W52P1J20C5003.pdf

PDF 2 MB Posted

Attached to
Repair Roof Building 212
Solicitation number
W52P1J20C5003
Issued by

About this file

This award notice documents a firm fixed price contract awarded to Freeport Industrial Roofing, Inc. for roof repair services. The contract W52P1J20C5003 was competitively awarded on April 29, 2020 by the Department of the Army Materiel Command Joint Munitions Command to Freeport Industrial Roofing, Inc. for $2,369,200. The contract requires repair of an existing low-scope EPDM roof with a new EPDM roofing system on Building 212 at the Rock Island Arsenal in Rock Island, Illinois. All work must be completed within 300 calendar days of notice to proceed in accordance with the scope of work and specifications. The contract incorporates Freeport Industrial Roofing's proposal and prevailing Davis-Bacon wage determinations for the performance period.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICIIAION NO

w52P1 J20R50020001

2. ryFEOF SOLCIATION

! searman (FB)

I Necornrro 1nre,t

3. DATE ISSUED

24-Apr-2020

PAGEOF PAGES

10F 28

IMPORIANT - The "offer" section on the reverse must be fully completed by offeror.

4 CONTMCT NO

w52P1 J20C5003

5. REQUISfl ON/PURCHASE REQUEST NO

001 14434140001

6. FROJECT NO.

201 8-2936

7. ISSUED BY CODE I W52P1J

ARIVY CONTRACTING COIVMAND - ROCK ISLAND

3055 RODMAN AVENUE

ROCK ISLAND lL 61299-8000

TEL: FAX:

8. ADDRESS OFFER TO (tf Other Than ltem 4 CODE I

See ltem 7

FAX:

9. FOR INFORMATION

CALL:

A. NAIVE

JOHN D KERCH

B. TB-EFHONENO. (lnclude area code) (NO COLLECT CALLS)

309-782-5830

SOLICITATION

NOTE: ln sealed bid soticitations "offer" and "offeror" mean "bid" and "bidder".

'10. THE GOVERNMENT REQUIRES FERFORMANCE OF THEWORK DESCRIBED lN THESE DOCUMENTS (Title, identifying no., date):

Repair Roof BLDG212

Hease see Becutive Sunrary

The United States Army Contracting Conrnand - Rock lsland (ACGRI) Contracting Center requests a proposal to repair an existing low-scope EPDM roof w ith a new EPDM roof ing system on Building (BLDG) 212.

This Request for froposal (RFfl is issued as a total '100% Snrall Business Set Aside.

This RFP contains a base bid and four (4) bid options. Contractors subnitting proposals MUST price the base bid and all bid options in their proposal.

All w ork is to be conpleted in accordance w ith (lA\ttQ the Scope of Work (SOW, attached specif ications, and plans. See DFARS 252.236-7001.

tAW FAR 36.204, Dsclosure of the nragnitude of construction projects, the total estineted nngnitude of construction is betw een $1 ,000,000 and $5,000,000.

Contractor Questions are due February 20, 2020 at 1 PM CST.

A fte-Construction site visit is scheduled f or 0900 (9:00 AIVI) Central llne (CT) on Tuesday, February 11, 2020 in the fublic Works Conference Room, Basenent of Building 102, Rock lsland Arsenal. Wrile attendance is not mandatory although encouraged, to subnit a proposal, if attending, reservations are required. Seethe *ecutive Sunrnary for reservation instructions.

1 1 . The Contractor shall begin perf ornence w ithin 14 calendar days and conplete it w ithin

! awarO, I notice to proceed. This perfornunce period is I nnndatory, ! negotiable.

calendar days after receiving

(See _

12 A. THE CONTMCTOR MUST FURNISH ANY REQUIRED FMFORMANCE AND PAYMENT BONDS?

(lf "YES," indicate within how many calendar days after award in ltem 128.)

fivrs ! No

128. CALENDAR DAYS

1 3. ADDTIIOML SOLICTTATION REQUIREMENTS:

A. Sealed off ers in original and copies to perf orm the w ork required are due at the place specif ied in ltem 8 by 09:00 AM fiour) local tinE 03 Mar 2020 (date) lf this is a sealed bid solicitation, offers mrst be publicly opened at that tirne. Seated envelopes containing offers shall be nurked to show the offeror's nane and address, the solicitation nunber, and the date and tine offers are due.

B. An offer guarantee E a, n is not required.

C. All offersaresubjecttothe(1)workrequirenents,and(2)otherprovisionsandclausesincorporatedinthesolicitationinfull textorbyreference.

D. Offersprovidinglessthan 60 calendardaysforGovernnentacceptanceafterthedateoffersareduewill notbeconsideredandwill berejected.

