This document is a Questions and Answers (Q&A) sheet for a wall locker procurement by the North Dakota Army National Guard (NDARNG). The solicitation (W901UZ25Q0724) seeks wall lockers to be delivered between October 1-10, 2025, during normal business hours. Key details from the Q&A include: lockers must be delivered fully assembled, NDARNG personnel will unload the lockers using a forklift, no installation is required, lockers should not include legs, and a dumpster will be available on-site. The solicitation is open to SAM-registered companies and requires quotes to include all freight and handling costs, with the opportunity focusing on supplying wall lockers as specified in the attached Product Description PDF.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 817 EN CO Wall Lockers (Revised 7.30).pdf | ||
| QA - 817 EN CO Wall Lockers.docx | DOCX document | |
| RFQ 817 EN CO Wall Lockers.pdf | ||
| Product Description.pdf | ||
| Combined Synopsis and Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
817 EN CO Wall Locker Q&A
Q: When should the lockers be delivered?
A: Lockers shall be delivered between 1 October 2025 and 10 October 2025 during normal business hours Monday-Friday 8 AM – 4 PM CST.
Q: Do the lockers need to be delivered assembled?
A: Yes.
Q: Is there a loading dock at destination?
A: No, there is no loading dock.
Q: Will contractor be responsible for unloading tools and labor?
A: NDARNG personnel will be on site (with a forklift if needed) to unload the lockers.
Q: Is installation required?
A: No, installation is not required.
Q: Should the lockers include legs?
A: No.
Q: Can a room layout be provided?
A: Installation will not be required so a room layout will not be provided.
Q: Is there a dumpster on site?
A: Yes.