AMP GAS Industry Questions Answers.pdf
PDF 100 KB Posted
- Attached to
- Request for Information: Advanced Multi-Purpose Round (AMP) Gunner’s Auxiliary Sight (GAS)
- Solicitation number
- W56HZV-19-R-0023
About this file
This document contains questions and answers regarding solicitation number W56HZV-19-R-0023. The solicitation proposes awarding a new requirements contract over five years for the production of Advanced Multi-Purpose Round Gunner's Auxiliary Sight units. The contract will support the Abrams Family of Vehicles program. Offerors must have an approved SECRET facility clearance and the ability to handle classified materials, as the technical data package contains classified specifications. While the solicitation is expected to be posted in October 2020, the government will not release the technical data package or classified specifications to any offerors prior to the official release of the solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMP GAS Industry Questions & Answers
W56HZV-19-R-0023
1) QUESTION: Will the Government accept part numbers that are alternate to AMP
GAS part number 13076936?
ANSWER: No, the Government will not accept alternate part numbers. The offeror must be capable of producing the AMP GAS in accordance with the details within the solicitation in order to be considered for this opportunity.
2) QUESTION: Does the legacy GAS require re-etching of the reticle to produce the
AMP GAS?
ANSWER: Yes. The legacy GAS does require re-etching of the reticle to produce the AMP GAS, but the Government will not accept the Fiber Optic GAS as an alternative. The offeror must be able to produce the AMP GAS as specified in the Technical Data Package.
3) QUESTION: Does the offeror have to have an approved Facility Clearance in place prior to submitting a bid?
ANSWER: Yes. IAW Section M.1.2 (d) of the solicitation, the offeror and its subcontractors must have a SECRET Facility Clearance (FCL) at time of proposal. (See Section L.5.7).
4) QUESTION: If the offeror has an approved Facility Clearance will the
Government release the TDP prior to the release of the official Solicitation?
RESPONSE: No. The Government will not release the TDP to an offeror regardless of whether their Facility Clearance is approved until the official