This document contains questions and responses regarding Solicitation Number W564KV-23-Q-0020 for Aerial Port of Debarkation (APOD) services in Slatina, Kosovo. The requirement includes cleaning services, pest control, environmental inspections, and building maintenance and inspections for a base period of one year and two one-year option periods from March 15, 2023 to March 14, 2026. A site visit is scheduled for March 13, 2023 at 1400 for offerors to view the buildings. Layout maps and square footage information for each building will be provided after the site visit. The Army Contracting Command will evaluate proposals based on price alone in accordance with FAR 52.212-2. The contractor must provide on-site management and tools/equipment and will be responsible for their own dumpster services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Slatina, Kosovo Aerial Port of Debarkation Questions and Responses
1. Is there a current contractor providing the service?
A: No there is not a current contract in place.
2. If there is a current contractor, can you please let us know what the contract number is for base period and each option period?
A: There is not a current contractor providing g this service for Slatina APOD.
3. In order to have fair evaluation of the scope of the works, can the USG organize a site visit?
A: Site visit scheduled for 13 March 2023 at 1400
4. Can you provide a layout map of all the building included on the SOW?
A: YES, layouts can be provided right after the site visit.
5. Can you provide the SQM for each building included on the SOW?
A: Layouts will have that information on.
6. How will the USG evaluate the technical and price proposal?
A: Technical proposals will be evaluated on lowest price offeror.
7. Does the USD require that we have on-site Management Personnel physically located during the working hours and if yes will the USG provide an office space?
A: YES to both questions.
8. Will you evaluate only Price or Technical Proposal also?
A: We are looking at price only.
9. Do we need to have past performance submitted with the TP and if yes how many?
A: No, please see FAR 52.212-2 for evaluations of offerors.
10. Is this an LPTA contract?
A: Yes.
11. What will the relationship be between NSPA, the US Government and Contractor since NSPA is mentioned on the SOW?
A: Please ignore NSPA this has been removed from SOW.
12. Are there any government furnished equipment or tools that will be provided?
A: Contractor will need to provide their own tools and equipment.
13. What are the size and number of dumpsters on site?
A: There are no dumpsters on site. This has been removed from SOW.