STANDARD FORM 1442 (REV 4-85)

Pr6cribed byGSA

FAR (48 CFR) 53 23G1(e)

NSN 7540-01-155-3212

TEL:

SOLICITATION, OFFER, AND AWARD (Continued) (Con stru ctio n, Alte ration, or Re pai r)

OFFER (M ust be fully completed by offeror) '14. MMEAND ADDRESS OF OFFEROR (lnctude ZtP Code)

FREEPORT INDUSTRIAL ROOFING, INC.

PAUL HOEFER

3507 IL RTE 26 S

FREEPORT IL 61032-9374

1 5. TELEFHONE NO. (lnclude area code)

16. REMITANCEADDRESS (lnclude onlyif differentthan ltem 14)

See Item 14

CODE

00D7'1

FACLTY CODE

'17. The off eror agrees to perf orm the w ork required at the prices specif ied below in strict accordance w ith the terns of this solicitation, if this of f er is acceptedbytheGovernnentinwritingwithin_ calendardaysafterthedateoffersaredue. (lnseftanynumberequal toorgreaterthan the minimum requirements stated in ltem 13D Failure to inseft any number means the offeror accepts the minimum in ltem 13D )

I

I

AMOUNTS I SU SCHOULE OF FRTCES

18. The offeror agrees to furnish any required perfornunce and paynent bonds.

1 9. ACKNO\A/-EDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of arendrenls to the solicitation -- give nunber and date of each)

AMENDIVENT NO.

DATE

2OA MMEAND TITLE OF FERSON AUTHORZED TO SIGN

OFFER (Type or print) 2OB. SGMruRE 2OC. OFFER DATE

AWARD (To be completed by Government)

21. IIEII/IS ACCEPIED:

SEE SCHEDULE

22. AI\4OUNT

$2,369,200.00

23. ACCOUNTING AND AFFROPRIATION DATA

See Schedule

24. SUBMII- IIWOICES TO ADDRESS SHO!\4! IN

(4 copies unless olherulse specified)

ITEM 25. OTHER TFIAN FULL AND OPEN COMPETITION RJRSUANT TO

!ro u.s c. 2304(c) !+r u s c 253(c)

26. ADMINISTERED BY CODE

See Item 7

27. PAYMENTWLL BEMADEBY: coDE I uoo+go

DEFENSE FINANCE AND ACCOUNTING SERVICE

DFAgINDY VP GFEBS

8899 E 56TH STREET

INDIANAPOUS lN 462493800

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

l-l ze. neoortATED AGREEIVENT (contractor is required to sisn this L__t docurent and return _ copies to issuing office ) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration stated in this contract The rights and obligations ot the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by refer-ence in or attached to this contract

J X I ZS. nWnnO (contractor is not rcquircd to sign this docunEnt )LI Your off er on this solicitation, is hereby accepted as to the items listed. This aMrd con-summates the contract, lvtlich consists of (a) the Government solicitation and y our offer, and (b) this contract award No further contractual document is necessary

REF: W52P1J20R5002

3OA. MME AND TILE OF CONTMCTOR OR FERSON AUTHORZED

TO SIGN lype or print) Paul G. Hoefer, President

31A. NAME OE CONTRACTING OEFICER (TWe or prjnt)

IEL: El,lAIL:

a;, 3OC DATE

04t24/2020

31 B. UNITED STATES OF AMERICA I 31C. AWARD DATE

BYI

NSN 7540-01- 1 55-3212 STANDARDFORM 1442 BACK (REV.4-85)

Molly J Lewis molly.j.lewis4.civ@mail.mil 309-782-1837 w52P tJ20C5003

Page 3 of28

Section SF 30 - Block l4 Continuation Page (SF 30)

AWARD NARRATIVE

AWARD NARRATIVE

1. This Firm Fixed Price contract W52P1J-20-C-5003 is issued to Freeport lndustrial Roofing, lnc. in support of repair an existing low-scope EPDM roof with a new EPDM roofing system on Building (BLDG) 212 on the Rock lsland Arsenal, Rock lsland, lL. This work will be done in accordance with the Scope of Work (SOW) and Attachments included with the solicitation and this resulting contract.

2. A Notice to Proceed will be provided at the pre-construction conference to be scheduled at a later date. Work is not to begin until the Notice to Proceed has been issued. The period of performance will begin upon receipt of the Notice to Proceed (NTP) and the project to include the base plus all bld options must be completed within 300 calendar days from the NTP.

3. A certification of insurance, as set forth in the contract, is required before work commences.

4. Please display all hot line posters at your work site per the safety requirement.

5. Freeport lndustrialRoofing, lnc.'s proposaldated 23 March 2O2Ois hereby incorporated intothis contract.

6. The prevailing Davis Bacon Wage determination is incorporated and will be in effect the entire performance period. The most recent wage determination is provided as Attachment 004.

