Note proposals are due 12:00 am local Afghanistan time; which is approximately 03:30 am eastern The U.S. Army Corps of Engineers (USACE), Afghanistan District intends to solicit a requirement for the Afghanistan Air Force (AAF) Aviation Enhancement at Mazar-e-Sharif. The project consists of the design and construction (Design Build) of a new Life Support Area (LSA) Expansion, a new mixed rotary and fixed wing rigid paved Airfield, and airfield Operations facilities for support and maintenance of aircraft
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0002_W5J9JE-18-R-0014_block_13.pdf | ||
| Amendment_0001_W5J9JE-18-R-0014_Proposal_extension.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation W5J9JE18R0014
US Army Corps of Engineers Transatlantic Afghanistan District
AFGHANISTAN NATIONAL ARMY
(ANA)
AFGHANISTAN AIR FORCE (AAF)
AVIATION ENHANCEMENT MAZAR-E-
SHARIF (MeS), AFGHANISTAN (PLANNING, DESIGN, AND CONSTRUCTION)
Mazar-e-Sharif, Afghanistan
Project Number: ANA 18-072
Phase One Proposal Requirements, Solicitation, Conditions of the Contract, and Basis of Award
August 2018
[This page was intentionally left blank for duplex printing.]
Afghan National Army (ANA) 18-072
AAF Aviation Enhancement MeS
The offerors shall have an active and valid Afghan Investment Support Agency (AISA) License or new ly acquired Ministry of Commerce and Industries (MoCI) Entrepreneurial License. In addition, the Offeror shall have an active and completed registration in the System f or Aw ards Management (SAM) and the Joint Contingency Contracting System (JCCS) at time of proposal submission to be considered. The Offeror shall maintain their registrations throughout the solicitation phases and if aw arded a contract, throughout the contract’s duration.
In accordance w ith CENTCOM-Joint Theater Support Contracting Command (C-JTSCC) Clause 5152.225-5916, Mandatory Eligibility for Installation Access, offerors and their subcontractors are required to be eligible at the time of proposal submission, and remain eligible, if aw arded a contract, during the entire contract period of performance to include any w arranty period, for installation access to the U.S. and/or coalition installation, regardless of w hether the performance w ill take place on or off a U.S. or coalition installation. The offeror’s not eligible for Base Access w ill be found unacceptable.
TERESA L KELLY
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
04-Aug-2018
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________551 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________25 Aug 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USACE TRANSATLANTIC AFGHANISTAN DISTRICT
CETAA-CT, USACE TAA HQ BAF, BAGRAM
APO AE 09354
W5J9JE
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
12:00 AM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W5J9JE18R0014 95
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W5J9JE18R0014
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Mobilization/Demobilization
FFP
FOB: Destination
NET AMT
0002 1 Job Security
0003 1 Job Demining and UXO Clearance
0004 1 Job Survey and Site Investigation
0005 1 Job Architectural and Engineer Design
0006 1 Job Geotechnical Analysis
0007 1 Job As-Built Drawings
0008 1 Job LSA Expansion Demolition
0009 1 Job Airfield/Operations Demolition
0010 1 Job LSA Expansion Perimeter Wall
0011 4 Each Guard Towers
0012 1 Job Alaska Barrier Wall
0013 1 Job Security Fence
0014 1 Job Site Grading and Drainage
0015 1 Job Concrete Lined Ditches and Culverts
0016 1 Job Perimeter Road
0017 1 Job Concrete Sidewalk
0018 1 Job Aggregate Sidewalk
0019 1 Job Water Well
0020 1 Job Water Storage and Distribution System
0021 1 Job Waste Water Treatment Plant
0022 1 Job Waste Water Treatment Effluent Discharge
0023 1 Job Wastewater Collection System
0024 1 Job Power Connect & Elec Distribution Sys
0025 1 Job Communication Distribution System
0026 1 Job Airfield Rigid Pavement
0027 1 Job Asphalt Pavement
0028 1 Job Airfield Shoulders
0029 1 Job Airfield Paint Striping
0030 1 Job Tie-Downs
0031 1 Job Static Grounding
0032 1 Job Aircraft Barriers
0033 1 Job Exterior Hangar Pavement
0034 1 Job Collapsible Soil Mitigation
0035 2 Each B03-Officers Barracks
0036 2 Each B04-Noncommissioned Officer Barracks
0037 2 Each B06-Enlisted Barracks
0038 1 Job D02-Dining Facility
0039 2 Each AD03-Admin Training
0040 1 Job S01-Storage
0041 1 Job Waste Water Treatment Plant Control Bldg
0042 7 Each UH-60 Hangar
0043 8 Each Relocatable Buildings
0044 1 Job Furniture,Fixtures & Equipment Package 1
0045 4 Each OPTION B03-Officers Barracks
0046 1 Each OPTION B04-Noncommission Officer Barracks
0047 1 Job OPTION Furniture,Fixtures & Equipment Package 2
0048 1 Job OPTION CH-47 Hangar
0049 1 Job OPTION MD-530 Hangar Demolition
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 551 dys. ANP 1 USACE TRANSATLANTIC AFGHANISTAN
DISTRICT
CONSTRUCTION DIVISION
CETAA-CT, USACE TAA HQ BAF,
BAGRAM
APO AE 09354
W5J9JE
