use in a similar climatic region 5 years or more and show no sign of fading, peeling or flaking. Supply project locations exceeding 5 years of service.

L. Moisture Vapor Transmission: Must allow moisture from building interior to pass through the substrate and stain with a perm rating of greater than 5.00 when tested in accordance with ASTM E 96.

2.3.2 Water repellent stain

Water repellent stain shall be a water-based, modified acrylic, penetrating stain designed to provide long term color uniformity, ultraviolet resistance, alkali and pollution resistance, plus water repellency without disturbing the natural texture of the substrate. It shall be for use over vertical, above- grade, smooth or textured concrete, exposed aggregate concrete, glass reinforced concrete, brick, stone, stucco and other masonry surfaces. Water repellent stain shall meet the following minimum requirements:

A. Solids by volume shall be a maximum of 30 percent (+/-2) [ASTM D 2697]

B. Weight per gallon shall be a minimum of 9.2 (+/-.2) lbs. [ASTM D 1475]

C. Dry time shall be 15 minutes at 24 degree C (75 degree F), 50 percent R.H. [ASTM D 1640]

D. Cure time shall be 1 hour at 24 degree C (75 degree F), 50 percent R.H. [ASTM D 1640]

E. Gloss (Angular Reflectance) shall be 4 at 60 degree Gardner [ASTM D 523]

F. Adhesion to Concrete shall be a minimum of 700 lbs./sq. in. [ASTM D 3359]

G. Temperature Limits for Service Conditions shall range from -56 degree C to 93 degree C (-70 degree F to 200 degree F).

H. Toning pigments shall be inorganic oxides.

I. Resistance to Accelerated Weathering: Color retention and ultraviolet resistance of the treated specimen shall meet the following requirements after 3,000 hours of testing in accordance with ASTM G 154 in a QUV cabinet.

1. Color Retention: Within five (5) N.B.S. (National Bureau of Standards) units when tested in accordance with ASTM D 2244; or shall show no appreciable change when tested in accordance with ASTM D 1729. Inspection is compared to unweathered specimen.

2. Ultraviolet Resistance: No chalking or flaking when tested in accordance with ASTM D 4214 and D 722.

J. Resistance to Accelerated Atmospheric Exposure: Specimen shall exhibit no visible change after 12-month exposure in accordance with ASTM G 7.

K. Resistance to Salt Spray: Color retention and degree of efflorescence of the treated specimen shall meet the following requirements after 500 hours of testing in accordance with ASTM B 117 in a Harshaw Salt Spray Cabinet.

1. Color Retention: Within five (5) N.B.S. (National Bureau of Standards) units when tested in accordance with ASTM D 2244; or shall show no appreciable change when tested in accordance with ASTM D 1729. Inspection is compared to unweathered specimen.

2. Degree of Efflorescence: Specimen shall exhibit no efflorescence.

L. Resistance to Sulfide Staining: No discoloration after 15 minutes immersion in saturated hydrogen sulfide gas solution when tested in accordance with ASTM D 1712.

Compare with control specimen not exposed to hydrogen sulfide gas solution.

M. Resistance to Chemical Reagents: Specimen shall exhibit none or slight color change and no softening or deterioration after 7 days immersion in the following chemicals:

ammonium hydroxide - 10 percent; sodium hydroxide - 10 percent; mineral spirits, KB value 38. Inspection is compared to specimen not exposed to chemical reagents.

N. Verification of Minimum 10 Year Exposure to Appropriate Climate: Stain shall have been in use in a similar climatic region 10 years or more and show no sign of fading, peeling or flaking. Supply project locations exceeding 10 years of service.

O. Moisture Vapor Transmission: Must allow moisture from building interior to pass through the substrate and stain with a perm rating of greater than 5.00 when tested in accordance with ASTM E 96.

PART 3 EXECUTION

3.1 PRE-ROOFING MEETING

Not less than 3 days prior to the start of the roofing work, contractor shall schedule a pre-roofing meeting. This meeting shall include the Contracting Officer's Representative, government inspector, designer, and coating manufacturer's representative. Items that shall be prepared to discuss are schedule of the work, material storage areas, safety measures, protection of building components not to receive roofing materials, inspection methods, method of installation and points of contact in emergencies.

