RFQ_-_Modular_Vault_IDS_and_Installation.pdf

PDF 154 KB Posted

Attached to
Modular Vault w/ IDS System and Installation
Solicitation number
W901UZ0900305
Issued by

About this file

Solicitation for Modular Vault with IDS System and Installation

View the file

Other files

File Type Posted
252.209-7996_FY16.pdf PDF
252.209-7991FY16.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL GUARD BUREAU

OFFICE OF THE UNITED STATES PROPERTY AND FISCAL OFFICER, NORTH DAKOTA

PO BOX 5511, BISMARCK, NORTH DAKOTA 58506-5511

26 August 2016 To Whom It May Concern,

1. The North Dakota Army National Guard has a requirement for:

One (1) each Modular Vault

One (1) each Modular Vault Intrusion Detection System

One (1) each Installation of Modular Vault and IDS System

One (1) each Freight/Shipping Charge (if applicable)

2. Only new items are acceptable; no refurbished items will be considered. Award will be made to only one vendor. All offerors shall submit complete specifications of the items offered with their offer. The Government will award to the responsible offeror whose offer, conforming to the request for quote, will be most advantageous to the Government (price and other factors considered). This may result in award to other than the lowest priced offer. The following factors shall be used to evaluate offers: price, delivery time, and specifications. All evaluation factors other than cost or price, when combined, are approximately equal to cost or price. The Contracting Officer will evaluate products on the basis of information furnished by the quote or identified in the quote and reasonably available to the Contracting Officer. The Contracting Officer is not responsible for locating or obtaining any information not identified in the quote. FOB Destination: USPFO Warehouse, BLDG 6330, Camp Gilbert C. Grafton, 4417 HWY 20, Devils Lake ND 58301.

3. Complete the information below and return it with your quote. Quotes are due no later than 1:00 PM CDT on 7 September 2016. All late quotes will be rejected. Point of contact for this acquisition is:

SFC Cody Martin USPFO for North Dakota, P&C PO Box 5511 Bismarck, ND 58506-5511

Email: cody.t.martin.mil@mail.mil Fax: 701-333-2230

4. An extract from DFARS 252.209-7991 & 252.209-7996 are attached separately, and must be completed and returned with your offer.

5. All offerors must be registered in the System for Award Management (SAM) database. Lack of registration in SAM will make an offeror ineligible for award. Registration information can be found at http://www.sam.gov. The Department of Defense requires vendors to submit invoices in the Wide Area Workflow System (WAWF); please go to https://wawf.eb.mil/ for more information. Information concerning FAR clauses can be obtained at http://farsite.hill.af.mil or http://www.arnet.gov/far. Point of Contact for this combined synopsis/solicitation is SFC Cody Martin, 701-333-2295.

SFC CODY MARTIN

Contract Specialist

INCUDED: Vault Specifications, Statement of Work Vault, Specification and Statement of Work Intrusion Detection System

SEPARATE ATTACHMENTS: Extract DFARS 252.209-7991 & 252.209-7996

RE: ND National Guard Vault with IDS System

COMPANY NAME: ____________________________________________________________

DUNS NUMBER: ______________________ TAX ID: _______________________

CAGE CODE: _______________________ GSA Contract #: _________________

MODULAR VAULT PRICE: $_____________________________________

ELK IDS (#ELK-NGM1K1): $_____________________________________

INSTALLATION OF VAULT & IDS: $_____________________________________

FREIGHT: $_____________________________________

GRAND TOTAL: $______________________

DELIVERY (Days/Weeks after Receipt of Order): _________________________

(Signature) (Date)

Printed Name: ____________________________________________________________

Modular Vault Specifications:

Dimensions: 28L x 14W x 10H (interior ceiling height) Door opening: 7'W x 8'H In order to receive an NGB furnished IDS, vault must be applicable to AR 190-11, Appendix G standards.

Below is regulatory guidance that will need to be considered:

Walls: Walls will be of 8 inches of concrete reinforced with No. 4 reinforcing bars at 9 inches on center in each direction in each face of the wall. Reinforcement in the two faces of the wall will be staggered on each face to form a projected grid approximately 4-1/2 inches square. Reinforcement in the walls will be tied into floors and ceilings per American Concrete Institute standards.

Ceilings & Roofs: Ceilings and roofs will be of reinforced concrete construction. The thinnest portion may not be less than 6 inches. Reinforcing bar spacing will form a grid so that the area of any opening does not exceed 96 square inches using No. 4 bars or larger.

Floors: Floors, if on grade, will be a minimum of 6-inch thick reinforced concrete construction reinforced with 6 inches by 6 inches, W4 by W4 welded wire fabric or equivalent steel reinforcing bars (based on area of steel per square foot). Where the floor slab acts as the ceiling of an underlying room or area, the ceiling standards will apply. Where equivalent steel reinforcing bars are used, bar spacing will form a grid so that the area of any opening does not exceed 96 square inches.

