There has been a conflict with the project duration. As it states 456 calendar days in Standard Form 1442 (see attachment no.1) but, In the submission requirement for Factor 3: Schedule its states that the proposed duration of the project is 931 days (see attachment no.2). We are at the very last stages of the schedule preparation, please confirm the exact duration for the subject project before sequencing the project activities.
Please ensure you review all requirement documents and attachments. The 456 calendar days on the SF 1442 is the Period of Performance (POP) for the Base Items reference your Price Schedule. The 931 days is the POP for the entire project, base and optional Items; if the Government was to exercise options 1 or 2 or both. Factor 3 is a schedule for the entire project, 931 days.