PD_AWS_Industry_Day_Briefing_01Dec15.pdf
PDF 13 MB Posted
- Solicitation number
- W56HZV15R0187
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pd_AWS_Industry_Day_Company_Attendees.pdf | ||
| Industry_Day_Agenda.pdf | ||
| Notice-MSV-L-FOUO-Instructions.docx | DOCX document | |
| Army_Watercraft_Systems_(AWS)_Industry_Day_Announcement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Mr. Michael Upton Deputy Product Director
Ms. Zina Kozak-Zachary Product Director
Army Watercraft Systems
Industry Day
1 December 2015
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Welcome
Purpose:
1. To provide Industry insight on opportunities for Army Watercraft technologies and services being considered and planned for Army acquisition
2. To improve the development of formal solicitations
3. To promote a Small Business subcontracting network
Objectives:
1. Enhance collaboration between Industry and the Product Director Army
Watercraft Systems (PD AWS)
2. Improve industrial base awareness
3. Leverage Better Buying Process initiatives to reduce costs in all phases of acquisition
4. Improve operational efficiencies/conserve manpower
5. Better understand industry interests and capabilities to address Army Watercraft requirements
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
• Administrative Guidelines/Ground Rules Mr. Michael Upton 0900-0905
• Opening Remarks 0905-0935
• Program Executive Officer Combat Mr. Scott Davis
Support & Combat Service Support Comments
• Project Manager Transportation Systems COL Daniel Furber
• Requirements Perspective COL Steven George 0935-1000
• Army Watercraft Overview Ms. Zina Kozak-Zachary 1000-1030
• BREAK 1030-1045
• Opportunities
• Maneuver Support Vessel (Light) Mr. John McLeish 1045-1115
• Cost Reporting Requirements Mr. Dave Holm 1115-1135
• Research, Development, Test, & Evaluation CPT Ted Halinski 1135-1200
• TACOM Strategic Service Solutions (TS3) Mr. Michael Upton 1200-1215
• LUNCH BREAK 1215-1330
• Small Business Participation/Communication Mr. Andre Shina 1330-1345
Process
• Question/Answer Session 1345-1500
• Closing Remarks 1500
Agenda
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Administrative Guidelines
1. This is an unclassified brief; classified or FOUO information cannot be discussed
2. This is a non-smoking facility
3. Please turn off/silence cell phones, smart phones and pagers
4. Restroom locations
5. Emergency exits
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Ground Rules
1. Questions are desired and encouraged!
• Submit on index cards provided (one question per card).
• Ensure questions are concise and legible.
• Government will answer as many questions as possible during the session today.
• All questions and answers, and the presentations, will be posted to the FBO
Army Watercraft website
(https://www.fbo.gov/index?s=opportunity&mode=form&id=1205a792edce147
2bec4fafb1e40b35e&tab=core&_cview=1); the posted answers will serve as the official Government responses.
2. All program information and presented material remains pre-decisional.
3. Requirements specified in any requests for proposals, once released, will take precedence over Industry Day information.
4. Content is subject to change; nothing said or shown today is binding on the Government.
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
COL Daniel Furber
Project Manager, Transportation Systems
Mr. Scott Davis
Program Executive Officer, Combat Support &
Combat Service Support
Opening Comments
First to the Field … Last to Leave
Force Sustainment Systems
Diving Equipment
Watercraft Systems
Bridging Systems
Construction Equipment
Tactical Vehicles
MRAP Vehicles
Petroleum &
Water Systems
Inflatable Boats & Motors
Test & Diagnostic
Equipment
Mobile Electric Power
Causeways
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional. 7
Transportation Systems
Product Manager Heavy Tactical Vehicles
(PdM HTV)
Product DirectorArmy Watercraft Systems
(PdD AWS)
Product Manager Medium Tactical Vehicles
(PdM MTV)
Product Manager Allied Tactical Vehicles
(PdM ATV)
Product Director Light Tactical Vehicles
(PdD LTV)
Heavy Equipment Transporter System
(HETS)
Line-Haul Tractors
Heavy Expanded Mobility Tactical Truck
(HEMTT)
Palletized Load System (PLS)
FMTV Trailers
FMTV Based Specialty Vehicles
High Mobility Multipurpose Wheeled Vehicle (HMMWV)
Light Tactical Trailer
HMMWV Ambulance
HMMWV With TOW
Mobile Strike Force Vehicle (MSFV)
Landing Craft (Lighters)
Floating Craft
Sports Utility Vehicle ASUV)
Allied Medium Tactical Vehicle
(AMTV)
Allied Light Tactical Vehicle (ALTV)
Bus
Medium Tactical Vehicles (MTV)
Light Medium Tactical Vehicles (LMTV)
Product Director Ground Mobility Vehicles
(PdD GMV)
Air Drop (Notional)
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional. 8
GMV
(Notional)
Support Starts Here!
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.01 Dec 15
Welcome to CASCOM
TRADOC Capability Manager-Transportation
Home of the Army’s Sustainment Think Tank!
Combined Arms Support Command and the
Sustainment Center of Excellence Fort Lee, Virginia
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Army Watercraft and
Maneuver Support Vessel
1-3 Dec 15
COL Steven M. George Director TRADOC Capability Manager – Transportation
CW5 Richard A. Turner Deputy Director, AWS TRADOC Capability Manager – Transportation
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Army Watercraft – A Force Multiplier
A flexible capability which covers diverse mission sets across mission command, sustainment, and movement and maneuver warfighting functions.
Rebalance to Asia Pacific – Potential for long term employment of Army Watercraft as a regionally aligned mobility enabler; enables joint security cooperation and security engagement.
• Supports movement and maneuver: strategic, operational and tactical mobility for Joint and Army forces.
• A2/AD: exploit waterborne maneuver corridors to provide commanders options IOT launch and sustain joint and Army forces along coastal littorals and through inland waterways.
• Operational maneuver: provide the JFC with operational adaptability and assured mobility through the waterborne delivery of combat-configured task organized forces and sustainment.
• Maneuver Support Vessel - Light: future variants bridge strategic to expeditionary maneuver; transition in theater to operational maneuver in support of ULO.