0002 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0003 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0004 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0005 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0006 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0007 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0008 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0009 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0010 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0011 551 dys. ANP 4 (SAME AS PREVIOUS LOCATION)
0012 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0013 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0014 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0015 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0016 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0017 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0018 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0019 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0020 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0021 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0022 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0023 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0024 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0025 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0026 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0027 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0028 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0029 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0030 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0031 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0032 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0033 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0034 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0035 551 dys. ANP 2 (SAME AS PREVIOUS LOCATION)
0036 551 dys. ANP 2 (SAME AS PREVIOUS LOCATION)
0037 551 dys. ANP 2 (SAME AS PREVIOUS LOCATION)
0038 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0039 551 dys. ANP 2 (SAME AS PREVIOUS LOCATION)
0040 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0041 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0042 551 dys. ANP 7 (SAME AS PREVIOUS LOCATION)
0043 551 dys. ANP 8 (SAME AS PREVIOUS LOCATION)
0044 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0045 551 dys. ANP 4 (SAME AS PREVIOUS LOCATION)
0046 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0047 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0048 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0049 551 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
Section 00 21 16 - Instructions to Proposers
CLAUSES INCORPORATED BY REFERENCE
52.215-20 Requirements for Certified Cost or Pricing Data or
Information Other Than Certified Cost or Pricing Data
OCT 2010
52.236-28 Preparation of Proposals--Construction OCT 1997 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.236-7008 Contract Prices-Bidding Schedules DEC 1991
CLAUSES INCORPORATED BY FULL TEXT
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
Offers submitted in response to this solicitation shall be in the English language. Offers received in other than English shall be rejected.
(End of provision)
52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2017)
(a) Definitions. As used in this provision--
“Discussions” are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
“In writing or written” means any worded or numbered expression which can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.
“Proposal modification” is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
“Proposal revision” is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
“Time”, if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror.
Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(2) The first page of the proposal must show--
(i) The solicitation number;
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.
(3) Submission, modification, or revision, of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications, or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(ii)(A) Any proposal, modification, or revision received at the Government office designated in the solicitation after the exact time specified for receipt of offers is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and--
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(2) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or
(3) It is the only proposal received.
(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at
52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.
(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(e) Restriction on disclosure and use of data. Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall--
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed--in whole or in part--for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of--or in connection with-- the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(f) Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(2) The Government may reject any or all proposals if such action is in the Government's interest.
(3) The Government may waive informalities and minor irregularities in proposals received.
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.
(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.
(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.
(iv) A summary of the rationale for award.
