ANA-16-001

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Questions & Answ ers for the Solicitation -

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 25-Nov-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W5J9JE-16-R-0005

X 9B. DATED (SEE ITEM 11)

13-Nov-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

25-Nov-2015

CODE

TRANSATLANTIC AFGHANISTAN ENGINEER - TAA

DISTRICT (TAA), US ARMY CORPS OF ENGINEERS

CETAA-CT, BAGRAM AE 09354

W5J9JE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W5J9JE-16-R-0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION _ - SF 30 BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

Q&A Q. is Section 600 required?

A. N0 – section 600 is not required

Q. The Solicitation says hard copies in block 13 – but in the instructions it says Electronic Copies?

A. Only Electronic copies will be accepted.

Q. Is there a limit to the file size for transmission?

A. Yes – our system will only accept files smaller than 10MB – you may have to send multiple e‐mails to submit your proposals. You are reminded that our server date/time stamps all incoming traffic – your proposal must be accepted by our system by 3:00Pm to on time – if you send it at 2:55 and our system accepts it at 3:01 your late and will not be considered.

Q. How many Guard Towers and how many man‐holes are on the site – so we can calculate the number of T‐walls?

A. The exact number is unknown – for planning purposes please consider that on the West & North site there are 2 towers and no man‐holes, on the PEH Compound & South site there are 4 towers and 13 man‐holes.

Q. What is the distance between fence posts as shown on attachment K for Sniper Screening?

A. The distance varies from 2.5M to 3M – but the average is approximately 2.8M apart.

Q. We have done many projects in Afghanistan for USACE – we are a Turkish Company can we submit a proposal.

A. Anyone can submit a proposal – however this project is set‐aside for 886 companies – only Afghan companies can be awarded the contract.

Q. Can I enter into a Joint Venture – and be awarded this contract?

A. Joint Ventures are permitted – as long as they are registered in JCCS and at www.SAM.gov as a Joint venture by the proposal deadline.

Q. Can I be added to the USACE’s Vendor List?

A. USACE does not maintain a Vendors list – most solicitations will be posted on www.FBO.gov as 886 set‐asides. USACE uses the JCCS system on limited competition requirements

Q. Can I be paid in US Dollars for this project?

A. N0 –Afghan Law requires us to pay in Afghan currency to Afghan Contractors. Since this is set‐aside for only Afghan Contractors – Payment will be made through www.ITS.gov at the 3‐day international transfer rate. Contractors should consider this when developing their proposals. Some Afghan banks

W5J9JE-16-R-0005

will charge a commission to convert payments back to US Dollars. Also the 3‐day official rate is normally lower than the daily transfer rate.

Q. As about 80% project is (T‐Walls), so should we make the T‐Walls on site or need to Build outside and Deliver them to the Site?

A. There is little to no room on site to manufacture T‐Walls on Site – contractors should plan on bring them in from off site.

Q. can we do a site visit?

A. No official site visit is available – offerors are encouraged to make their own site visit if possible.

(End of Summary of Changes)