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Harbormaster C3 7 Required 7 on hand
(3 AC/4 USAR)
Landing Craft Mechanized Mod 2 (6)
(1 AC/1 USAR/4 APS)
Barge Derrick (4)
(2 USAR/2 APS)
Small Tug (16)
(2 AC/6 USAR/8 APS)
Large Tug (8)
(I AC/3 USAR/4 APS)
2ea in Lieu of 100 ft tugs
Causeway Ferry (3)
Warping Tug (18)
3 Modular Causeway Systems (1 AC/2 APS)
Floating Causeway (3)
Roll-on/Roll-off Discharge Facility (6)
Landing Craft Utility (34)
(7 AC/7 USAR/ 20 APS)
Logistics Support Vessel (8)
(5 AC/3 USAR)
Landing Craft Mechanized Mod 1 (30)
(8 AC/8 USAR/14 APS)
Principal Fighting Functions
1. Mission Command: Harbormaster, Logistics Over the Shore (LOTS) and Battle Command on the Move
2. Movement & Maneuver: Assured Access, Simultaneous/ Distributed Operations, Controlled Operational Tempo
3. Sustainment: Intra-Theater Distribution, Access to Degraded & Austere Ports/Seaport, Damage/Vessel Salvage, Tugs/Firefighting and Rescue
2 & 3
Operational Force
Army Watercraft Systems
Soldiers
Fleet Size
Army Watercraft MTOE Overview
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
13Support Starts Here!
Army Watercraft Systems (AWS) Vision
Challenges
• Fleet Age
• Constrained resources
• Heavier Combat Systems
• Promote understanding of watercraft as a mobility force multiplier
Frame the Problem
Frame the Operating Environment
Operational Environment (Army Operating Concept)
• Fiscally Constrained
• CONUS based force
• Domain convergence
• Globalization
• Velocity of human interaction
• Advanced technology access
• Regional political instability
• Hybrid strategies and tactics
• Advances in A2/AD
• Non-state political authority
2025 Force Attributes
• Decisive
• Expeditionary
• Responsive
• Adaptive
• Balanced
• Scalable
• Lean
Vision must be informed by CCDR OPLAN requirements and long range emerging concepts (JOAC) AWS Vision
Army Watercraft Fleet Capabilities:
Integrate the Army Warfighting Functions
• Movement & Maneuver
• Sustainment
• Mission Command
Conduct Unified Land Operations
Combined Arms Maneuver
• Decisive, expeditionary & lean
• Move and Maneuver task-organized, combat-ready forces to point of employment
• Responsive mobility enables Operational Access
• Self-deployable, globally positioned & regionally aligned
Wide Area Security
• Responsive, adaptive & scalable
• Agile maneuver & sustainment to distributed forces in A2/AD environments
• Conduct major campaigns, crisis response and military engagement operations simultaneously
Balance Expeditionary & Campaign-Quality Sustainment
• Adaptive, responsive, balanced, & lean
• Enable Strategic and Operational Reach, Freedom of Action and Endurance
• Execute lean, expeditionary sustainment across the distributed OE
• Operate within Unified Land Operations (ULO) , on the seam between maneuver and sustainment
• Reduce tooth-to-tail ratio through innovative nonstandard support mechanisms
An Army Watercraft Fleet for the Army 2025 and beyond capable of conducting expeditionary sustainment, and movement and maneuver of combat forces, in support of
Unified Land Operations.
Problem Statement:
How to achieve an Army 2025 watercraft fleet capable of supporting Unified Land Operations.
“Globally responsive and regionally engaged; set the theater and project power in and through multiple domains.”
Army Operating Concept
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.01 Dec 15
SOF
I
I
I
I
Army Watercraft are Employed in Support of Unified Land Operations to:
Deliver Mission-Tailored Combat-Configured Maneuver Force Elements from Staging/Support Bases to Multiple Points of Entry
Move and Support Widely Distributed Maneuver Force Elements with Sufficient Fire Power, Mobility and Protection to Mitigate Anti-Access Strategies
Conduct Distributed Support and Sustainment Operations Through the Littorals and Waterways , in Fixed and Austere Ports, and JLOTS Operations, Even in Anti- Access/Area Denial Environments, Throughout the Operational Area
JIIM Operations
NGO/IGO/PVO
JLOTS
Support SOF
Intra-theater
Austere Port
HCCC
HCCC
I I
Fixed Port
I I
I
I I
Army Watercraft Operational Concept and Joint Interoperability
“Army forces of sufficient scale must combine quickly with joint, interorganizational, and multinational partners to create multiple options for combatant commanders across the land, maritime …domains…”
FORWARD BASE /
SEABASE
Multiple access points provide options to the CCDR, and pose multiple dilemmas for the adversary.
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional. 14
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
An Army Fleet designed to meet the operational demands of 2020 and beyond Supports implementation of Joint Operational Access Concept
Operational movement and maneuver of combat power
Operational reach from forward station to tactical access points
Deliver operationally significant forces
Seize and sustain momentum with tailored force packages
U.S. Army Strategic Advantages: Leader Development, Mission Command, Mobility & Logistics
• Bridges the gap from strategic deployment to tactical employment of combat power. Mitigating Anti Access/Area Denial (A2/AD) challenges
• Expands the warfighters’ operational reach and freedom of maneuver to seize, occupy and defend land areas, exploit the initiative and create conditions for favorable conflict resolution
Watercraft in the Future Environment
Global and Regional Agility
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Support Starts Here!
will displace the Landing Craft Mechanized 8. This multifunctional landing craft will retain traditional logistics capabilities, but through design modifications will accommodate troops and combat configured equipment.
Regulatory and Doctrinal Framework
Globally postured, regionally aligned waterborne capability that can rapidly deploy combat ready, mission-tailored, ground force formations…to the point of employment…despite austere and denied operational environments…
Ensure freedom of maneuver to the Joint Force Commander
A waterborne corridor for both maneuver and sustainment
Maneuver Support Vessel (Light) (CONOP & Strategy)
Global and Regional Agility
Expeditionary Sustainment & Operational Maneuver
Replaces an aging Vietnam era capability with a multifunctional mobility platform aligned to 2025 and beyond expeditionary operations and Joint Operational Access Concepts.
IAW Title 10, the Army owns watercraft, as required, to execute prompt and sustained combat incident to operations on land.
Joint and Army concepts and doctrine detail the need for future Army forces to bypass developed ports and exploit the sea as maneuver space.
Army Operating Concept Globally responsive and regionally engaged; set the theater and project power in and through multiple domains.
Army 2020: “The Army must re-invigorate capabilities that have declined, develop new capabilities for the changing world and adapt processes to reflect the broader range of requirements."