7. All other terms and conditions of solicitation W52P1J-20-R-5002 and all of its amendments, attachments, and discussions are hereby incorporated into this contract.

lr

Page 4 of28

Section 00 l0 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

$667.000.00000 I I Job $667,000.00

Repair Existing Roofing

FFP

Base Bid roofing repair IAW Scope of Work for PR 2018-293 FOB: Destination

PURCHASE REQUEST NUMBER: 001 1443416-0001

PSC CD: Z2AZ

NET AMT $667,000.00

$667,000.00ACRN AA

CIN: GFEBS00 I I 4434160000 |

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job $510,900.00 $510,900.00 EXERCISED Repair Existiug RoofingoPrroN FFi'

Bid Option l roofing repair IAW Scope of Wotk for PR 2018-293 FOB: Destination

PURCHASE REQUEST NUMBER: 001 1443416-0001

PSCCD: Z2AZ

NET AMT $s 10,900.00

$51 0,900.00ACRN AA

CIN: GFEBS001 1 44341600002

tr w52P 1J20C5003

Page 5 of28

ITEM NO

lrXlr,RClSEI)

OI'TION

SUPPLIES/SERVICES QUANTITY UNIT

1 Job

Repair Existing Roofing

FFP

Bid Option 2 r'oofing repair IAW Scope of Wolk tbr PR 2018-293 FOB:Destination

PURCHASE REQUEST NUMBER: 00 I 1443416-0001

PSC CD: Z2AZ

UNIT PRICE

$437, r 50.00

NET AMT

UNIT PRICE

$324.300.00

NET AMT

AMOUNT

$437. r s0.00

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT

0004 I Job EX_ERCISED Repair Existing Roofi rrgoPrToN FFi'

ACRN AA

CIN: GFEBS00 I 144341600003

Bid Option 3 r'oofing repair IAW Scope of Worl< for PR 2018-293 FOB: Destination

PURCHASE REQUEST NUMBER: 00 I 1443416-0001

PSC CD: Z2AZ

$437, r 50.00

$437,r s0.00

AMOUNT

$324.300.00

$324,300.00

$324,300.00ACRN AA

CIN: GFEBS00I I 4434 I 600004

Page 6 of28

ITEM NO SUPPLIES/SERVICES QUANTITY LINIT UNIT PRICE AMOUNT

000s I Job $429,850.00 $429,850.00 EXERCISED Repair Existing RoofingoPrroN FFi'

Bid Option 4 loofing repair IAW Scope of Worh fbr PR 2018-293 FOB: Destination

PURCHASE REQUEST NUMBER: 001 1443416-0001

PSC CD: Z2AZ

NET AMT $429,850.00

$429,850.00ACRN AA

CIN : CFEBS00l 1 44341600005

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 PoP l5-MAY-2020 TO N/A GARRISON - ROCK TSLAND ARSENAL W9l QFD II-MAR-2o2I ERIC BUTZ

IMRI-PW

BLDG I02, ISTFLOOR

I ROCK ISLAND ARSENAL

ROCK ISLAND IL 61299

309-782-2365 FOB: Destination

OOO2 POP I5-MAY-2OZOTO N/A (SAME AS PREVIOUS LOCATION) WgIQFD I I-MAR-2021 FOB: Destination

OOO3 POP I5-MAY-2O2OTO N/A (SAME AS PREVIOUS LOCATION) WgIQFD I I-MAR-2021 FOB: Destination

OOO4 POP I5-MAY-2O2OTO N/A (SAME AS PREVIOUS LOCATION) WgIQFD 1I-MAR-2021 FOB: Destination

OOO5 POP 15.MAY-2O2OTO N/A (SAME AS PREVIOUS LOCATION) WgIQFD I 1-MAR-2021 FOB: Destination

ACCOLINTING AND APPROPRIA TION DATA

w52P rJ20C5003

Page 7 of28

44.02120202t)2020200000il3t32254 i\I0092735 l 6 I 00 900002 l 00 I

COST CODE: A60SG

AMOUNT: $2,369,200 00

ACRN CLIN/SLIN

AA 000r

CTN

GFEBS00rr4434r600001 GFEBS0Ol 144341600002 GFEBS00t I44341600003

GFEBS00I 144341600004

GFEBS00I I4434I 600005

AMOUNT

$667,000 00

$5 I 0,900 00

$437. l 50 00

$324,300 00 $429,850 00

CLAUSES INCORPORATED BY REFERENCE

Systenr fbr Award Managenrent Maintenance Perfornrance and Paynrent Borrds--Constluction A nti ten'oli snr Awareness Trai n i ng for Cotrtractors.