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price (FFP) contract resulting from this solicitation.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
USACE TAA-HQ
CONTRACTING DIVISION
CHIEF, CONTRACTING
APO AE 09354
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
THERE IS NO OFFICIAL SITE VISIT. THE OFFERORS MAY VISIT THE SITE AT THEIR OWN
EXPENSE AND RISK.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of"(DEVIATION)" after the date of the provision.
http://www.acquisition.gov/far
(b) The use in this solicitation of any Defense Federal Acquisition Regulation Supplement (DFARS) (48 CFR Chapter 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
252.232-7014 NOTIFICATION OF PAYMENT IN LOCAL CURRENCY (AFGHANISTAN) (SEP 2014)
(a) The contract resulting from this solicitation will be paid in Afghani (local currency) if the contract is awarded to a host nation vendor (Afghan), pursuant to the authority of USCENTCOM Fragmentary Order (FRAGO) 09-1567 and FRAGO 10-143. Contract payment will be made in Afghani (local currency) via electronic funds transfer (EFT) to a local (Afghan) banking institution, unless an exception in paragraph (c) applies. Contracts shall not be awarded to host nation vendors who do not bank locally. If award is made to other than a host nation vendor, the contract will be awarded in U.S. dollars.
(b) Vendors shall submit quotations and offers in U.S. dollars. If the contract is awarded to an Afghan vendor, the quotation or offer will be converted to Afghani using a Government budget rate of on date of payment in accordance with the Department of Defense Financial Management Regulation (DOD FMR) official three-day International Transfer Rate. Afghani per U.S. dollar.
(c) By exception, the following forms of payment are acceptable, in the following order of priority, when the local finance office determines that EFT using ITS.gov is not available:
(1) EFT using Limited Depository Account (LDA).
(2) Check from the local finance office LDA.
(3) Local currency cash payments in Afghani (must be approved in writing by the local finance office and contracting office prior to contract award). Payments in cash are restricted to contracts when--
(i) The vendor provides proof via a letter from the host nation banking institution that it is not EFT capable; and
(ii) The local finance office validates that the vendor's banking institution is not EFT capable. Cash payments will be made in Afghani.
http://its.gov/
PHASE ONE - INSTRUCTIONS
SOLICITATION SECTION 00 21 16, INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFEROR
1.0 GENERAL INSTRUCTIONS AND INFORMATION
For clarity, the addressed section shall reference the Solicitation. This section is IAW the Construction Specifications Institute (CSI) pursuant to U.S. Army Corps of Engineers Desk Guide (UDG) 5114.201-1.
This section provides general guidance, as well as specific instructions on format and content, for preparing the offeror’s proposal. The offeror’s proposal shall include all information requested and shall be submitted IAW the Solicitation’s instructions. Compliance with these instructions is mandatory and failure to furnish a complete proposal, at the time of proposal submission, may result in the proposal being unacceptable to the Government and may eliminate the offeror from further consideration for award. It is the offeror's responsibility to ensure the completeness of the proposal submitted. Evaluation of a proposal will be conducted solely on the basis of the information contained within it and the Government will not assume that an offeror possesses any capabilities not specified. Inconsistencies among the parts of each proposal shall be explained. Any unexplained inconsistency may raise a fundamental question of the offeror's understanding of the requirement and/or ability to perform. The offerors are advised that their proposal is presumed to represent its best efforts and most complete responses to the Solicitation.
Proposals that simply reiterate, “Parroting” the contents of the Solicitation, or contain only superficial responses, may be considered unacceptable. Evidence of experience, capability, and qualifications that clearly demonstrate and support the offeror’s claims are essential. The absence of such evidence will adversely influence the evaluation of the proposal.
The Solicitation is to design, procure, and construction AAF Aviation Enhancement at MeS Logistics Support Area (LSA) and Air Wing Operations (AWO) to support roughly 564-personnel (breakdown: 96- Officers, 176-NCOs, 292-Enlisted).
