Attachment C-5.11
Training SOW
As of 4 May 2017 1
STATEMENT OF WORK (SOW)
FOR
TRAINING
FOR THE
LAUNDRY ADVANCED SYSTEM (LADS)
1. SCOPE. The Contractor shall develop and provide all training related aids/materials utilizing the attached
Contract Data Requirements Lists (CDRL), appropriate Data Item Descriptions (DID), and this statement of work (SOW). Upon approval of all training the Contractor shall provide the necessary number of copies referenced for conduct of the training courses as stated in the CDRLs identified in the table below.
This shall include training lesson plans, trainee guides, viewgraphs, Technical Manuals (TM), and other training material, as well as visual aid devices during presentation, such as diagrams, wall charts, schematics, practical exercise sheets, test materials, etc.
CDRL Authority Title SOW Para.
A019 DI-SESS-81518C Instructional Performance Requirements
Document, Operator for Laundry Advanced
System (LADS)
3.2
A020 DI-SESS-81518C Instructional Performance Requirements
Document, Maintainer for Laundry Advanced
System (LADS)
3.3
A023 DI-PSSS-81523C Training Conduct Support Document, Program of Instruction (POI), Operator for Laundry
Advanced System (LADS)
3.4
A024 DI-PSSS-81523C Training Conduct Support Document, Program of Instruction (POI), Maintainer for Laundry
Advanced System (LADS)
3.5
A021 DI-PSSS-81523C Training Conduct Support Document, Lesson
Plan/Trainee Guide/Visual Aids, Operator for
Laundry Advanced System (LADS)
3.6
A022 DI-PSSS-81523C Training Conduct Support Document, Lesson
Plan/Trainee Guide/Visual Aids, Maintainer for Laundry Advanced System (LADS)
3.7
A025 DI-PSSS-81523C Training Conduct Support Document, Conduct of Training, Operator & Maintainer for
Laundry Advanced System (LADS)
3.9 april.l.neihsl Sticky Note what standard will performance be measured by?
april.l.neihsl Sticky Note not tracking the scope references. Do these paragraphs exist? (I think they are below but not in the SOW itself)
Mike.E.Chandler Sticky Note They are listed in the logistic section 5 of the main SOW
As of 4 May 2017 2
2. APPLICABLE DOCUMENTS.
Document ID Title
TRADOC Regulation 350-70 Army Learning Policy and Systems
TRADOC Pamphlet 350-70-9 Total Army School System (TASS) Training Requirement
Analysis System (TRAS)
TRADOC Pamphlet 528-8-2 The U.S. Army Learning Concept
TRADOC Pamphlet 350-70-7 Army Educational Processes http://www.tradoc.army.mil/tpubs/pams/tp350-70-7.pdf
DI-SESS-81518C, including all changes Data Item Description, Instructional Performance Requirements
Document, 17 December 2013. (This DID supersedes DI-SESS-
81518B.)
DI-PSSS-81523C, including all changes Data Item Description, Training Conduct Support Document, 20
November 2014. (This DID supersedes DI-SESS-81523B.)
MIL-PRF-29612B, including all
Revision Notices
Training Data Products
MIL-HDBK-1379
(For Guidance only)
Guidance for Acquisition of Training Data Products and Services
The following items will provided by AMSTA-LCS-EB (TACOM ILSC) at the Logistics Guidance
Conference/Start of Work Meeting:
Warning Icons https://www.logsa.army.mil/mil40051/warning-icons.cfm
3. TASK DESCRIPTION.
http://www.tradoc.army.mil/tpubs/pams/tp350-70-7.pdf https://www.logsa.army.mil/mil40051/warning-icons.cfm
As of 4 May 2017 3
3.1. Army Learning Product Development Overview. The analysis, design, development, implementation, and evaluation (ADDIE) process is a vital mission component that provides mission-focused and task-based training and education. The ADDIE process produces effective and efficient instruction that promotes transfer of learning from the instructional setting to the job. The ADDIE process is a systematic approach to making decisions regarding Army training and education (See U.S. Army
Training and Doctrine Command (TRADOC) regulation (TR) 350-70. This process is used to determine the need, audience, subject, tasks, learning objectives, outcomes, setting, delivery method, and resources required to produce and implement relevant, effective, efficient, and current instruction.
3.2. Instructional Performance Requirements Document (IPRD), Operator. The Contractor shall develop and submit IPRDs for the Operator for the Laundry Advanced System (LADS) (CDRL A019).
3.3. Instructional Performance Requirements Document (IPRD), Maintainer. The Contractor shall develop and submit IPRDs for the Maintainer for the Laundry Advanced System (LADS) (CDRL A020).
3.4. Program of Instruction (POI), Operator. The Contractor shall develop and submit a POI for the
Operator for the Laundry Advanced System (LADS) (CDRL A023).
3.5. Program of Instruction (POI), Maintainer. The Contractor shall develop and submit a POI the
Maintainer for the Laundry Advanced System (LADS) (CDRLs A024).
3.6. Lesson Plan/Trainee Guide/Visual Aids, Operator. The Contractor shall develop and submit Lesson
Plan/Trainee Guide/Visual Aids for the Operator for the Laundry Advanced System
(LADS) (CDRLs A021).