52.204-t3 52.228-15 252.204-7004 ocT20r8 ocT 20 r0

FEB 20I9

CLAUSES INCORPORATED BY FULL TEXT

52.228-t BrD GUARANTEE (SEP t996)

(a) Failure to furnish a bid guarantee in the proper forrn and anrount, by the tinre set for opening of bids, rray be cause for rejection ofthe bid.

(b) The bidder shall furnish a bid guarantee in the fonn of a firm comrritrnent, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Governnrent, postal rnoney order, certified check, cashier's check, irrevocable letter of credit, or, nnder Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (l ) to unsuccessful bidders as soon as placticable afterthe opening ofbids, and (2) to the successful bidder upon execution ofcontractual documents and bonds (including any necessary coinsuratrce or reirrsurance agreerrents), as required by the bid as accepted.-

(c) The arnoullt of the bid guarautee shall be 20 percent of the bid price or 3 rnillion whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Governrnent within the period specified for acceptance, fails to execute all contractual documents or furn ish executed bond(s) with in I 0 days after receipt of the forlns by the bidder, the Contracting Officer rray ternrinate the contract for default.-

(e) In the event the contract is terminated for default, tlre bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the diff'erence.

(End of provision)

52.232-t8 AVAILABILITy OF FUNDS (ApR t984)

Fnnds are not presently available forthis contract. The Covernnrent's obligation underthis coutract is contingent upon the availability of appropriated funds frorr which payrnent fol contract purposes can be nrade. No legal liability on the part of the Govel'urrtent for any payrllent nray arise Lrntil tunds are rnade available to the Contracting Officel fol this cotttract and until the Contractor receives notice of such availability, to be corrfirnred in writing by

Page 8 of28 the Contracting Officer.

(End ofclause)

Page 9 of28

Section 00 45 00 - Replesentations and Certifications

CLAUSES INCORPORATED BY REFERENCE

52.204-19 Incorporation by Refererrce of Representations and DEC 20 l4 Certifications.

252.209-7004 Subcontlacting With Firms That Are Owned or Controlled By MAY 20 I 9 The Government of a Country that is a State Sponsor of Terrorism

Section 00 70 00 - Conditions of the Contlact

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

INSPECT BY

N/A N/A N/A N/A N/A

ACCEPT AT

N/A N/A N/A N/A N/A w52P rJ20C5003

Page l0 of28

ACCEPT BY

Governrnent Covernnrent Goverrrnent Government Goverrrrnent

CLIN INSPECT AT

0001 N/A 0002 N/A 0003 N/A 0004 N/A 0005 N/A

CLAUSES INCORPORATED BY REFERENCE

Defi nitions Gl'atuities Covenarrt Against Contingent Fees Restrictions On Subcontlactor Sales To The Government Anti-Kickback Procedures Cancellation, Rescission, and Recovery ofFunds for Illegal Improper Activity Price Or Fee Adjustment For Illegal Or Improper Activity Limitation On Payments To Influence Certain Federal Transactions Security Requirements (Aug 1996) - Alternate II Printed or Copied Double-Sided on Postconsunrer Fiber Content Paper Personal Identity Verification of Contractor Personnel Reporting Executive Cornpensation and First-Tier Subcontract Awards System for Award Management Maintenance Protecting the Governrnent's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debalment Prohibition on Contracting With Inverted Domestic Colporations Audit and Records--Negotiati on Notice of Total Srnall Business Set-Aside (DEVIATION 20 r 9-00003).

Utilization of Snrall Business Concellts Lirnitations on Subcontracting (DEVIATION 20 l9-00003).

Convict Labor Contract Work Hours and Safety Standards - Overtime Conrpensation Construction Wage Rate Requirements Withholding of Funds Payrolls and Basic Records Apprentices and Trainees

52.202-l 52.203-3 52.203-5 52.203-6 52.203-7 52.203-8

52.203-10 52.203-12

52.204-2 AltII 52.204-4

52.204-9 52.204-10

52.204-13 52.209-6

52.209-10

52.215-2 52.219-6 (Dev)

52.219-8 52.219-14 (Dev) 52.222-3 52.222-4

52.222-6 52.222-7 52.222-8 \) )))-q

NOV 201 3

APR I984

MAY 2014

SEP 2OO6

MAY 2014

orMAY 2014

MAY 20I4

ocT 2010

APR I984

MAY 2OII

JAN 201 I

ocT 201 8 ocT 20r 8 ocT 2015

NOV 2015

ocT20l0

JAN 20I9

ocT 20 r8

JAN 2OI9

JUN 2OO3

MAY 20I8

AUG 20I 8

MAY 20I4

AUG 20I8

JUL 2OO5

Page I I of28

52.222-t0 52.222-l 52.222-t2 52.222-13

52.222-14 52.222-15 52.222-21 52.222-26 52.222-27

52.222-35 52.222-36 52.222-37 52.222-40

52.222-50 52.222-s4 52.222-62 52.223-5 52.223-6 52.223-l

52.223-ts 52.223-17

52.223-18

52.225-13 52.227-l 52.227-2

52.227-4 52.228-2 52.228-11 52.228-t2 52.228-14 52.228-15 52.229-3 52.232-5 52.232-17 52.232-23 52.232-27 52.232-33