3.2 SURFACE EXAMINATION

Verify that all surfaces are ready to receive work. Roof surfaces shall be clean, dry, structurally sound, stable and well secured. The roof surface shall be free of excessive ponding water. A roof surface that allows standing water 48 hours after a rain shall be considered unacceptable. All water shall be allowed positive drainage from the roof.

Inspect condition of flashing details adjacent to protrusions, penetrations, roof mounted equipment, curbs, walls, parapets, drains and roof edge to ensure that details are acceptable and will maintain a weather-tight installation after being properly detailed and coated. Inspect parapets to ensure that concrete, masonry or metal caps are sound. Caulk, reinforce or replace as necessary in order to bring parapet and parapet cap into a weathertight condition. Determine moisture content of existing substrate, insulation and deck. A moisture content of 15 percent or greater indicates a potential problem. Work shall not proceed until the cause of high moisture content is verified and condition is corrected.

3.3 SURFACE PREPARATION

3.3.1 BUILT-UP ROOFING SUBSTRATE

3.3.1.1 All loose gravel, dirt and debris shall be removed by vacuuming and/or power sweeping. Roofs exhibiting heavily embedded gravel must be made smooth for acceptance of the fluid-applied roof coating system using one of the following methods:

A. Removal of the protruding gravel by spudding, scraping or scarifying the surface as necessary to create a smooth, acceptable surface. Take care to preserve the integrity of the existing asphalt membrane whenever possible.

B. Application of a flood-coat of asphaltic emulsion in sufficient quantity so as to encapsulate and bury the protruding gravel, creating a smooth, acceptable surface.

C. Application of an approved roof recovery board, as per manufacturer's instruction, so as to create a smooth, acceptable surface.

3.3.1.2 Roof deck areas shall have positive slope-to-drain. Tapered insulation, cant strips, spray-applied polyurethane foam or other similar materials shall be used to build up affected roof surfaces as necessary to provide adequate slope-to-drain.

3.3.1.3 Inspect parapets to ensure that concrete, masonry, wood or metal caps are sound.

Caulk, reinforce or replace as necessary in order to bring parapet and parapet cap into a weathertight condition using an approved single- component urethane sealant.

3.3.1.4 Severely deteriorated flashings shall be removed and either replaced, or repaired utilizing spray-applied polyurethane foam. Seal reglet conterflashings with single-component urethane sealant.

3.3.1.5 Any unsound areas in the roof deck or insulation, including blisters, delamination, deterioration, excessive moisture content, etc. shall be repaired or replaced.

All blisters, delaminations, wrinkles and loose areas shall both be cut away and removed, or cut open and nailed flat to the deck.

3.3.1.6 All built-up roofing surfaces shall be cleaned using an approved, biodegradable cleaner, following manufacturer's instructions. Rinse thoroughly with fresh water under high pressure to remove the solution from the roof and achieve a "jet black" clean surface. Heavy deposits of dirt or contamination may require agitation with a stiff-bristle broom or similar mechanical scrubber. Allow the roof to dry thoroughly.

3.3.1.7 If the roof has been previously coated with aluminized asphalt of any kind, a penetrating primer must be applied to prevent potential "leafing" of the surface. Consult coatings manufacturer prior to application of the acrylic coating system over aluminized asphalt surfaces.

3.3.1.8 Reinforce repaired areas by encapsulating reinforcement fabric into the encapsulation coat over the repair. Cut a strip of reinforcement fabric (width depending on the size of the detail) to the desired length, and center it over the detail area. Apply encapsulation coat liberally from the top side using a brush or roller, working the encapsulation coat into the fabric so as to eliminate air pockets, wrinkles and gaps.

Ensure that the reinforcement fabric is thoroughly saturated, encapsulated and fully adhered to the substrate.

3.3.1.9 All cracks, splits, voids or holes larger than 3 mm (1/8 inch) in width shall be filled and leveled using an approved single-component urethane caulk or acrylic mastic.