The number in parenthesis below indicates the priority level for those buildings and features to be completed to meet interim completion dates specified herein. The project includes, but is not limited to, the engineering design, materials, labor, and equipment to design and construct the following buildings, utilities, and infrastructure for the Base Proposal Schedule:
LSA
a. Use of all standard designs
b. Perimeter T-wall/wall construction with 4-guard towers around new LSA (Phase 1)
c. 2-Officer barracks to support 96-personnel (Phase 1)
d. 2-NCO barracks to support 176-personnel (Phase 1)
e. 2-Enlisted barracks to support 292-personnel (Phase 1)
f. Demolition of existing buildings on the existing site (Phase 1)
g. Wastewater treatment lagoon system to support the LSA (Phase 1)
h. 2-Standard design (AD03) administration buildings (Phase 2)
i. 1-Dining facility (D02) (Phase 2)
j. 4-Officer barracks to support 192-personnel (Phase 2)
k. 1-NCO barracks to support 88-personnel (Phase 2)
l. 1-Storage facility for class 4 (Phase 2)
m. 1-Well and well house (Phase 2)
n. 1-Water storage tank (Phase 2)
o. Electrical distribution for the LSA will be underground and connected to the local grid
p. FF&E for each facility (CLIN option)
AWO
a. (New paving on the southern portion of the ramp)
b. (Paving repair for sections of the northern part of the ramp)
c. Construct HESCO/T-wall barriers as required for arming/de-arming on the ramp
d. Painting/striping for aircraft parking and operations
e. Aircraft tie downs
f. Ramp lighting for force protection
g. 3-LAMS for aircraft maintenance as part of the base contract
h. 7 –Preengineered metal buiding hangars for UH-60 helicopters
i. 1- Preengineered metal building hangar for CH-47 helicopter
1.1 The offeror is required to follow the procedures in the USACE Engineers Manual (EM) 385-1-1, Safety and Health Requirements.
1.2 The Solicitation will be solicited as full-and-open competition, open to all businesses. A pre-solicitation notice will be published prior to the Solicitation via FBO.
1.3 The acquisition will be subject to FAR Subpart 36.3, Two-Phase Design-Build Selection Procedures, and FAR 15.101-1, Tradeoff Source Selection Process. One solicitation will be issued for this acquisition consisting of a Request for Qualification (RFQ) during Phase One pursuant to FAR 36.3 and Request for Proposal (RFP) for Phase Two pursuant to FAR 15.101-1. (See Section II for further details on the selection process)
1.4 For Phase One, the Government intends to only select up to five offerors that are determined as the most highly qualified Design-Build firms and will be short-listed to participate in Phase Two of the acquisition process. Therefore, offerors should include their best terms and conditions (i.e., Phase One - technical and past performance and Phase Two – technical and cost/price) in the initial offer. The offerors should not assume that they will have an opportunity to participate in discussions or be asked to submit a revised offer.
The Government reserves the right to conduct discussions if the Source Selection Authority (SSA) later determines them to be necessary. By submitting an offer in response to the Solicitation, offerors are agreeing to comply with all the terms and conditions contained in the Solicitation.
1.5 The magnitude of construction is between $25,000,000.00 and $100,000,000.00.
1.6 The primary North American Industry Classification System (NAICS) code for the acquisition is 236220 – Commercial and Institutional Building Construction.
2.0 PROPOSAL VOLUME INSTRUCTIONS, REQUIREMENTS, CONTENTS, AND FORMAT
The Government will not reimburse any cost incurred or associated with preparation and submission of any responses to the Solicitation. Oral explanations or instructions to offerors are not binding. Any information given to an offeror which impacts the Solicitation and/or offer will be given in the form of a written amendment to the Solicitation. Any and all amendments to the Solicitation will be issued electronically via email; it is the offeror’s responsibility to acknowledge any and all amendments in its proposal submission.
The offerors should not modify the terms and conditions of the Solicitation in their technical proposals or add conditions or qualifications to their offers. Should an offeror include terms and conditions that conflict with the terms and conditions of the Solicitation, the offeror may be determined ineligible for award. Any questions related to specific terms and conditions contained within the Solicitation should be resolved prior to submission of an offer.
References to “confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the http://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/ http://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/ offeror’s technical proposal. The offerors that include information in their proposals that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall clearly mark their proposals IAW the instructions at FAR Clause 52.215-1, Instructions to Offerors – Competitive Acquisition, paragraph (e), Restriction on disclosure and use of data.