52.232-40

52.233-l 52.233-3 52.233-4 52.236-2 52.236-3 52.236-4 52.236-5 52.236-6

Conrpliance with Copeland Act Requilenrents Subcontracts (Labor Starrdards)

Contract Ternr i nati on-Debanrent Conrpliance With Constructiorr Wage Rate Requirerlents and Related Regulations Disputes Concernilrg Labor Standalds Celtifi cation of El igi bi I ity Prohibition Of Segregated Facilities Equal OpportLrnity A ffi rrnative Action Conr p I iance Requ i rernents for Construction E,qual OpportLrnify for Veterans Equal OpportLrnity fbr Wolkels with Disabilities E nrployrnent Repolts orr Vetel'ans Notification of Ernployee Rights Under the National Labor Relatiorrs Act Conrbating Trafficking irr Persons E,nrployrnent El igibi I ity Verifi cation Paid Sick Leave Under E,xecutive Order 13706 Pollution Prevention and Right-to-Know Inforrnatiorr Dlug-Free Woll<place Ozone-Depleting Substances and High Clobal Warrnilrg Potential Hydlofl uorocarbons.

E,nergy Effi c iency i rr Energy-Corrsuur i ng P roducts

FEB I988

MAY 2OI4

MAY 20 I4

MAY 20I4

FEB I 988

MAY 20I4

APR 20I5

SEP 20I6

APR 20I5

ocT 20r5 tuL20l4

FEB 20I6

DEC 20IO

JAN 20I9

ocT 201 5

JAN 20I7

MAY20II

MAY 2OOI

JUN 20I6

DEC2OOT

AUG 2OI I

JUN 2OO8

DEC2OOT

DE,C 2OO7

DEC 2OO7

ocT 1997

AUG 20I 8

MAY 20 I4

NOV 20r4 ocT 201 0

FEB 20I3

MAY 2OI4

MAY 20I4

MAY 20I4

JAN 20I 7

ocT 2018

DEC 20I3

MAY 20I4

AUG I996

ocT 2004

APR I984

APR I984

APR I984

APR I984

APR I984

Affirrnative Procurernent of EPA-Designated Iterls in ServiceAUG 2018 and Construction Contracts Encoulaging Contractor Policies To Ban Text Messaging While Driving Restrictious on Celtain Foreign Purchases Authorization and Consent Notice And Assistance Regarding Patent And Copyright Infringernent Patent Indemtr ity-Collstruction Contracts Additional Bond Security Pledges Of Assets Prospective Subcontractor Requests for Bonds L'revocable Letter of Credit

Pelformance and Payment Bonds--Constlucti on Federal. State And Local Taxes Payrnents under Fixed-Price Construction Contracts I nterest Assignrnent Of Claims Pronrpt Payrnent for Construction Contracts Paytrent by Electronic Fnnds Transfer--System for Award Managenrent Providing Accelerated Payments to Srnall Business Subcontractors Disputes Protest After Award Applicable Law for Breach of Contract Claim Differing Site Conditions Site Investigation and Conditions Affecting the Work Physical Data Matelial and Wolkrnanship Superintendence by the Contractor

52.236-7 52.236-8 52.236-9

52.236-10 52.236-il 52.236-12 52.236-t3 52.236-t4 52.236-15 52.236-16 52.236-17 52.236-26 52.242-5 52.242-13 52.242-14 52.243-4 52.244-6 52.246-12 52.246-21 52.248-3 52.249-2 AltI

52.249-10 52.253-l 252.201-7000 252.203-7000

252.203-7001

252.203-7002 252.203-7004 252.204-7003 252.204-7012

252.223-7006

252.225-7001 252.225-7012 252.225-7048 252.232-7003

252.232-7010 252.236-7000 2s2.236-7008 252.243-7001 252.247-7023

NOV l99 t

APR I984

APR I984

APR I984

APR I984

APR I984

NOV t99 t

APR I984

APR I984

APR I984

APR I984

FEB I995

JAN 20I7

JUL I995

APR I 984

JUN 2OO7

AUG 20I9

AUG I996

MAR I994

ocT 20r5

SEP I 996

APR I 984

JAN I99I

DEC I99I

SEP 2OI I

Permits and Responsibilities Other Contracts Protection of Existing Vegetation, Structures, Equiprnent, Uti I ities, and Improventents Operations and Storage Areas Use and Possession Prior to Completion Cleaning Up Accident Prevention Availability and Use of Utility Selvices Schedules for Construction Contracts