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
17Support Starts Here!
MSV Heavy MSV Medium
Modernization and transformation of Landing Craft
Fleet
Landing Craft Modernization
FY25 (Projected) FY31 (Projected)
LSV LCU
Landing Craft Mechanized (LCM-8) Maneuver Support Vessel (Light)
This is where we are………..and this is where we’re going.
Vietnam Era… …to 2025 and Beyond
Configuration: Roll through
Length: ~100 feet
Beam: ~30 feet
Draft: 5 feet
Speed: 15 knots
Range: 360 miles
Payload: M1A2 Abrams Tank
Configuration: Single ramp
Length: 74 feet
Beam: 21 feet
Draft: 5 feet
Speed: 9 knots
Range: 271 miles
Payload: 53 tons M1A2 SEPv3 Abrams MBT
2 Stryker with Slat Armor
4 JLTV ‘s
Yes
Yes
Yes
No
No
No
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.01 Dec 15
CASCOM…The Army’s Sustainment Think Tank
../../../CASCOM/James_Madison_Room/CASCOM/James_Madison_Room/2009_Ground_Robotics_Capabilities_Conference/Briefing/NCO Award.wmv ../../../CASCOM/James_Madison_Room/CASCOM/James_Madison_Room/2009_Ground_Robotics_Capabilities_Conference/Briefing/NCO Award.wmv
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Ms. Zina Kozak-Zachary Product Director
Army Watercraft Overview
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional. 20
Mission and Vision
LANDING CRAFT
• Logistic Support Vessel (LSV 1 / LSV 7 classes)
• Landing Craft Utility 2000 (LCU-2000)
• Landing Craft Mechanized (LCM-8) MOD I
• Maneuver Support Vessel (Light) (MSV(L)) - Planned
SHIP-TO-SHORE ENABLERS
• Modular Causeway Systems (MCS)
• Roll-on/Roll-off Discharge Facility (RRDF)
• Floating Causeway (FC)
• Causeway Ferry (CF)
• Modular Warping Tug (MWT)
TOWING AND TERMINAL OPERATIONS
• Large Tug 800 (LT-800)
• Small Tug 900 (ST-900)
• Barge Derrick, 115 Ton (BD-115T)
WATERCRAFT OPERATIONS SUPPORT
• LCM-8 MOD II
Provide efficient and effective Life Cycle Management of the global Army watercraft fleet by delivering the most safe, suitable, and supportable systems to the Army Mariner.
MISSION SYSTEMS OF PRIMARY FOCUS
Committed to providing the best materiel solutions through superior acquisition practices.
VISION
AR 70-1 Army Acquisition Policy: PMs are responsible and accountable for the life cycle management of their assigned programs. As such, there is no transition of life cycle management responsibility away from the PM.
Our primary customers are the Soldier and the taxpayer.
TCM-T is our primary interface with the Soldier.
Product Director (PD)
Ms. Zina Kozak-Zachary
Deputy PD: Mr. Michael Upton
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Department of the Army
Army
Materiel
Command
(AMC)
ASA(ALT)
PEO
Soldier
PEO
CS&CSS
PEO
GCS
TACOM
LCMC
RDECOM
ARDEC TARDEC NSRDEC
PEO I
PM LAV
Army
Contracting
Command
ECBCJPEO
CBD
Depots and
Arsenals
PM TS
PD AWS
ILSC
PD AWS executes Life Cycle Management (LCM) through a unique matrix of organizations
Organizational Structure
Army
Contracting
Command -
Warren
Modernization
Sustainment http://images.google.com/imgres?imgurl=https://remedyweb.scn.spawar.navy.mil/SSC_ATL_reg mark_72dpi.jpg&imgrefurl=https://remedyweb.scn.spawar.navy.mil/&usg=__7SS8mZM_IOxwvWCOvDcOZFziBW0=&h=215&w=217&sz=50&hl=en&start=4&um=1&tbnid=h-cq6_Vv2VCAMM:&tbnh=106&tbnw=107&prev=/images?q=spawar+ssc+logo&hl=en&um=1 http://images.google.com/imgres?imgurl=https://remedyweb.scn.spawar.navy.mil/SSC_ATL_reg mark_72dpi.jpg&imgrefurl=https://remedyweb.scn.spawar.navy.mil/&usg=__7SS8mZM_IOxwvWCOvDcOZFziBW0=&h=215&w=217&sz=50&hl=en&start=4&um=1&tbnid=h-cq6_Vv2VCAMM:&tbnh=106&tbnw=107&prev=/images?q=spawar+ssc+logo&hl=en&um=1
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
L & T support agencies work with PD AWS on the deck plates
ILSC - PSID
Gary Vollmer (A)
• Logistics management
• Technical publications
Carderock Kevin Driscoll
Hull and System Modernization
• In service engineering
• MWO design and install
• Panama City: SCBA engineer
PEO C3T/ CECOM
C4ISR sustainment
• Sustainment level maintenance
• C4ISR contract field support
• C4ISR technical publications
SPAWAR
George Oakley
C4ISR modernization
• C4ISR engineering
• MWO design and install
Vessel PI’s
Vessel Assistant Product
Managers
PD AWS
Zina Kozak-Zachary
Technology Acquisition Logistics
TARDEC
Watercraft Inspection Branch Tim Claus
• Sustainment level maintenance (2LM)
• On Condition Cyclic Maintenance
Marine Engineer Mgr CW4 James Crouse
TACOM Safety
• Safety and risk assessment
Deputy PD Michael Upton
Business Branch
Engineering Branch
Logistics Branch
LCM Partnerships http://images.google.com/imgres?imgurl=https://remedyweb.scn.spawar.navy.mil/SSC_ATL_reg mark_72dpi.jpg&imgrefurl=https://remedyweb.scn.spawar.navy.mil/&usg=__7SS8mZM_IOxwvWCOvDcOZFziBW0=&h=215&w=217&sz=50&hl=en&start=4&um=1&tbnid=h-cq6_Vv2VCAMM:&tbnh=106&tbnw=107&prev=/images?q=spawar+ssc+logo&hl=en&um=1 http://images.google.com/imgres?imgurl=https://remedyweb.scn.spawar.navy.mil/SSC_ATL_reg mark_72dpi.jpg&imgrefurl=https://remedyweb.scn.spawar.navy.mil/&usg=__7SS8mZM_IOxwvWCOvDcOZFziBW0=&h=215&w=217&sz=50&hl=en&start=4&um=1&tbnid=h-cq6_Vv2VCAMM:&tbnh=106&tbnw=107&prev=/images?q=spawar+ssc+logo&hl=en&um=1
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Modular Causeway System (MCS)
Logistic Support Vessel (LSV)
Landing Craft Utility (LCU) 2000
Landing Craft Mechanized (LCM-8)
Large Tug (LT)
Small Tug (ST)
Barge Derrick (BD)
Roll-On/Roll-Off Discharge Facility (RRDF)
Causeway Ferry (CF)
Modular Warping Tug (MWT)
Floating Causeway (FC)
5 AC/3 RC/0 APS 1 AC/2 RC/3 APS
7 AC/7 RC/20 APS 2 AC/6 RC/8 APS