Doors and door frames: The door will be GSA-approved Class 5 armory door per GSA Federal Specification AA-D-600D(4). A GSA-approved Class 5 vault door is not encouraged, due to its electromechanical lock. Double door protection for arms storage facilities is not required. Door frames will be per Federal Specification AA-D-600(4).

Windows and other openings: Windows are not authorized. Ducts, vents, and other openings of 96 square inches or more with the least dimension greater than 6 inches will be secured per one of the following methods and otherwise limited to the minimum number and size that are essential:

(1) Sealed with material comparable to that forming the adjacent walls.

(2) Fitted with any of the barriers below with bars or steel mesh securely embedded in the structure of the building or welded to a steel frame that will be securely attached to the wall with fastenings inaccessible from the exterior of arms storage facility.

(a) Three-eighth inch or larger hardened steel bars with vertical bars not more than 4 inches apart and with horizontal bars welded to the vertical bars so that the openings do not exceed 32 square inches.

(b) A minimum of 8-gauge high carbon manganese steel mesh with 2-inch diamond grid.

(c) A 6-gauge cold drawn steel wire mesh with 2-inch diamond grid when 8-gauge mesh above is not available.

MODULAR VAULT AND IDS INSTALLATION STATEMENT OF WORK (SOW)

1. LOCATION: North Dakota Army National Guard, Camp Grafton Training Center (CGTC), Devils

Lake, ND (Attachment #1).

2. STATEMENT OF WORK: This statement of work will identify the specifications and criteria for the purchase and delivery of one modular vault (MV) with a standardized ELK Intrusion Detection System (IDS) installed as a turnkey solution. The vault will be used as an Arms, Ammunition & Explosives CAT II – IV storage area therefore all requirements must be in compliance with DoD rules, AR 190-11, DD4604 certified. Structure must adhere to NSWC-Point Hueneme testing for 15-minute forced entry.

NSWC-Point Hueneme certificate of compliance must be provided as evidence of the structure passing required testing. No vendor documentation or other third party documentation is acceptable as evidence of compliance and satisfaction of the forced entry test certification. Doors and door frames will be GSA approved Class 5 armory door per GSA Fed Spec AA-D-600D-10 (26FEB13). The work covered in this contract consists of furnishing all plant, labor, expertise, equipment, materials, facilities, transportation, and appliances necessary to deliver a fully operational and functional modular vault with a standardized IDS installed. Any relevant details required for completion that may have been inadvertently omitted in the contract plans and specifications will be provided by the Contractor at no cost to the government.

The modular Military Weapons Storage Vault is to be installed at the USPFO Warehouse, BLDG 6330 located at CGTC. This is a state-government owned facility. The requirements for the custom vault are as follows: 28’ long x 14’ wide x 10’ high (outside dimensions). Interior vault walls and ceiling will be the standard unfinished but primed with a white enamel paint. The six sided vault consists of a ceiling and floor section with four walls. The wall panels will be anchored to existing concrete slab. The system must incorporate access for phone, electric, alarm, HVAC and possibly sprinkler systems. In addition, the interior vault ceiling support system is designed to incorporate the existing building columns, structural steel and its own structural support system, while not encroaching on the anticipated internal rack/storage system. This purchase will include all CV engineered vault shop drawings, fabrication, freight, delivery and installation of modular vault systems, internal vault structural steel, and GSA vault door.

There may be issues regarding the installation requirements. Offloading the freight truck with the use of a forklift and then deliver the vault into the space through openings large enough to fit the lift. The opening to the area of consideration is 12’ high x 17’ wide. Vendor is responsible for cost of their site survey that may be required to detail the installation access.

3. SUMMARY OF WORK: The work shall consist of but is not limited to the following:

(1) Installation of Modular Vault:

The modular vault will be 14’W x 28’L x 10’H (outside dimensions) with a GSA approved

Class 5 armory door opening of 7’W x 8’H.

The vault components must be applicable to the standards within AR 190-11, Appendix G.

One combination lock (FF-L-2937) with an emergency escape mechanism.

2 – 20 amp circuits will be installed. One dedicated to the Intrusion Detection System (IDS) and the other to the lights, outlets, and switches.

6 fluorescent light fixtures will be installed.

One outlet per 6 feet will be installed.