Quantity Surveys Layout of Work Preconstluction Conference Payrnents to Small Busirress Subcontractols Bankruptcy Suspension of Work Changes Subcontracts for Commercial Iterns Inspection of Construction Warranty of Construction Value Engi neeling-Cotrstruction Termination for Convenience of the Government (Fixed- Price) (Apr 2012) - Alternate I Default (Fixed-Price Constluction) Conrputer Generated Fornrs Contracting Offi cer's Representative Requirernents Relating to Contpensation of Fornrer DoD Officials Prohibition On Pelsons Convicted of FraLrd or Other Defense- DEC 2008 Contract-Related Felonies Reqnilernent to Inforrl Enrployees of Whistleblowel' Rights Display of Hotline Posters Control Of Govenlnerrt Pelsonnel Worl< Prodtrct Safeguarding Covered Defense Tnfonnatiolr and Cyber Incident Repolting Prohibition On Stolage, Treatrreut, and Disposal of Toxic or Hazardous Materials Bny Anrelican Aud Balance Of Payments Progrant-- Basic Preference For Cet'tain Dotnestic Contntodities E,xport-Contlol led Itenrs E,lectronic Subnrissiorr of Payrnent Requests and Receiving Repofts Levies on Contract Payments Modifi cation Proposals-Price Breal<down Contract Prices-B idding Schedules Pricing Of Contract Modifications Transpoltatiorr of Supplies by Sea

SEP 2OI3

AUG 20I9

APR I992

ocT 201 6

SEP20I4

DF,C 2017

DEC,2017

JUN 20 I3

DEC20I8

DEC 2006

DEC I99I

DEC I99I

DEC I99I

FEB 20I9

CLAUSES INCORPORATED BY FULL TEXT

52.211-IO COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR I984)

The Colrtractor shall be required to (a) conrmence work under this contract within 180 calendar days after the date

Page l3 of28 the Contlactor receives the notice to ploceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than I 80 days after the notice to proceed. The time stated for contpletion shall include final cleanup of the prernises. Additional time will be given for option CLINs and will be reflected on the Notice To Ptoceed provided at the pre-construciton conference.

(End ofclause)

52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATTON (JULY 2013)

(a) Definitions. As used in this clause--

Long-term contt'act lueans a contract of more than five years in dulation, including options. However, the ternr does not include cotttracts that exceed five yeals in duration because the period ofperformance has been extended for a cutrrulative period not to exceed six nrorrths under the clause at 52.217-8, Option to Extend Services, or other appropliate authority.

Snrall business concenr mearls a concenl, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Governrnent contracts, and qualified as a small business under the criteria in I 3 CFR part l2l and the size standard in paragraph (c) ofthis clause. Such a concenl is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a nunrbel of business coucerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volurne of business, nurnber of ernployees, financial resources, conrpetitive status or position, ownership or corrtrol of rnaterials, processes, patents, license agreeluents, facilities, sales territory, and nature ofbusiness activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contl'act, the Contractor shall rerepresent its size status according to paragraph (e) ofthis clause or, ifapplicable, paragraph (g) oftlris clause, upon the occun'ence of any of the following:

(l) Within 30 days after execution of a novation agreementor within 30 days after modification ofthe contractto include this clause, ifthe novation agreenrerlt was executed prior to inclusion ofthis clause in the contract.

(2) Within 30 days after a tnerger or acquisition that does not require a novation ol withiu 30 days after rnodification ofthe contlact to include this clause, ifthe merger or acquisition occurred prior to inclusion ofthis clause in the contract.

(3) For long-ternr contracts--

(i) Within 60 to 120 days plior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified iu the contractforexercising any option thereafter.

(c) The Contractor shall ret'epresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this cotrtract. The snrall business size standard corresponding to this NAICS code can be found at http ://www. sba.gov/content/tab le-srnal I -busi ness-si ze-standards.

(d) The small business size standard fol a Contractol providing a product which it does not rnanufactule itselll for a contract other than a construction or service cotltract, is 500 entployees.

(e) Except as provided in paragraph (g) ofthis clause, the Contractor shall nrake the representation required by paragraph (b) ofthis clause by validating or updating all its representations in the Representations and Certifications

Page l4 of28 section of the Systern for Award Managernent (SAM) and its other data in SAM, as necessaly, to ensure that they reflect the Contractor's cul'rellt status. The Contractot'shall notif, the conttacting office in writing within the tilrefi'arnes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date ofthe validation or update.