9 AC/9 RC/18 APS 0 AC/2 RC/2 APS
2 AC/0 RC/4 APS 5 AC/0 RC/11 APS
1 AC/0 RC/2 APS 1 AC/0 RC/2 APS
Years
Years
Years
Years
Years
Years
• Small density fleet
• No single OEM or Depot
• Many different configurations
• Several platforms at or past EUL
(To be displaced by the MSV(L))
Years
Years
Years
Years
1988 – First Fielding 1994 – First Fielding
1990 – First Fielding 1998 – First Fielding
1967 – First Fielding 1999 – First Fielding
1996 – First Fielding
Fleet Overview
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Small Tug 900
Baltimore (1)
Tacoma (2)
Fort Belvoir(8)
Small Tug 900 Large Tug 128
Landing Craft Mechanized (LCM)
Landing Craft Utility (LCU) 2000
Landing Craft Utility (LCU) 2000
Morehead City (1)
Tampa(1)
Mare Island (5)
Prepositioned Equipment Packages
APS 4 Storage Site:
Japan
LCU 2000
LCM 8s
Large Tugs (128 ft)
Small Tugs
Barge Derrick
Total
O/H
APS 5 Storage Site:
Kuwait
LCU 2000
LCM 8s
Large Tugs
Small Tugs
Barge Derrick
Total
O/H
Small Tug 900
Reserve Component Current Watercraft Locations
Baltimore (1)
Tacoma (2)
Fort Belvoir(3)
Small Tug 900 Large Tug 128
Landing Craft Utility
Morehead City (1)
Tampa(1)
Port Hueneme (4)
Barge Derrick 115 ton
Baltimore (1)
Tacoma(1)
Baltimore (1)
Tacoma (2)
Mare Island (2)
Logistic Support Vessel
Hawaii (1)
Tacoma (1)
Baltimore - KU (1)
Landing Craft Mech
Tacoma (2)
Landing Craft Utility
Baltimore (1)
Morehead City (1)
MCS System 1MCS System 1
Tampa(1)Tampa(2)
Active Component Current Watercraft Locations
Ft. Eustis (1)
Ft Eustis (9)
Small Tug 900
Large Tug 128
Landing Craft Mechanized (LCM) -8
Landing Craft Utility (LCU) 2000
Logistic Support Vessel (LSV)
Ft. Eustis (7)
Hawaii (2)
Kuwait (2)
Ft. Eustis (2)
Modular Causeway System:
Causeway Ferry (1) , Roll - On/Roll -Off Discharge Facility (2), Floating Causeway (1), Warping Tug (6)
Ft. Eustis (1)
Logistic Support Vessel (LSV)
CENTCOM
SOUTHCOM
NORTHCOM
PACOM
COCOM Watercraft Support
Landing Craft Mech-8
Landing Craft Utility
Landing Craft Mech-8
Small Tug 900
Current Locations
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Portfolio Priorities
1. Continue execution of LCU C4ISR Upgrade
2. LCU Service Life Extension Program (SLEP)
• Released Request for Proposal (RFP) on 18 Sept 2015
• Contract Award in FY16
3. Maneuver Support Vessel Light (MSV(L))
• Release RFP
• MS B
• Contract Award
25 25
1 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional. 26
Opportunities
DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Mr. John McLeish Program Integrator
Maneuver Support Vessel (Light)
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
MSV(L) Description & Overview o New Start Army Acquisition Program o Description:
Represents a key capability in mitigating anti-access/area denial environments by exploiting waterborne maneuver corridors to deliver operationally significant combat power to a point of advantage over an adversary.
Operates in and along coastal waters, narrow inland waterways and rivers; enables access through multiple points of entry and is not reliant on infrastructure afloat or ashore.
This multifunctional landing craft will retain traditional logistics capabilities, but through design modifications, will accommodate troops and their combat configured equipment.
Will provide greater capability over the vessel it displaces in payload, speed, improved Draft and Force Protection/Survivability, while being more energy efficient.
o Displacement: Will displace the current Landing Craft Mechanized-8 (LCM-8).
o Army Acquisition Objective (AAO): 36 o Army Procurement Objective (APO): 28
Still an Affordability Driven Acquisition Strategy – Unit Cost is still an objective!
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
What changed from last year?
o Analysis of Alternatives (AOA) completed: Approved 16 June 2014. Final report was signed 19 February 2015 o Requirement was approved: Capability Development Document (CDD) approved 7 August o Published Request for Information (RFI) posted, 9 June 15 and closed 7 July 15 Draft documents included with RFI: Section C – Statement of Work (SOW), Army
Technical Product Description (ATPD), Production Schedule, and Payload Requirements Average Unit Manufacturing Cost (AUMC) cost caps were stated for the Prototype, Low
Rate Initial Production (LRIP) and Full Rate Production (FRP) vessels o Industry: You got our attention – you told us
Trades required to meet cost goals More time required for you to design and for prototype build Provided insight into cost drivers o Our response:
Took a hard look at requirements, resulting in de-scoping and adjusting requirements in the CDD, Army Technical Purchase Description (ATPD) & Scope of Work (SOW) Working Program Objective Memorandum (POM) Fiscal Year (FY)18-22
Wide Stakeholder Support for MSV(L)!
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Acquisition Strategy
Phase 1: Engineering Manufacturing Development (EMD)/LRIP Phase [6-years period of performance]
Build two (2) scale models; conduct Model Testing to prove out seaworthiness & seakeeping
Build one (1) Full Scale Prototype
Deliver Commercial Off the Shelf (COTS) Technical Manuals (TMs) and training to commence test
Test prototype vessel to achieve performance requirements
Refine Final Design
Start the development of Integrated Logistics Support (ILS) products
Produce four (4) LRIP
Conduct First Article Test (FAT)/Production Verification Testing (PVT)
Deliver all ILS products necessary for fielding to include TMs, training packages, etc.
