This amendment modifies a solicitation for electrical work. The amendment identifies that CLIN 0003 is an option for low bay buss duct work, including running conduit and installing bus duct from the switch gear down the north wall and in the center of the building between specified columns. The Department of the Army Materiel Command Contracting Command at Rock Island Arsenal seeks this electrical work on Building 299. The amendment provides additional details on the scope of work for the optional CLIN. All other terms and conditions of the solicitation remain unchanged.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCK ISLAND ARSENAL (ACC-RI)

HEATHER PETERSEN

309-782-2456

ROCK ISLAND IL 61299

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment 0002 is outlined in the Amendment 0002 Narrative.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 22-Jun-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9098S21R0014

X 9B. DATED (SEE ITEM 11)

26-May-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

22-Jun-2021

CODE

ROCK ISLAND ARSENAL (ACC-RI)

3055 RODMAN AVENUE

ROCK ISLAND IL 61299-8000

W9098S 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W9098S

FACILITY CODECODE

EMAIL:TEL:

W9098S21R0014

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SUPPLIES OR SERVICES AND PRICES

CLIN 0003

The CLIN extended description has changed from:

Option - Electrical Work on the NW End of Bldg 299.IN ACCORDANCE WITH Attachment 0002 - RIPD E4000- 18-03-02 - NW End 299 ElectricalA CONTRACTING OFFICER'S REPRESENTATIVE (COR) WILL

BEASSIGNED AT THE TIME OF CONTRACT AWARD. SEE DFARS 252.201-7000

To:

Option - Electrical Work on the NW End of Bldg 299.IN ACCORDANCE WITH Attachment 0002 - RIPD E4000- 18-03-02 - NW End 299 Electrical, SECTION 5A CONTRACTING OFFICER'S REPRESENTATIVE (COR)

WILL BEASSIGNED AT THE TIME OF CONTRACT AWARD. SEE DFARS 252.201-7000

The following have been added by full text:

AMENDMENT 0002 NARRATIVE

The purpose of this Amendment is to identify in the Attachment 0002 - RIPD E4000-18-03-02 - NW End 299 Electrical which part is the Option. CLIN 0003 Option is section 5:

5. LOW BAY BUSS DUCTS

5.1.1 Run off one of the 800-Amp switches that will feed an 800-amp, 480-volt, 3-phase buss duct. Run a conduit out of the switch gear down the North wall high enough to clear the overhead doors to column number 24. Then run the conduit down the low bay area and install 40 feet of bus duct is in the center of the building between columns G and K (see attached drawing).

5.1.2 Run off one of the 800-Amp switches that will feed an 800-amp, 480-volt, 3-phase buss duct. Run a conduit out of the switch gear down the North wall high enough to clear the overhead doors to column number 29. Then run the conduit down the low bay area and install 40-feet of buss duct is in the center of the building between columns G and K (see attached drawing).

5.1.3 Run off one of the 800-Amp switches that will feed an 800-amp, 480-volt, 3-phase buss duct. Run a conduit out of the switch gear down the North wall high enough to clear the overhead doors to column number 36. Then run the conduit down the low bay area and install 40 feet of buss duct is in the center of the building between columns G and K (see attached drawing).

5.1.4 The last switch in the switch gear is a 400-amp switch reserved for future requirements.

All other terms and conditions remain unchanged.

W9098S21R0014

(End of Summary of Changes)