Use of the words “will,” “shall,” or “must” indicate a mandatory requirement for which failure to comply, at the time and date for submission of proposals, may result in the offeror’s proposal being disqualified from consideration for award, or a deficiency or weakness being assessed for the factor. The Government may elect to initiate discussions with some or all of the offerors, thereby providing a means by which appropriate corrections by the offeror(s) involved can be made. Failure to comply with non-pricing or pricing requirements that are annotated with the words “should” or “may” can result in an unacceptable, which can affect the offeror being selected for the contract award. Time periods, if stated as a number of days, are calendar days unless otherwise specified.
2.1 INSTALLATION ACCESS. IAW CENTCOM-Joint Theater Support Contracting Command (C-JTSCC) Clause 5152.225-5916, Mandatory Eligibility for Installation Access, the Government will determine an offeror non-responsible as a result of an offeror’s base access ineligibility. The Government reserves the right to make this determination at the time of receipt of proposals and prior to the start of evaluations. In this instance, the non-responsible offeror’s proposal will not be evaluated. The Government also reserves the right to determine an offeror non-responsible at any time after receipt of proposals if an offeror becomes ineligible for installation access. A determination that an offeror is non-responsible will result in the removal of the offeror’s proposal from the competition. No debriefing will be provided for those offerors’ found non-responsible as a result of their access ineligibility as the determination may be made in advance of the offeror’s technical proposal being evaluated or completed.
2.2 REQUIREMENTS – E-BUSINESS REGISTRATIONS. Failure to have an active and completed registration in any one of the following electronic database systems below may determine an offeror ineligible for award and removed from competition. A successful offeror with incomplete or expired registrations at the time of award may not be eligible for a contract. In such instances, the Government will award to the next successful offeror who is eligible for award. The Government reserves the right to determine an offeror non-responsible at any time after receipt of proposal if the offeror is found to be ineligible for installation access, as previously stated.
Information contained within an offeror’s registration shall be current and valid. The responsibility of maintaining current information contained in an offeror’s registration rests solely on the offeror.
a. System for Award Management (SAM): http://www.sam.gov/
b. Joint Contingency Contracting System (JCCS): http://www.jccs.gov/
c. Active Afghan Investment Support Agency (AISA) License: http://www.aisa.org.af/ or newly acquired Ministry of Commerce and Industries (MoCI) Entrepreneurial License: http://moci.gov.af/.
***If you are not currently approved in JCCS system, please advise Contract Specialist Teresa Kelly via email at teresa.l.kelly@usace.army.mil, when all required documents have been uploaded.
If an offeror is a joint venture (JV), the JV entity shall have a valid registration representing the JV as one business/firm/entity. This is applicable to SAM, JCCS, and AISA/MoCI. The Government will not accept separate registrations and licenses from each separate entity representing the JV.
An offeror’s subcontractor(s) are required to be registered and active in JCCS. IAW C-JTSCC Clause 5152.225-5916, offerors are required to submit a listing of all proposed subcontractors, at all tiers, to the Contracting Officer (KO) with the submission of their proposal, and provide updates during life of the contract when subcontractors are added or removed. If no subcontractors are expected to perform during the life of the contract, the offeror shall submit a negative response to the KO within its proposal.
https://www.acquisition.gov/browsefar https://www.acquisition.gov/browsefar http://www.sam.gov/ http://www.jccs.gov/ http://www.aisa.org.af/ http://moci.gov.af/ mailto:teresa.l.kelly@usace.army.mil
Subcontractors at every tier are held to the same installation access requirements, as noted above, as the prime contractor.
Joint Venture. A joint venture (JV) is defined as a legal business entity formed between two or more companies to undertake the performance activities of a contract together. The offerors proposing as JV shall provide evidence that the JV as a legal entity has been duly formed. The JV shall include a copy of the legal JV agreement signed by an authorized officer from each of the firms comprising the JV, with the chief executive of each entity identified. The Government will not evaluate the capability of any firms that are not included in the JV agreement.
If submitting a proposal as a JV, the experience of each of the JV partners can be submitted for the JV entity. The experience of either JV partner will be considered the experience of the joint venture entity.