4. REFERENCES: All work performed under this contract shall be in accordance with Federal Specification Modular Vault Systems AA-V-2737, Physical Security of AA&E: AR 190-11 Appendix G, ARNG-ILI-IDS certification course 964-CFMO-110, Unified Facilities Guide Specifications (UFGS) 28 20 01.00 10, federal, state and local codes & standards, as well as widely accepted industry standards, including but not limited to: American Institute of Architects, American Concrete Institute, American Institute of Electrical Engineers, American Institute of Steel Construction, American National Standards Institute, American Society of Heating, Refrigerating and Air Conditioning Engineers, American Society of Mechanical Engineers, American Society of Testing Materials, National Bureau of Standards, National Electric Code, American Welding Society, Brick Institute of America, Building Officials and Code Administrators, Federal Aviation Administration, National Fire Protection Association, National Electric Code, Occupational Safety & Health Administration, Rubber Manufacturers Association, Underwriters Laboratories, and the North Dakota DOT standard specification. Additionally, all requirements of the North Dakota Department of Health must be satisfied in their entirety for any work performed or materials bought under this contract. Failure to comply with any of the afore mentioned codes and standards shall be considered as a failure to comply to contract specifications

5. UTILITIES: The contractor shall coordinate with all utilities with Mr. Tom Bertsch, CGTC Physical Plant Director (701) 665-7661.

6. MATERIALS: The materials shall conform to specifications, applicable industry codes and standards and the manufacturer's recommendations, whichever is more stringent. Certificates of compliance and Technical Data Sheets are required for all materials supplied.

7. SITE INSPECTION: The Contractor is required to acknowledge, at time of Bid Opening that said contractor has inspected, and is fully cognizant of conditions at the site. No allowance or consideration will be given after award for any condition(s) which was(were) existing at the time of the site visit.

8. SAFETY: Compliance with OSHA and other applicable laws and regulations for the protection of employees is exclusively the obligation of the commercial contractor. Government employees must comply with AFOSH.

9. CLEAN-UP: Clean-up and remove debris generated by this contract to an approved off-base location.

Two (2) copies of the receiving (tipping or dumping) tickets, with a cover letter from the Prime Contractor stating the full name and address of the approved location to which debris was taken. Provide tonnage.

10. GOVERNMENT RESOURCES: No Government resources shall be made available to the contractor, unless otherwise stated in this Statement of Work. The contractor shall provide for all necessary resources to provide a complete and usable facility or systems as described in the contract documents. The contractor shall not obligate Government resources in any manner. The Government shall seek remedy for any obligation or encumbrance imposed by the Contractors actions. Government resources include, but are not limited to, government owned materials, equipment, tools, vehicles, personnel and facilities.

INSTALLATION AND INTRUSION DETECTION SYSTEM STATEMENT OF WORK

(SOW) & SPECIFICATIONS

1. Location: North Dakota Army National Guard - Camp Grafton Training Center - 4417 Hwy 20 -

Devils Lake, ND 58301

2. Scope of work: This Request for Quote statement of work is specific to the existing USPFO warehouse facility, building 6330 at Camp Grafton to obtain an approved AA&E storage area modular vault with a standardized Intrusion Detection System installed as a turnkey solution.

3. Summary of work: The work shall consist of but is not limited to the following:

(1) Purchase of modular vault for highest category of Arms, Ammunition and Explosives to be stored therein.

(2) Installation of modular vault:

The modular vault is to be shipped fully assembled and upon delivery to building 6330 the owner will coordinate placement of vault within building 6330.

Utilities: Owner will facilitate the connection of electrical and telephone service to modular vault.

(3) Installation of IDS:

The modular vault will be shipped with a standardized Intrusion Detection System installed. Therefore once electrical and telephone service are connected to the modular vault on site the IDS will be programmed then placed in service by NGND-DFE-ESS Electronic Security Systems program office certified personnel on site.

(4) Reference: All work performed under this contract shall be in accordance with federal, state and local codes & standards, as well as widely accepted industry standards, including but not limited to: Federal Specification Modular Vault Systems AA-V-2737, Physical Security of AA&E: AR 190-11 Appendix G2, ARNG-ILI IDS certification course 964-ARNG-CFMO- 110, Unified Facilities Guide Specifications (UFGS) 28 20 01.00 10, Failure to comply with any of the afore mentioned codes, standards and certification requirements shall be considered a failure to comply with contract specifications.

(5) Utilities: Due to the age of building 6330 and electrical service capacity limitations the available electrical service for the standardized Intrusion Detection System is 120 VAC, 20 amp. Two 120 VAC, 20 amp dedicated circuits will be will be provided at the final installation site by owner.

(6) Attachments:

Section 1: Intrusion Detection System (IDS) specifications & criteria

Section 2: Electronic Security System Standards & Criteria Compliance letter, 10 Aug

Section 1: Intrusion Detection System (IDS) specifications & criteria

The following Intrusion Detection System information is specific to the Camp Grafton USPFO warehouse modular vault RFQ.

1. Prerequisite for Intrusion Detection System installation in an modular vault used for storage of

AA&E

The modular vault must meet the physical security construction standards for the highest category of AA&E to be stored therein prior to installation of the Intrusion Detection System.

2. Intrusion Detection System equipment installation requirements

The NDARNG state specific standardized Intrusion Detection System solution is the ELK PRODUCTS Elk-M1 alarm panel part number ELK-NGM1K1, National Guard-MILCON, single vault kit w/28” encl. box available from Elk direct only.

All Intrusion Detection Systems for ARNG vaults storing AA&E must be DIACAP (Defense Information Assurance Certification & Accreditation Process) certified and use ARNG-ILI ESS standardized program equipment with DIACAP ESS v2.0.

Installers of ARNG Intrusion Detection Systems must have completed the appropriate NGB-ARI ESS certification course 964-ARNG-CFMO-110, possess a program certificate and identification card issued by the Professional Education Center at Camp Robinson - Little Rock, AR.

Proof of NGB-ARI ESS certification course 964-ARNG-CFMO-110 attendance within the past three years must accompany the modular vault RFQ.

Modular vault must have the Intrusion Detection System for a single vault installed by certified personnel using the Installation Design Package for Arms, Ammunition and Explosives Storage Areas ELK-M1 with typical installation drawings & specifications obtained during the NGB-ARI ESS certification course 964-ARNG-CFMO-110.

Reference: Electronic Security System Standards & Criteria Compliance letter, 10 Aug 2005 (Attachment #2)

3. Intrusion Detection System electrical service requirements

Due to the age of building 6330 the available electrical service for the standardized Intrusion Detection System is 120 VAC, 20 amp. Two 120 VAC, 20 amp circuits will be will be provided at the final installation site by owner.

A single 120 VAC, 20 amp dedicated circuit must be provided inside of the modular vault at the circuit breaker panel solely for the purpose of operating the Elk-M1 alarm panel and accessories.

Another 120 VAC, 20 amp dedicated circuit must be provided inside of the modular vault at the circuit breaker panel solely for the purpose of lighting and wall outlets.

4. Intrusion Detection System electrical conduit, coupling and connector requirements

AC power and Data transmission lines located inside of the modular vault must each have dedicated electric metallic tubing (EMT) conduits that complies with UFGS 26 20 00. Electric metallic tubing couplings and connectors must be compression type.

All power and data transmission lines exiting the modular vault interior but still located interior to the building, may be enclosed in intermediate tubing that complies with UFGS 26 20 00.

Therefore the modular vault must have two separate access points of entry into the modular vault.

One for the AC power and another for the data transmission line to enter/exit the modular vault structure.

Section 2: Electronic Security System Standards & Criteria Compliance letter, 10 Aug 2005

-----Original Message----- From: Walker, Glenn W COL NGB-ARNG <glenn.w.walker@us.army.mil> To: NGJP USPFOs-All States Private DL <USPFOs.AllStates@ngb.ang.af.mil>;

'DOLs' [EX:/O=ORGANIZATION/OU=NGB-ARNG/CN=ORGANIZATIONAL

RECIPIENTS/CN=DOLS];

Sent: Wed Aug 10 10:12:17 2005 Subject: FW: Authorization and Approval of Electronic Security Systems

All: We are experiencing some activity in the security installation area that does not conform to Corps of Engineers/NGB standards. Please review the following and assure that we are on track to install correct equipment for the safety of our soldiers and civilians at your sites. We stand ready to assist at any time if there are questions or issues with determining availability and accreditation of contractors to provide you the appropriate services.

Thanks, Glenn

Glenn W. Walker

COL, GS

G4 ARNG

(703) 607-9746 cell (571) 243-5635 Electronic Security Systems Standards and Criteria Compliance

NGB-ARI has developed standards and criteria for all Electronic Security Systems (ESS) used to provide security and protection for all ARNG facilities. These standards and criteria were developed jointly with NGB-ARO-I and include:

* Types and quantities of ESS equipment to be approved by NGB-ARI-FM and used for each ARNG facility

* Standardized equipment solutions selected and approved by NGB-ARI-FM

* Standard installation methods and drawings for the installation and interconnection of all NGB-ARI approved ESS equipment

* Integration standards for ESS equipment with other facility infrastructure and monitoring equipment

* Qualification and Certification requirements for all personnel designing, engineering, installing, operating, or maintaining ESS equipment

* Maintenance standards and procedures

* Training requirements

All States will ensure that all NGB criteria and standards are met at all locations. This includes ensuring that NGB-ARI reviews and approves all ESS projects that are federally funded. All equipment used shall meet NGB criteria and standards. All personnel including contractor personnel must be currently certified through the NGB-ARI ESS Certification Course at the Professional Education Center at Camp Robinson.

USPFOs will ensure that all funding received for ESS projects or services conform to the NGB ESS standards and criteria.

2016-08-26T07:25:35-0500
MARTIN.CODY.THOMAS.1146168465

File details come from the government source that posted it. Updated .