Achieve Full Material Release (FMR) and Full Rate Production (FRP)
Phase 2: Production [5-year period of performance] FRP up to an additional 32 vessels
Contractor fielded In Accordance With (IAW) Total Package Fielding (TPF) concept
De-processing, Inventory, and Hand-off of the vessel with all associated support equipment, and TMs; and Training
Still One contractor – start to finish!
Pre-Decisional
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Draft Program Schedule
EMD Production Schedule
FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27
MSV(L) 0 0 1 0 2 2 4 6 8 8 6
LRIP vessels for PVT/FAT/Logistics
• Developmental
• User Test
• FRP
• Fielding starts
One Prototype for test
Performance gates throughout acquisition
Pre-Decisional Production Schedule reflects AAO = 36
APO = 28 vessels
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Draft Acquisition Timeline
Evalution Process
Second Expanded
RFI
Posted
Final RFP Released
JAN
JUN
AUG
MAR
Contract
Award
2021-
EMD Phase (4 years) 2017-20
Production of 4 LRIP Vessels
2023-
Model Basin Testing
APR
Start of Work
Meeting
Proposals
Received
Full Rate Production (32 vessels)
Production Phase (7 Years) 2021-27
Production of Full Scale
Prototype Vessel
Prototype Testing
Logistics Efforts (Technical Manuals, Provisioning, Training, etc)
More time to get it right during EMD phase!
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Proposed Contract Strategy
Full and Open Competition
One contract award
• During Source Selection Evaluation Board (SSEB) selects one contractor for all phases
• Fixed Price Incentive (Firm Target) FPI(F)
• Indefinite Delivery/Indefinite Quantity (IDIQ) Contract Type
EMD Phase: For risk reduction, prototype, and test and evaluation. If successful exercise production option
Production Options: Produce, train, and field
Requirements/Deliverables for EMD Phase:
• Design, integrate Government Furnished Equipment (GFE), and test one prototype vessel
• Provide test support during developmental, performance, Reliability and Maintainability Development (RAMD), and Limited User Testing (LUT)
Requirements/Deliverables for Production:
• Develop and deliver Government Purpose Technical Data Package (TDP) (Level III drawings)
• Develop and deliver all ILS products including Interactive Electronic Technical Manuals (IETMs); Technical Data; Packaging, Handling, Storage & Transportation (PHS&T); Training Support Package (TSP);
Maintenance; Supply; and Support Equipment
• Conduct Initial Key Personnel Training (IKPT) and New Equipment Training (NET) for both Operator and Maintenance training
• Produce and field 36 MSV(L) vessels (4-LRIP; up to 32 after FRP)
• Provide Field Service Representative (FSR) support
Yes, there will be deliverables! Yes, there will be logistics!
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Important Points of Interest
• GFE: Contractor integrated. PD AWS will provide interface data, space claim, etc.
in RFP Solicitation. Will provide suites of hardware after award, prior to prototype build Two (2) Army Program of Record (POR) Remote Weapon Stations (RWS) currently Common Remotely Operated Remote Weapon Station (CROWS II) Command, Control, Communications, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) GCSS-A workstation and Maintenance Support Device (MSD)
• Modeling & Simulation (M&S): Strategy to utilize M&S where needed or feasible Model and Sea-Keeping Testing (MASK): Dynamic Stability Test & Sea Keeping
Test (self propelled) Basin Tests: Resistance Test & Power Test (towed) Must pass prior to authorizing prototype start.
• Build to American Bureau of Shipping (ABS) High Speed Craft (HSC) Rules and the Code of Federal Regulation (CFR) which will be coordinated and managed by the Contractor.
• Data Bus: MSV(L) will be the Army’s first digital vessel
ATPD specifies nearly 500 singularized requirements!
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Key Performance Parameters (KPPs)
1. Payload One M1A2 Tank, (weight driver) or Four JLTVs w/o trailers, (cube driver) or Two Strykers with Bar armor, (Ramp width driver) or Two Bradleys, or One LHS or PLS with trailer Tie downs must allow or enable ramps to be dropped and doors to be open
2. Functional Draft Operational at <5 feet of water Further defined “operational” in shallow water
3. Survivability Seaworthy fully loaded at Sea State 7
(SS7) (MASK model testing)
4. Force Protection Remote Weapons Stations (GFE) Identification Friend or Foe (IFF)
(GFE)
Subsurface Surveillance (Classified
Annex to ATPD)
5. Speed 15 Knots laden / 24 Knots un-laden in SS3
6. Energy Efficiency Move a CAB(-) or equivalent lethality more efficiently than the
LCM-8
Key vessel design drivers; threshold requirements summarized. Fully Loaded (laden) means combat loaded with troops and all equipment and supplies!
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Key System Attributes (KSAs)
1. Range 400 nautical miles (nm) empty; 360 nm fully loaded Continuous operation for 24 hours without refueling or re-provisioning
2. Vessel Defense (Classified Annex of
ATPD)
Ballistic protection Thermal and acoustic signature;
and dark ship capability
3. Vessel Ramps Bow ramp & Stern Access Drive through capability!
4. Cargo Operations Dependent on Army BCT MHE Deck configuration, arrangement, PSI, and tie-downs must accommodate identified payloads!
5. Vessel Operations Operational in SS3 fully loaded
6. Inter-Theater Movement Capable of being loaded and moved on heavy lift ships or semi-submersible vessels
7. Reliability, Availability, Maintainability No less than two propulsion systems; 90% plus readiness
8. Condition Based Maintenance Plus (CBM+) Lowered Threshold -
Diagnostics Created Objective - Prognostics
9. Training Development Designed to operate by MOS
88K, 88L, 880A, and 881A.
List is not inclusive. Highlights some of the Key Characteristics at the threshold level
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Additional Performance Attributes
(APAs)
1. Crew Support Equipped with PA System, Intercom System, and climate controlled Meet human factors requirements for all mission tasks in all environments Water & sewage with potable water & sewage (UNDS) treatment for crew and embarked unit personnel
2. Embarked Unit support
Able to supply power to embarked unit platforms while enroute.