Page and project form limits apply to the JV as a whole, i.e., a submission limitation of two (2) projects under Factor 1 – Specialized Experience and Technical Competence is not an allowance of two projects for each of the JV partners. Prospective offerors that submit proposals may not change their JV firms, if selected for award.
Subcontractors. If the offeror’s proposal includes the use of subcontractors, the offeror may not change subcontractors without the KO’s approval. If the offeror proposes to change subcontractors after award, the offeror may not change subcontractors or LOC without the KO’s approval. Approval will not be given unless the KO considers the proposed substitute to be equal or better in all respects to the originally proposed subcontractor and that the substitution is in the best interests of the Government.
3.0 PROPOSAL CONTENT.
Phase One Technical Proposal. The offerors are required to submit Phase One proposals with at least the minimum specified herein. An offeror’s proposal without the minimum content may be determined ineligible for award and removed from the competition. The Government will not make assumptions concerning intent, capabilities, or experiences. Clear identification of proposal details shall be the sole responsibility of the offeror. The Government may reject incomplete proposals after initial evaluation without further consideration.
All information intended to be evaluated as part of the technical proposal shall be submitted within the technical proposal. Do not include references to material or information not found within its respective volumes. Information submitted in the wrong volumes could lead to an offeror’s proposal being determined unacceptable if materially incomplete in any aspect.
The Government will not evaluate any material that exceeds the page limits specified within each evaluation factor and sub-factors. Elaborately prepared proposals are not required, and any material in excess of what is requested, such as corporate marketing information, will not be considered.
Cover Page: A cover page shall appear at the beginning of each volume and, at a minimum, shall consist of the following information:
a. Solicitation number;
b. Offeror’s name, physical mailing addresses, telephone number, and email address of the official having the authority to bind the offeror contractually;
c. Offeror’s Dun and Bradstreet (DUNS) number, Commercial and Government Entity (CAGE) code, JCCS code, AISA/MOCI license number, and Tax Identification Number (TIN).
Table of Contents: The offerors shall provide a table of contents, placed in each volume and shall identify major areas by title, volume location, and page number.
Volumes: The offerors shall provide three separate proposal volumes: General and Contract Documentation, Technical Proposal, and Past Performance.
Proposal volume organization, number of copies, and page limits. The offeror shall prepare its proposal as set forth below. The Government will not evaluate any pages that exceed the page limitations identified in the Solicitation.
Relative Importance of Phase One Evaluation Factors. Factor 1 and Factor 2 are equal to each other.
Factor 1 is more important than Factor 3. Factor 2 is also more important than Factor 3 – Past Performance.
Volume I – General and Contract Documentation. Volume I shall be clearly marked “VOLUME I –
SOLICITATION W5J9JE18R0014.”
a. Signed Solicitation, Offer, and Award (Standard Form (SF) 1442) with Blocks 14 thru 20c completed, including acknowledgement of all amendments;
b. Completed Corporate Certificate/Authority to Bind Partnership (Attachment 1);
• If the offeror is a corporation, completed Corporate Certificate; or
• If the offeror is a partnership, completed Authority to Bind Partnership and a copy of the
Partnership Agreement; or
• If the offeror is a JV, completed Corporate Certificate for each member of the JV and a copy of the
JV Agreement.
c. Completed Representation and Certification (Section 00 45 00);
d. Completed Financial Standing Questionnaire (Attachment 2); and
e. Copy of valid AISA/MoCI License.
Volume II – Technical Proposal. Volume II shall be clearly marked “VOLUME II – SOLICITATION
W5J9JE18R0014.”
NOTE: DO NOT SUBMIT PRICING INFORMATION IN THE TECHNICAL PROPOSAL.
The offeror shall provide listing of all proposed subcontractors at every tier. In addition, the offeror shall provide Subcontractor and Key Personnel LOC, if applicable.
Note, Lack of applicable LOC is considered a deficiency and submissions lacking the applicable LOC may not be considered.