Heavy alligatoring or rough texture in the existing built-up roofing shall be leveled by applying a flood-coat of approved asphalt emulsion, in sufficient quantity so as to achieve a smooth surface.

3.3.1.10 Reinforce all split seams, roof termination points, openings, around the base of all vents, pipes and other protrusions, as well as HVAC units and other roof mounted equipment with reinforcement fabric and encapsulation coat as described in 3.3.8 above.

3.3.2 CONCRETE ROOFING SUBSTRATE

3.3.2.1 All surfaces shall be clean and dry, and free of any dirt, dust, gravel, oil, surface chemicals or other contaminants that may interfere with optimum adhesion.

3.3.2.2 Any unsound areas in the roof deck, including deterioration, pitted or spalled concrete, excessive moisture content, etc. shall be repaired or replaced.

3.3.2.3 Roof deck areas shall have positive slope-to-drain. Tapered insulation, cant strips, spray-applied polyurethane foam or other similar materials shall be used to build up affected roof surfaces as necessary.

3.3.2.4 Fill any pits or holes in the concrete with concrete repair material so they are flush with the surrounding substrate. Spalled sections of the concrete should be resurfaced using a slurry-coat of concrete repair material, trowelled smooth over the affected area.

3.3.2.5 "Moving cracks" larger than 3 mm (1/8 inch) in diameter shall be routed out and filled using an approved urethane caulk. Cracks larger than 6 mm (1/4 inch) in diameter shall be routed out and fitted with polyethylene backer rod prior to caulking.

3.3.2.6 Inspect parapets to ensure that concrete, masonry, wood or metal caps are sound.

Caulk, reinforce or replace as necessary in order to bring parapet and parapet cap into a weathertight condition.

3.3.2.7 All concrete surfaces, whether new or existing, shall be cleaned using an approved biodegradable cleaner, following manufacturer's instructions. Rinse thoroughly with fresh water under high pressure (minimum 2,000 psi - 13,790 Kpa) to remove the solution from the roof. Heavy deposits of dirt or contamination may require agitation with a stiff-bristle broom or similar mechanical scrubber. Allow the roof to dry thoroughly.

3.3.2.8 Prime all concrete surfaces with one coat of concrete prime material at a rate according to manufacturer's instruction to seal and solidify the surface.

3.3.2.9 Reinforce all "moving" cracks and/or seams, control joints, vertical/horizontal interfaces, roof termination points, openings, around the base of all vents pipes and other protrusions, as well as HVAC units and other roof mounted equipment with reinforcement fabric embedded into encapsulation coat. Cut a strip of reinforcement fabric (width depending upon the detail) to the desired length, and center it over the detail area. Apply encapsulation coat liberally from the top side using a brush or roller, working the encapsulation coat into the fabric so as to eliminate air pockets, wrinkles and gaps.

Ensure that the reinforcement fabric is thoroughly saturated, encapsulated and fully adhered to the substrate.

3.3.3 METAL ROOFING SUBSTRATE

3.3.3.1 Metal surfaces to be coated shall be clean, dry, sound, and free of dirt, grease, oil, and any other contaminants that might interfere with the adhesion of the elastomeric acrylic coating.

3.3.3.2 All mechanical fasteners shall be checked for integrity. Retighten or replace as necessary. "Stripped out" fasteners shall be replaced using a larger diameter fastener.

3.3.3.3 Unsound rust shall be wire brushed, sandblasted or mechanically abraded to remove all loose rust. Metal panels deteriorated to the point that their structural integrity is compromised shall be replaced.

3.3.3.4 Remove excessive amounts of asphaltic-based or other deteriorated patching/flashing materials if present.

3.3.3.5 Check all seams to ensure that they are tight and flush. Excessive gaps or deflection between panels shall be eliminated by installing additional screws or rivets as necessary to restrict deflection to 6 mm (1/4 inch) or less.