(f) If the Contractor represented that itwas otherthan asnrall business concel'n priorto award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) ofthis clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a r.epresentation in SAM for the NAICS code applicable to this contract, the Contractol is required to complete the following t'erepresentation and submit it to the contracting office, along with the contract nurnbel and the date on which the rerepresentation was completed ;

TheContlactorrepresentsthatit( )is,( )isnotasnrall businessconcel'nunderNAICSCode238l60-Roofing Contractors assigned to solicitation number W52P I J20R5002.

(Contractor to sign and date and insert autholized signer's name and title).

(End ofclause)

52.225-9 BUy AMERTCAN-CONSTRUCTTON MATERTALS (MAy 2014)

(a) Definitions. As used in this clause--

Commercially avai lable off-the-shelf (COTS) item-

(l) Means any itern of supply (including construction rnaterial) that is--

(i) A commercial item (as defined in paragraph ( I ) of the definition at FAR 2.10 | );

(ii) Sold in substantial quantities in the commer.cial marketplace; and

(iii) Offered to the Governrnent, under a contract or subcontract at any tier, without modification, in the sarne form in which it is sold in the comlnercial nrarketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.

Component lreans an alticle, material, or supply incolpolated directly into a construction material.

Construction tnaterial lneans an article, rnaterial, or supply bloughtto the construction site by the Contr.actor or a subcontractor for incot'poration into the building or work. The term also includes an item brought to the site

Page l5 of28 pleassembled frorn alticles, materials, or supplies. However', emergency life safety systerns, such as emer.gency lighting, fire alartn, and audio evacuation systems, that ale discrete systems incorporated into a public building or work and that are produced as complete systerns, are evaluated as a single and distinct construction rnaterial regardless of when or how the individual parts or components of those systetl.ls are delivered to the construction site.

Materials purchased directly by the Government are supplies, not construction material.

Cost of components means--

( I ) For components purchased by the Contractor', the acquisition cost, including transpoltation costs to the place of incorporation into the constl'uctiott material (whether or not such costs are paid to a domestic firm), and any applicable duty (whethet or not a duty-flee entry certificate is issued); or

(2) For components manufactured by the Contlactor', all costs associated with the manufactute of the component, including tratrsportation costs as described in paragraph (l ) ofthis definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the nranufacture of the construction material.

Domestic construction rnaterial meatls--

(l) An unmanufactured construction material rnined ol produced in the United States;

(2) A construction lnatelial manufactured irr the United States, if--

(i) The cost of its cotnponents mined, produced, or rnanufactured in the United States exceeds 50 percent ofthe cost of all its components. Components of foreign origin of the sarne class or kind for which nonavailability deterrninations have been made are treated as domestic; o

(ii) The construction material is a COTS item.

Foreign construction Inaterial rneans a construction material other than a dornestic construction material.

United States means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(l)Thisclauseirnplements4l U.S.C.chapter83,BuyAmerican,byptovidingapreferencefordomestic construction material. In accordance with 4l U.S.C. I 907,the cotnponent test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction nratelial in perfolnring this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a comlnercial itern or to the construction nraterials or compouents listed by the Government as follows:

(3) The Contracting Officer may add other foreign construction rnaterial to the list in paragraph (b)(2) of this clause if the Government deterrnines that

(i) The cost of domestic constluction rnaterial would be unreasonable. The cost of a particulat domestic construction rnaterial subject to the requirements of the Buy American Act is unreasolrable when the cost of such material exceeds the cost offoreign lraterial by nrole than 6 percent;

(ii) The application of the restliction of the Buy American Actto a particulal construction rnaterial would be inrplacticable or inconsistent with the public interest; ot

Page l6 of28

(iii) The construction lnatet'ial is not rrined, produced, or manufactuled in the United States in sr-rfficient and reasonably available comlnercial quantities of a satisfactory qualify.

(c) Request for determination of inapplicability of the Buy American Act. (l)(i) Any Contractor requestto use foreign construction material in accordance with paragraph (bX3) of this clause shall include adequate infotmation for Governrnent evaluation of the request, including--

(A) A description of the foreign and domestic construction ntaterials;

(B) Unit of measure;

(C) Quanti8;

(D) Price;

(E) Time of delivery or availability;

(F) Location ofthe construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) ofthis clause.

(ii) A request based on unreasonable cost shall include a reasorrable sulvey ofthe rnarket and a conrpleted price cornparison table in the format in paragraph (d) of this clause.

(iii) The price ofconstruction material shall include all delivery costs to the construction site and any applicable duty (wlrether or not a duty-free certificate rnay be issued).

(iv) Any Cotrtractor request for a determination subrnitted aftel contract award shall explain why the Contractor could not reasonably fot'esee the need for such detelmination and could not have requested tlre determination before contract award. If the Contractor does not subrrit a satisfactory explanation, the Contracting Officer need not make a determ ination.

