06/03/2019

M969PRID 145CS101-3Part Number

1680-01-120-7511NSN CH-47FSystem

BRAKE, MAGNETIC YAWNomenclature

YAdequate DMWR Available?

DMWR-55-1680-341DMWR ID

06/15/2013DMWR Date

DMWR Chg #

YPre-Award Survey Recommended?

NCorrelation Performance Study Required ? YPVA Recommended?

See DMWR 55-1680-341 paragraph 3-11 for Overhaul Inspection Procedures (OIP) and Inspection Methods.

Nondestructive testing (NDT) procedures for magnetic particle and flourescent penetrant shall be in acccordance with ASTM E1444 and ASTM E1417 as per DMWR 55-1680-341 paragraph 3-11. All technique sheets shall be reviewed and approved by a certified Level III NDT Inspector. All personnel performing inspection tasks shall be certified in accordance with AIA/NAS 410.

The overhaul facility is responsible for acquisition, maintenance, calibration, and disposition of all Test, Measurement and Diagnostic Equipment (TMDE). TMDE shall be maintained and controlled in accordance with MIL-I-45607, AMCOM-R-70202 or NCSL Z540.3. Calibration documents for all TMDE shall be traceable to the National Institute of Standards of Technology

(NIST).

See DMWR 55-1680-341 paragraphs 4-2 through 4-10 for Final Performance Check procedures. The overhaul facility shall have special tools and test/inspection equipment as specified in DMWR 55-1680-341 paragraphs 2-2.a through 2-2.b. All substitute and equivalent tooling shall require Government approval. The solicitation/RFP shall require that all proposals/responses include a special tooling and test equipment section that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:

1. Physical possession of the required tools.

2. Confirmed requisitions for the required tools.

3. Confirmed arrangements for subcontracting the processes requiring the special tools.

4. Specific plans describing their technical approach to develop equivalent tools.

Identify Any Special Processes, Test Procedures, and/or Instructions

NCritical Safety Item?

There are no emerging airworthiness issues, no issues related to ECPs affecting the CSI status, and no concerns over reliability/durability for the CH-47F Magnetic Yaw Brake at the time of this review.

Special Airworthiness Considerations

AED Notes: FCDD-AMA-M-Sustainment verified the CSI/NST status through the ARIS CIM database on 16 April 2019 and the part is Non-CSI and Non-NST. JC

Other Requirements / Comments

If the item is not a CSI and no adequate DMWR is available, approved sources, if any, are listed by CAGE as follows:

NSpecial Post-Contract Award Requirements?

The applicable DMWR contains detailed procedures regarding IUID requirements for this component. These procedures can be found in MEO D2202, D2203, and D2204.

Other Requirements / Comments (Part II)

AED Notes: FCDD-AMA-M-Sustainment re-verified the CSI/NST status through the ARIS CIM database on 15 May 2019 and the part is Non-CSI and Non-NST. No changes required DEM

Other Requirements / Comments (Part III)

NDoes QE-STD-2 Apply?

N

Additional CSI Requirements

CSI Contains CSI Replacement Parts? NEngineering Testing Required?

The solicitation/RFP shall require that all proposals/responses include a special tooling and test equipment section that addresses the contractor's plan to meet all government special tooling and test equipment requirements with either:

1. Physical possession of the required tools, 2. Confirmed requisitions for the required tools, 3. Confirmed arrangements for subcontracting the processes requiring the special tools, or 4. Specific plans describing their technical approach to develop equivalent tools.

RStatus

YTDPL?

Approved Date

M&O AED REQUIREMENTS DATA

Commerciality Determination

Commercial Item? N NBest Commercial Practice Acceptable?

06/03/2019

M969PRID 145CS101-3Part Number

1680-01-120-7511NSN CH-47FSystem

C4598

D1095

D1258

D1807

D2202

D2203

D2204

See Tables 2-1 and 2-2 of DMWR 55-1680-341 for critical tools and test/inspection equipment.

Critical Tools and Test and Inspection Equipment Requiring AED Approval for Substitutes

MEOs Required for Competitive Contract?

Special Post-Contract Award Requirements

Other Requirements / Comments (Part IV)

Other Requirements / Comments (Part V)

RStatus

Correlation Performance Study Requirements