3.3.3.6 All metal surfaces, whether new or existing, shall be cleaned using an approved biodegradable cleaner, following manufacturer's instructions. Rinse thoroughly with fresh water under high pressure (minimum 2,000 psi - 13,790 Kpa) to remove the solution from the roof. Heavy deposits of dirt or contamination may require agitation with a stiff-bristle broom or similar mechanical scrubber. Allow the roof to dry thoroughly.

3.3.3.7 All existing "sound" rusted areas shall be primed with metal primer according to the manufacturer's instructions.

3.3.3.8 If the roof has been previously coated with aluminized asphalt of any kind, a penetrating primer must applied to prevent potential "leafing" of the surface. Consult coatings manufacturer prior to application of the acrylic coating system over aluminized asphalt surfaces.

3.3.3.9 Fill gaps between 6 and 13 mm (1/4 and 1/2 inch) at panel seams, joints and protrusions with an approved single-component urethane caulk. Fill gaps larger than 13 mm (1/2 inch) such as at the ridge cap, roof edge and/or interface of dissimilar materials, using polyethylene backer rod or spray- applied polyurethane foam.

3.3.3.10 All horizontal (end-lap) seams and vertical (side-lap) seams which have not been factory crimped or presealed, roof terminations and flashings, around drains, scuppers and skylights, and the base of all vents, conduits, HVAC equipment and other protrusions shall be reinforced using one or more of the following methods:

A. Apply base coat acrylic elastomer liberally, using a brush or roller, along the area to be detailed. While the base coat is still wet, embed a strip of 15 to 30 cm (6 to 12 inch) reinforcement mesh for end-lap seams. For side-lap seams, use 5 to 10 cm (2 to 4 inch) reinforcement mesh, as per detail requirements, centered over the seam, joint or interface. Work the reinforcement mesh into the base coat, applying additional material as necessary to totally encapsulate the reinforcement fabric.

B. Cut a length of 15 cm (6 inch) reinforcement tape to the desired length, peel off the release backing, center over the end-lap detail area and press firmly into place, removing all wrinkles and bubbles. For side lap seams 5 to 10 cm (2 to 3 inch) reinforcement tape may be used. A wallpaper seam roller is helpful in securing the reinforcement tape to the metal deck.

C. Apply a minimum of two (2) coats of acrylic mastic, using a brush, roller or airless spray, to a total thickness of 60 to 80 dry mils (1,524 to 2,032 microns) over the detail area. Extend the sealant a minimum of 8 cm (3 inch) on either side of seams, joints and interfaces.

3.3.3.11 At the interface of any metal with a dissimilar material, detail the joint using one of the following methods:

A. Apply 15 cm (6 inch) reinforcement mesh embedded into base coat as previously described in 3.3.3.10 a.

D. Apply a strip of 15 cm (6 inch) reinforcement tape as previously described in

3.3.3.10 b.

E. Apply two (2) coats of acrylic mastic to a total thickness of 60 to 80 mils (1,524 to 2,032 microns) as previously described in 3.3.3.10 c.

3.3.4 TILE ROOFING SUBSTRATE

3.3.4.1 All surfaces shall be clean and dry, and free of any dirt, dust, gravel, oil, surface chemicals or other contaminants that may interfere with optimum adhesion.

3.3.4.2 Any unsound areas in the roof deck, including deterioration, pitted or spalled concrete, excessive moisture content, etc. shall be repaired or replaced.

3.3.4.3 Roof deck areas shall have positive slope-to-drain. Tapered insulation, cant strips, spray-applied polyurethane foam or other similar materials shall be used to build up affected roof surfaces as necessary to allow positive drainage.

3.3.4.4 Fill any pits or holes with concrete repair material so they are flush with the surrounding substrate.

3.3.4.5 Inspect parapets to ensure that concrete, masonry, wood or metal caps are sound.

Caulk, reinforce or replace as necessary in order to bring parapet and parapet cap into a weathertight condition.

3.3.4.6 Remove excessive amounts of asphaltic-based or other deteriorated patching/flashing materials if present.

3.3.4.7 All concrete roof tile surfaces, whether new or existing, shall be cleaned using…