Sanitary facilities must be sufficient to accommodate embarked unit personnel Infantry Platoon:
Storable seating equipped with seat belts, sun/rain temporary cover on main deck.
Storage space for individual weapon, helmet, body armor, and Load Bearing Equipment (LBE) near soldier.
3. Refueling Operations Able to refuel and be refueled by other vessels in Army Watercraft fleet Able to be refueled by military and commercial facilities worldwide Fuel tanks will be sub-divided to minimize free surface effects, improve stability
List is not inclusive. Highlights some of the Key Characteristics at the threshold level
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Additional Requirements Information
• Service Electrical Service Life Margin: lowered (T) to 10% and created (O) at 20%
• Climate & HVAC: Lowered (T); created (O)
HOT:
o Remain fully operational at ambient air temperature of 95F (T) and 110F (O) o Remain operational at a sea water temperature of 95F (T), 110F (O) without degradation
Cold:
o Fully operational at ambient air temperature of -5F (T) to -25F (O) o Operational at a sea water temperature of 32F (T), 25F (O) without degradation
General:
o Meet all operational performance requirements for all equipment and machinery located in exposed conditions in ambient air temperatures of -5F (T), - 25F (O) in Sea State 7 wind conditions o Propulsion equipment that takes air from within the machinery space shall meet all operational performance requirements in ambient air temperatures of +20F minimum to +120F maximum o HVAC shall be designed for 10F and 110F environments; maintain occupied spaces (not machinery) to +/- 10F
• Dynamic Positioning (DPS): Created lower (T); moved DPS to (O) Provide an anchoring system capable of kedging and maintaining vessel orientation while conducting beach loading and unloading operations (T)
Provide a dynamic positioning system that can keep the vessel stationary during in-stream operations (O)
Look for these adjustments and others in updated ATPD.
01 Dec 15 DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Closing MSV(L) Highlights
• RFIs: PD AWS has posted RFIs in 2012, 2013, 2014, & 2015 as the requirement has matured
• Path forward:
Publish one more RFI before releasing draft RFP. It is intended to include:
Updated requirement in ATPD format
Updated Section C – SOW with Contract Data Requirement List (CDRLs) items
Provide: Section E (quality), Section J (attachments), & others as may be available
Classified Annex to ATPD has been completed. It is available upon request – follow procedures
Publish a draft RFP in the spring
Publish a final RFP in the summer
Bottom Line:
• We are moving forward, building RFP package, striving to get it right!
• Your feedback is important to us!
• We are leveraging wide stakeholder support!
• Winning competitor must be able to perform as the prime, managing all sub-contractors, tasks, and functions to success!
40DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Maneuver Support Vessel (Light)
Industry Day
Introduction to
Cost and Software Data Reporting
Mr. David Holm
Director, Cost and Systems Analysis
Materiel Systems Organization
U.S. Army TACOM LCMC
41DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Agenda
• History and Description of CSDRs
• CSDR Benefits
• MSV(L) CSDR Reporting requirements
• Readiness Review
• Summary
42DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
History & Purpose of CSDRs within the DoD
• History ▫ Official cost reporting dates to 1960s
▫ Software reporting introduced in late 1990s
▫ OSD established Defense Cost & Resource Center (DCARC) office in late 1990s to manage ACAT 1 level programs.
• Purpose ▫ Cost data
A systematic and standardized process to collect return cost data by MIL-STD-881C Work Breakdown Structure
▫ Software Data
Collect via Data Item Description (DID) at levels consistent with software estimating needs
43DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
• GAO identifies the availability of valid data as a basic characteristic of a credible cost estimate ▫ Numerous sources of suitable, relevant, and available data should be used
▫ Relevant historical data should be used from similar systems to project costs of new systems. The historical data should be directly related to the system performance characteristics
• Cost and Software Data Reports (CSDRs) constitute relevant historical data
Importance of CSDRs to Cost Estimation
“Deriving quality cost estimates depends on the quality of historical databases. In most cases, the better the data are, the better the resulting estimate will be.”
Source: GAO – Cost Assessment Guide, Best Practices for Estimating and Managing Program Costs (July 2007)
44DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
What are Cost and Software Data Reports? (CSDRs)
CCDR SRDR CSDR
Contractor Cost
Data Report
Software Resources
Data Report
Cost and Software
Data Report
Organized via a standard, product-oriented WBS
Using MIL-STD-881C Appendix E Sea Systems WBS for prime system contracts
Reporting required on MDAP/MAIS contracts and subcontracts
‒ Over $50M / Optional between $20M and $50M / Special Interest
Data helps project future program & contract costs
Data is available to all DoD Government analysts electronically
What purpose do
CSDRs serve?
What types of reports does
DCARC
have?
Why are these reports required?
How does this help me?
45DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Types of CSDRs
CSDRs CSDR Plan
(DD 2794)
Contract Work Breakdown Structure Dictionary
Cost Data Summary Report
(DD 1921)
Functional Cost- Hour Report
(DD 1921-1)
Progress Curve Report
(DD 1921-2)
Contractor Business Data
Report
(DD 1921-3)
Sustainment Report
(DD 1921-4/5)
Software Resource Data Reports
(SRDRs)
“Dictionary”
“Cost Summary”
“Functional Breakout” “By Tail Number”
“Business Base”
“Sustainment”
“Software”“Plan”
Technical Data Report (1921-T)
Coming Soon
= Applicable to MSV(L) program
46DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
CSDR Plan
Defines WBS used for CSDR submissions
Identifies required reports
Lists Submission Events and expected due dates
Contains Standard Plan Language and Special Contractor
Instructions
CSDR Plan - DD Form 2794
a. NAME:
Pre-A B C-FRP
A C-LRIP O&S
PROGRAM
a. CWBS
DICTIONARY
d. DD 1921-2
(PCR)
f. SRDR
FORMATS
DD FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE
3. SUBMISSION TYPE
9c. APPROPRIATION
RDT&E
PROCUREMENT
O&M
4. CURRENT SUBMISSION
DATE (YYYYMMDD)
5. LAST APPROVED PLAN DATE
(YYYYMMDD)
e. DD 1921-4
(CSR)
COST AND SOFTWARE DATA REPORTING PLAN
Form Approved
OMB No. 0704-0188
b. PHASE/MILESTONE c. PRIME MISSION PRODUCT
The public reporting burden for this collection of information is estimated to average 8 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information.
Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ORGANIZATION.
2. WBS SYSTEM TYPE
1. MAJOR PROGRAM
6b. TELEPHONE NUMBER (Include Area Code) 6c. FAX NUMBER (Include Area Code)
INITIAL
CHANGE
7. PLAN TYPE
CONTRACT (PRIME)
CONTRACT (SUB)
8. PREPARING
ORGANIZATION ii. DIVISIONi. PERFORMING ORGANIZATION
9b. CONTRACT NUMBER
6d. E-MAIL ADDRESS6a. POINT OF CONTACT (POC) NAME AND ADDRESS (Include ZIP Code)
10. APPROVED PLAN NUMBER
11. WBS ELEMENT CODE
13. REPORTS REQUIRED
(X if applicable)
9a. CONTRACTOR NAME/ADDRESS
DD 1921-3 (CBDR):
a. PROGRAM/
CONTRACT/
SUBCONTRACT
b. CONTRACT/
SUBCONTRACT
12.
WBS REPORTING ELEMENTS
b. DD 1921
(CDSR)
c. DD 1921-1
(FCHR)
d. AS OF DATE e. DUE DATE
(YYYYMMDD) (YYYYMMDD)
DD FORM 2794 (PAGE 2), MAY 2011 PREVIOUS EDITION IS OBSOLETE
14. CSDR SUBMISSION DATES
15. REMARKS
c.
EVENT
a.
SUBMISSION
b.
FORM(S)
Submission Events
Contract Plan
Language and
Special Instructions
Metadata
Element Code and
Reporting
Elements
Required
Reports
47DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Top Level View of CSDRs
DD 1921
Displays ALL WBS elements
Recurring & Nonrecurring costs
Actual costs to date, estimates at completion
Number of Units
Contract Totals
G&A, FCCM,
UB, MR, and
Fee
DD 1921-1
Insight into individual
WBS elements
Recurring & Nonrecurring costs
Actual costs to date, estimates at completion
Detailed breakout of all resource data
Reporting by functional categories
CWBS
Dictionary
Provides definitions for all
WBS elements
Cost, technical and work content included in definitions
Physical description for all hardware elements
DD 1921-2
For specific hardware WBS elements
Unit or Lot reporting
Technical Characteristics
To Date, Direct Recurring costs
& hours
Detailed breakout of resource data
Reporting by functional category
48DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
What are the benefits of CSDR data?
• CSDR deliverables are specific to a single contract
• Reported data reflects contractor cost data and visibility into profit
• Data supports development of homogeneous data sets pooled from multiple programs
• Structure of actuals data collection is consistent with structure of estimates
• Product oriented vs. Process oriented
• Separate identification of recurring and nonrecurring HW costs, which in turn facilitates estimation of ▫ Design cost
▫ Prototype vs. Production hardware cost
• Separate identification of functional category costs (e.g. Engineering, Manufacturing Operations, Materials)
• Data supports development of homogeneous data sets pooled from multiple programs
• The use of CSDR data as the basis for cost estimates yield:
▫ Credible cost estimates
▫ Realistic budgets
▫ Executable program
49DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Goals & Expectations for Industry
• Each firm under contract for the MSV(L) program should know how to:
▫ Effectively plan for CSDR requirements
▫ Effectively manage all CSDR requirements
▫ Effectively deliver mathematically accurate data consistent with Contract CSDR Plan and DID, and derived from cost account data
CSDRs will be reviewed and validated for mathematical accuracy by the TACOM Cost and Systems Analysis office
We validate cost reports, CWBS dictionaries and software reports
If a CSDR deliverable is rejected, the firm is required to resubmit
50DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
WBS # Level 1 Level 2 Level 3
1.0 Sea System
1.1 Ship
1.1.1 Hull Structure
1.1.2 Propulsion Plant
1.1.3 Electric Plant
1.1.4 Command, Communications and Surveillance
1.1.5 Auxiliary Systems
1.1.6 Outfit and Furnishings
1.1.7 Armament
1.1.8 Total Ship Integration/Engineering
1.1.9 Ship Assembly and Support Services
1.2 System Engineering
1.3 Program Management
1.4 System Test and Evaluation
1.4.1 Development Test and Evaluation
1.4.2 Operational Test and Evaluation
1.4.3 Mock-ups / System Integration Labs (SILs)
1.4.4 Test and Evaluation Support
1.4.5 Test Facilities
1.5 Training
1.5.1 Equipment
1.5.2 Services
1.5.3 Facilities
1.6 Data
1.6.1 Technical Publications
1.6.2 Engineering Data
1.6.3 Management Data
1.6.4 Support Data
1.6.5 Data Depository
1.7 Peculiar Support Equipment
1.7.1 Test and Measurement Equipment
1.7.2 Support and Handling Equipment
1.8 Common Support Equipment
1.8.1 Test and Measurement Equipment
1.8.2 Support and Handling Equipment
1.9 Operational/Site Activation
1.9.1 System Assembly, Installation and Checkout on Site
1.9.2 Contractor Technical Support
1.9.3 Site Construction
1.9.4 Site/Ship/Vehicle Conversion
1.9.5 Sustainment/Interim Contractor Support
1.10 Industrial Facilities
1.10.1 Construction/Conversion/Expansion
1.10.2 Equipment Acquisition or Modernization
1.10.3 Maintenance (Industrial Facilities)
1.11 Initial Spares and Repair Parts
Reporting Structure – MIL-STD-881C
Appendix E (Sea Systems)
51DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
MSV(L) Cost Reporting Plan
COST AND SOFTWARE DATA REPORTING PLAN
Form Approved
OMB No. 0704-0188
1. MAJOR PROGRAM a. NAME: Maneuver Support Vessel (Light) Program
b. PHASE/MILESTONE c. PRIME MISSION PRODUCT 2. WBS SYSTEM TYPE
3. SUBMISSION TYPE 4. CURRENT SUBMISSION DATE
(YYYYMMDD)
5. LAST APPROVED PLAN DATE
(YYYYMMDD)
Pre-A X B X C-FRP Landing Craft Sea Systems
X INITIAL
A X C-LRIP O&S CHANGE
6a. POINT OF CONTACT (POC) NAME AND ADDRESS (Include ZIP Code) 6b. TELEPHONE NUMBER (Include Area Code) 6c. FAX NUMBER (Include Area Code) 6d. E-MAIL ADDRESS
7. PLAN TYPE
8. PREPARING
ORGANIZATION
9a. CONTRACTOR NAME/ADDRESS 9b. CONTRACT NUMBER 9c. APPROPRIATION 10. APPROVED PLAN NUMBER
PROGRAM X CONTRACT (PRIME) i. PERFORMING ORGANIZATION ii. DIVISION
TBD
X
RDT&E
NA
CONTRACT (SUB)
Product Director Army
Watercraft Systems
TBD
X PROCUREMENT
O&M
11. WBS ELEMENT CODE
12.
