B08 Responses to Industry Questions_Amendment 0001_21 Mar 23.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- Project Manager Expeditionary Energy and Sustainment Systems (PM E2S2) PRIME POWER CONNECTION KIT (PPCK)
- Solicitation number
- W909MY-23-R-G002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08 Format_Questions and Answers.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions
| Item # | Section, Paragraph, Sentence | Description | Question /Recommendation | Government Response |
| 1 | General | Does the government anticipate requiring a new design or simply improving the existing design. | Please clairify if the government is requesting an entirely new design which meets the specificiations or if the current Prime Power Kit should be used as a baseline with specific gaps to be addressed? | It is the responsibility of the respondent to describe its approach to meet the requirements of the essential characteristics and the component-specific technical requirements. |
| 2 | General | Does the government own the TDP for the existing design and will they make it available to us for the RFI? | Please provide the current TDP for the Prime Power Kit. | The government will not provide Technical Data Packages (TDPs). |
| 3 | General | What is lacking in the existing design? | Please describe the shortfalls of the current design and what gaps have been identified. | The government is seeking information on the Prine Power Connection Kit (PPCK) components based on the essential characteristics and technical requirements presented in the Sources Sought Notice (SSN). |
| 4 | General | Is there an estimated procurement qty? | Please provide the qty of PPCKs estimated to be purchased. | For this development, the government requires research, design, manufacture, and delivery two (2) First Article Test (FAT) units of each PPCK component: improved Secondary Distribution Center (iSDC), improved Primary Switching Center (iPSC), and Tactical Prime Power Transformer (TPPT). The government may procure up to 400 iSDC, 100 iPSC, and 100 TPPT production units. These are estimates with no guarantee of production quantities. |
| 5 | B Question. #1 Existing Technology or Technoloy Concept. | What does the government expect from the question B – ‘Existing technology or technology concept'? This is not a question. | Please clarify what is being asked for in this section | The government seeks to understand whether these requirements could be satisfied by existing products, modified products, or new development . |
| 6 | C. Technical Narrative 3. Estimated Project Timeframe and Cost b. What is the estimated cost of this effort? | Does the government have a budget target range for development? | Please provide any existing budget information | The government will not provide a budget target for the development of the PPCK components presented in the SSN. The government's market research seeks to develop information that may be used in budget analysis. |
| 7 |