Factor 1 – Specialized Experience
The offeror shall demonstrate recent and relevant specialized experience on same or similar projects to that of the construction requirements of the Solicitation using Solicitation, Section 00 50 00, Attachment 3 –
VOLUME VOLUME TITLE COPIES* PAGE LIMIT
I General & Contract Documentation *Must be signed
No limit
II Factor 1 – Specialized Experience and Technical Competence 1 See below Factor 2 – Organization and Technical Approach 1 See below
III Factor 3 – Past Performance 1 10 pages total
Experience Overview Sheet, and Attachment 4 – Experience Form. The offeror shall provide narrative that outlines how its recent and relevant experience on prior projects will positively impact its performance of the work contemplated to the Solicitation. Specifically, the offeror shall explain how its prior experience handling construction challenges that are frequently prevalent in Afghanistan will enable it to successfully perform the requirement of the Solicitation.
The offeror’s narrative shall discuss its experience in addressing the following challenges:
• Hiring qualified laborers and maintaining a qualified workforce;
• Application of US and foreign laws that affect contract performance;
• Procurement and shipping of long lead items;
• Obtaining access to work locations, such as obtaining base access;
• Coordination with host nation authorities during contract performance;
• Compliance with contractual, administrative, and other Combating Trafficking in Persons requirement;
and
• Coordination with multiple contractors on site.
Failure to address all the above challenges may result in a deficiency or weakness assessment for this factor.
The offeror may highlight any experience that it has gained, regardless of the date of the project on which this experience was gained or such project’s similarity to the size, scope, complexity, and location of the work contemplated by the Solicitation. For purposes of this portion of the evaluation, the focus is on the offeror’s prior experience in dealing with construction challenges.
The Government will not accept the experience of the offeror’s subcontractor(s). All experience presented shall be the offeror’s.
For each project specifically identified in the offeror’s narrative, the offeror shall provide a completed Attachment 4 – Experience Form. All information items shown on Attachment 4 shall be provided.
Note, for JVs, a strength may be given where the JV partners were the same as the JV offeror.
The prior experience narrative will be limited to 10 pages in length. Attachment 3 and 4 will not be included in the 10-page limitation. Any pages over the page limit will not be reviewed.
Experience narratives shall substantiate the offeror’s technical competence by relating how effectively the offeror’s team applied technical solutions to design and project execution challenges relative to construction of multiple facilities under contingency environment. The Government will evaluate the offeror’s experience on the basis of its breadth, its depth, and its relevance to the work that will be required in the Solicitation, based on the information provided in Attachment 3 and 4, in order to assess the offeror’s qualifications for the project described in the Solicitation.
For purposes of this evaluation, recent and relevant is defined as:
Recent: Projects that are substantially complete (at least 80.0% construction progress completed) or completed and turned over within five years of the Solicitation closing date, performed in Afghanistan, with a contract value at a minimum $15,000,000.00 or greater involving multiple facilities.
Relevant: Design-build construction projects performed in Afghanistan involving multiple facilities that include barracks, administration buildings, latrines, laundry facilities, dining facility, small arms storage, motor pool, electrical power generation facility, water treatment plant, roads and parking, and other supporting utilities with the project valued at a minimum $15,000,000.00 or greater.
Same or similar is defined as projects having the following:
Size. A project with a minimum contract value of $15,000,000.00. All submitted project experience shall meet this requirement.
Scope. A project requiring a similar level of activities (e.g., labor, equipment, materials, management, supervision, etc.) in the design and construction of multiple facilities that include barracks, administration buildings, latrines, laundry facilities, dining facility, small arm storage, motor pool, electrical power generation facility, water treatment plant, road and parking and other supporting utilities with project the valued at minimum $15,000,000.00 or greater.
Complexity. A project that demonstrates similarity in the interrelated work features required in executing multiple concurrent design and construction involving vertical and/or horizontal structures, as specified above. Similarities in features include, but are not limited to surveying, civil, piping and remediation, and construction project elements.
The offerors shall provide no more than three projects that demonstrate the breadth and depth of an offeror’s recent and relevant experience on same or similar projects to that of the construction requirements of the Solicitation. Any project(s) or a combination of projects shall demonstrate that they are the same or similar to the project described in the Solicitation.
Greater weight will be given to offerors for each relevant project evaluated, which includes design and construction of similar types of…