WBS REPORTING ELEMENTS
13. REPORTS REQUIRED
(X if applicable)
DD 1921-3 (CBDR):
a. PROGRAM/
CONTRACT/
SUBCONTRACT
b. CONTRACT/
SUBCONTRACT
a. CWBS
DICTIONARY
b. DD 1921
(CDSR)
c. DD 1921-1
(FCHR)
d. DD 1921-2
(PCR)
e. DD 1921-4
(CSR)
f. SRDR
FORMATS
1.0 MSV(L) - Maneuver Support Vessel (Light) Program X X X X X
1.1 Ship X X X X X
1.1.1 Hull Structure X X X X X
1.1.2 Propulsion Plant X X X X X
1.1.3 Electric Plant X X X X X
1.1.4 Command, Communications and Surveillance X X X X X
1.1.5 Auxiliary Systems X X X X X
1.1.6 Outfit and Furnishings X X X X X
1.1.7 Armament X N/A N/A N/A N/A
1.1.8 Total Ship Integration/Engineering X X X X X
1.1.9 Ship Assembly and Support Services X X X X X
1.2 System Engineering X X
1.3 Program Management X X
1.4 System Test and Evaluation X X
1.5 Training X X
1.6 Data X X
1.7 Peculiar Support Equipment X X
1.8 Common Support Equipment X X
1.9 Operational/Site Activation X N/A
1.10 Industrial Facilities X N/A
1.11 Initial Spares and Repair Parts X X
Subtotal Cost X
Reporting Contractor General & Administrative (G&A) X
Reporting Contractor Undistributed Budget X
Reporting Contractor Management Reserve X
Reporting Contractor Facilities Capital Cost of Money X
Total Cost X
Reporting Contractor Profit/Loss or Fee X
Total Price X
DD FORM 2794, MAY 2011 PREVIOUS EDITION IS OBSOLETE
52DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
CSDR Submission Events
14. CSDR SUBMISSION DATES
a.
SUBMISSION
b.
FORM(S)
c.
EVENT
d. REPORT AS OF DATE e. FINAL REPORT DUE DATE
(YYYYMMDD) (YYYYMMDD)
Milestone B: Engineering & Manufacturing Development (EMD)
001 CWBS, 1921, 1921-1, BOM, SRDR Initial Report: EMD Phase 2017/03/01 2017/05/30
002 CWBS, 1921, 1921-1, BOM, SRDR Final Report: EMD Year 1 2018/03/01 2018/05/30
003 CWBS, 1921, 1921-1, BOM, SRDR Final Report: EMD Year 2 2019/03/01 2019/05/30
004 CWBS, 1921, 1921-1, BOM, SRDR Final Report: EMD Year 3 2020/03/01 2020/05/30
005 CWBS, 1921, 1921-1, BOM, SRDR Final Report: EMD Year 4 2021/03/01 2021/05/30
Milestone C: Production & Deployment (P&D)
Low-Rate Initial Production (LRIP)
006 CWBS, 1921, 1921-1, BOM, SRDR Final Report: Delivery MSV(L) 1 2022/03/01 2022/05/30
007 CWBS, 1921, 1921-1, BOM, SRDR Final Report: Delivery MSV(L) 2 2022/03/01 2022/05/30
008 CWBS, 1921, 1921-1, BOM, SRDR Final Report: Delivery MSV(L) 3 2023/03/01 2023/05/30
009 CWBS, 1921, 1921-1, BOM, SRDR Final Report: Delivery MSV(L) 4 2023/03/01 2023/05/30
Full Rate Production (FRP)
010 CWBS, 1921, 1921-1, 1921-2, BOM, SRDR Final Report: Delivery MSV(L) Lot 1 2024/02/29 2024/05/29
011 CWBS, 1921, 1921-1, 1921-2, BOM, SRDR Final Report: Delivery MSV(L) Lot 2 2025/02/28 2025/05/29
012 CWBS, 1921, 1921-1, 1921-2, BOM, SRDR Final Report: Delivery MSV(L) Lot 3 2026/02/28 2026/05/29
013 CWBS, 1921, 1921-1, 1921-2, BOM, SRDR Final Report: Delivery MSV(L) Lot 4 2027/02/28 2027/05/29
014 CWBS, 1921, 1921-1, 1921-2, BOM, SRDR Final Report: Delivery MSV(L) Lot 5 2028/02/28 2028/05/28
• One submission per calendar year for 10 years starting in 2017 through 2028.
53DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited. Content is Pre-Decisional.
Point of Contact: Erin Bell, (310) 555-9461, ebell@company.com
1 2 3 4 5
1.0 X P-49 Phoenix Fighter
1.1 X Air Vehicle
1.1.1 X Airframe
1.1.2 X Propulsion
1.1.3 X
1.1.4 X
1.1.5 X
1.1.6 X
1.1.7 X
1.1.8 X
1.1.9 X
1.2 X
1.3 X
1.4 X
1.5 X
1.6 X
1.7 X
1.8 X
1.9 X
1.10 X
1.11 X
Program Management
System Test and Evaluation
Training
Data
Initial Spares & Repair Parts
Operational/Site Activation
Industrial Facilities
Peculiar Support Equipment
Common Support Equipment
Systems Engineering
Air Vehicle Software
Air Vehicle Integration, Assembly, Test, and Checkout
Armament/Weapons Delivery
Auxiliary Equipment
Furnishings and Equipment
Vehicle Subsystems
Avionics
Program management includes the contractor's efforts to perform tasks required for planning and control of program schedules, cost and technicla performance including WBS maintenance, work authorizations, budgeting and data reporting. Also included is management and maintenance of the requirements database.
This WBS element is not applicable to this contract.
This WBS element is not applicable to this contract.
This WBS element is not applicable to this contract.
This WBS element is not applicable to this contract.
This WBS element is not applicable to this contract.
This WBS element is not applicable to this contract.
This…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .