W81XWH21R0078 Follow Up Questions and Answers 12 Jan 2021.xlsx
XLSX spreadsheet 11 KB Posted
- Solicitation number
- W81XWH21R0078
- Issued by
-
Department of the Army Medical Command
About this file
This document contains questions and answers related to solicitation number W81XWH21R0078 from the Department of the Army Medical Command seeking Regulated Activities Support Services. The solicitation is for an Indefinite Delivery Indefinite Quantity contract to provide support services to the U.S. Army Medical Research and Development Command Office of Regulated Activities. Questions addressed include clarification that all ceiling rates in Attachment 05 of the solicitation should be hourly rates, confirmation that proposed ceiling rates in Attachment 05 may be discounted for initial or future task orders and will be evaluated for fairness and reasonableness, and whether a letter of commitment from all subcontractors can be submitted in lieu of subcontract agreements. An extension request to the response date was denied.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| W81XWH21R0078 Questions #2 (Follow up to Amendment 0001) | 1/12/21 | |||
| Number | Reference | Question | Answer | Resulting Amendment |
| 1 | Amendment 0001 Question 41 | In Question 41's response, the Government indicates it is seeking "FFP Completion" pricing regarding the FFP ceiling rates on Attachment 05. Please clarify whether the FFP ceiling rates requested on Attachment 05 should be "annual" or "hourly" ceiling rates? RFP Attachment 05 also requests T&M ceiling rates which are normally hourly rates, so we are seeking clarification as to whether the Government also intends the FFP ceiling rates to be "hourly", rather than an "annual" rate per labor category? | All ceiling rates in Attachment 05 should be hourly rates. | N/A |
| 2 | Amendment 0001 Question 17 | Can a letter of commitment from all subcontractors, including non-major subcontractors, be submitted in lieu of providing a subcontract agreement and teaming arrangement? | Yes. | N/A |
| 3 | Amendment 0001 Question 22 | Since this is an IDIQ contract, will the Government confirm that the rates provided in Attch05BasePrice Template are ceiling rates that then can be discounted for the Initial Task Order and future Task Orders based on the work requirements and level of personnel required? | Yes, the ceiling rates may be discounted for the initial task order or future task orders. The proposed ceiling rates will be evaluated for fairness and reasonableness. | N/A |
| 4 | N/A | Will the Government please provide a 4-day extension to January 25 at 10:00 a.m.? | The Government is unable to accommodate this request. | N/A |