3.7. Lesson Plan/Trainee Guide/Visual Aids, Maintainer. The Contractor shall develop and submit Lesson
Plan/Trainee Guide/Visual Aids for the Maintainer for the Laundry Advanced System
(LADS) (CDRLs A020).
3.8. MOS Requirements. The Operator for all training courses is Shower/Laundry and Clothing Repair
Specialist MOS 92S. The maintainer(s) shall be Quartermaster, Chemical Equipment Repairer MOS
91J and Power Generation Equipment Repairer MOS 91D.
3.9. Conduct of Training, Operator. The Contractor shall provide an Operator and Maintainer training course prior to the start of testing IAW the Master Schedule and IAW CDRLs A023, A024, and A025.
The training course shall utilize the draft training materials and Technical Manuals. The training course shall be provided by a qualified field service representative who has expert knowledge of the system from the Contractor. All documentation required for training shall be provided by the
Contractor.
april.l.neihsl Highlight april.l.neihsl Sticky Note how do we measure this?
Mike.E.Chandler Sticky Note ILSC has equipment specialist that have the necessary knowledge jacob.silcox Sticky Note So Mike, what you're saying then is that Government personnel will provide this training? That is not clear.
Mike.E.Chandler
Jake, i made a mistake it will be the contractor. i have redone the paragraph
As of 4 May 2017 4
The Contractor shall provide Instructor and Key Personnel Training. The training course shall utilize the approved draft training materials and Technical Manuals. The training course shall be provided by a qualified field service representative who has expert knowledge of the systems. All documentation required for training shall be provided by the Contractor.
4. CONTENT REQUIREMENTS.
4.1. IPRDs. All IPRDs shall include all content as identified in Training Matrix for IPRDs, Attachment 1 of this SOW.
4.2. POIs. All POIs will include all content as identified in Training Matrix for IPRDs, Attachment 2 of this
SOW. Format will comply with TRADOC Pamphlet 350-70-7 Army Education Process, LESSON
PLAN SAMPLE (PAGE 69). Link: http://www.tradoc.army.mil/tpubs/pams/tp350-70-7.pdf
4.3. Lesson Plan/Trainee Guide/Visual Aids. All Lesson Plan/Trainee Guide/Visual Aids will include all content as identified in Training Matrix for Lesson Plan/Trainee Guide/Visual Aids, Attachment 3 of this SOW.
5. FORMAT REQUIREMENTS.
5.1. Laundry Advanced System (LADS) Training Documents. All Laundry Advanced System
(LADS) training documents shall be developed, formatted, and delivered IAW TR 350-70 and TRADOC PAM 525-8 and the ADDIE process.
6. ACCEPTANCE/REJECTION OF DELIVERABLES.
6.1. Acceptance/Rejection of Submissions. The Government will evaluate and determine acceptance of all submissions. If any submission is found to be in error, insufficient, or otherwise does not meet the requirements in this SOW and the associated CDRL, the submission shall be rejected and considered a draft until the Contractor corrects the errors. If the Government rejects a submission, it will remain in rejected status until the Government approves that submission. No scheduled submission requirement shall be considered to have been met until the Government has accepted the submission.
6.2. Letter of Acceptance/Rejection of Submissions. The Government will provide written notification of acceptance or rejection to the Contractor.
7. MEETINGS/CONFERENCES.
7.1. Logistics Guidance Conference/Start of Work Meeting. This meeting shall take place at a mutually agreed-upon Government location and date to clarify all matters relating to development, preparation, and submission of data deliverables. The Contractor shall be prepared to identify all questions and discuss all
Training requirements. Follow-on meetings between the Contractor and Government representatives may be held at the request of either party to discuss specific document requirements as they relate to the development of equipment publications for this contract.
http://www.tradoc.army.mil/tpubs/pams/tp350-70-7.pdf april.l.neihsl Sticky Note what does this mean?
Mike.E.Chandler
All questions from the contractor
As of 4 May 2017 5
7.2. In-Process Reviews (IPR). IPR teleconferences will be held, if necessary, as agreed to by both the
Government and the Contractor at the Logistics Guidance Conference/Start of Work Meeting. During preparation of equipment publications, these IPRs will be used to clarify requirements and provide guidance to the Contractor, ensuring the training materials are written to conform to this SOW, the appropriate Army regulations, and the training requirements matrixes in Attachments 1 and 2 of this
SOW. Either the Contractor or the Government may request additional IPRs by teleconference or in person as required for development and delivery of the training materials.
8. DELIVERY REQUIREMENTS.
8.1. IPRDs, POIs, and Lesson Plan/Trainee Guide/Visual Aids. The IPRDs, POIs, and Lesson Plan/Trainee
Guide/Visual Aids shall be developed and delivered separately as distinct training packages. All POIs and IPRDS deliverables will be submitted in Microsoft Word. Lesson Plans/Trainee Guides/Visual
Aides will be submitted in Microsoft Word and PowerPoint. All deliveries will consist of electronic copies (QTY 2) and the final deliveries will also include DVD copies (QTY 2).
END OF LAUNDRY ADVANCED SYSTEM TRAINING STATEMENT OF WORK
april.l.neihsl Sticky Note do we know how many? How do we tell? Is it from the other attachments?
Mike.E.Chandler
It is listed as qty 2 for all items