(2) If the Government determines after contract award that an exception to the Buy Arnerican statute applies and the Contracting Officer and the Contractor negotiate adequate considelation, the Contracting Officer will modif, the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price ofa domestic construction nraterial, adequate consideration is not less than the differential established in paragraph (bX3)(i) ofthis clause.

(3) Unless the Government deterrnines that an exception to the Buy Anretican statute applies, use of foreign construction material is noncornpliant with the Buy Alrericalr statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on urrreasonable cost, the Contractor shall include the following infotmation and any applicable supporting data based on the survey of suppl iers:

Foleign and Donrestic Cotrstructiorr Materials Plice Colnparison

Constructiorr nratelial description Unit of tleasure

Item I

Foleign constluction materi al Domestic construction material

Quantity Price (dollars) \l\

Page l7 of28

Iten 2 Foreign coustruction material Domestic construction rnaterial

Include all delivery costs to the constluction site and any applicable duty (whether ol'not a duty-fi'ee entry certificate is issued).

List name, addtess, telephone number, and contact for suppliers surveyed. Attach copy ofresponse; iforal, attach summary.

lnclude other appl icable supporting i nformation.

(End ofclause) s2.228-5 TNSURANCE--WORK ON A GOVERNMENT TNSTALLATTON (JAN 1997)

(a) The Contractor shall, at its owrt expense, provide and maintain during the entil'e performance of this contract, at least the kinds and trinirnum amoullts of iusurance required in the Schedule or elsewhere in the contract.

(b) Before cotnmettciug work uuder this contract, the Contractot shall noti|l the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required irrsurauce shall contain au endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (l) for such period as the laws of the State in which this contract is to be pel'fol'med prescribe, or (2) until 30 days after the insurer or the Contlactor gives written notice to the Contracting Officer, whichever period is longer.

(c) The Contractor shall insert the substance ofthis clause, including this paragraph (c), in subcontracts under this contractthat require work on a Government installation and shall require subcontractors to provide and maintain the itrsurance required in the Schedule ol elsewhere in the colltract. The Contractor shall rnaintain a copy of all subcontractors' proofs ofrequired insurance, and shall rnake copies available to the Contracting Officer upon request.

(End ofclause)

52.236-1 PERFORMANCE OF WORK By THE CONTRACTOR (ApR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at Ieast not less than ]f percenl!-ofthe total amount ofwork to be perfornred under the contract. This percentage nlay be reduced by a supplemental agreement to this contract if, during perfonning the wolk, the Contlactot requests a reduction and the Contracting Officer detel'nriues that the reduction would be to the advantage of the Government.

(End ofclause)

52.236-2I SPECTFICATIONS AND DRAW]NCS FOR CONSTRUCIION (FEB I997)

(a) The Contl'actor shall l<eep on the worl< site a copy of the drawings and specifications and shall at alltirnes give the Contractirrg Officer access thereto. Anything rrrentioned in the specificatiorrs and not shorvn on the drawings, or shown on the drawings atrd not trrentioned in the specifications, shall be of lil<e efTect as if shown or tnentioned in both. In case ofdifferettce betrveen drawings and specifications, the specifications shall govern. Tn case of disc|epancy in the figures, in the drawings, ol in the specifications, the rlatter shall be prorlptly subnritted to the Contracting Officer', who shall prontptly nrake a detelnrination in writing. Any adjustnrent by the Corrtractor without sttch a detertrlination shall be at its own risk arrd expense. The Contracting Ofticer shall furnislr fi.oll titne to tinre sLrch detailed dlawirrgs atrd other inforrrration as considered necessary, unless othelwise provided.

ws2P 1J20c5003

Page lE of28

(b) Wherever in the specifications or upon the drawings the words "directed", "required", "ordered", "designated", "presct'ibed", or words of like import are used, it shall be understood that the "direction", "requirement", "order", "designation", or "prescription", of the Contracting Officer is itrtended and similarly the words "approved", "acceptable", "satisfactoty", ot'words of like import shall mean "approved by," or "acceptable to", or "satisfactory to" the Contracting Officer, unless otherwise expressly stated.

(c) Where "as shown," as indicated", "as detailed", ol words of similar inrport are used, it slrall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "ptovided" as used herein shall be understood to mean "provide conrplete in place," that is "furnished and installed".

(d) Shop drawirrgs t.tteatrs drawings, submitted to the Governnrent by the Contractor, subcontractol', or any lower tier subcontractor pul'suant to a constl'uction contlact, showing in detail ( l ) the pLoposed fabrication and assembly of stt'uctural elenrettts, and (2) the installatiorr (i.e., fit, and attachnrerrt details) of ntaterials or equipment. It includes dlawings, diaglams, layouts, schematics, descliptive literatule, illustlations, schedules, performance and test data, and sirnilar materials furnished by the contractor to explain in detail specific portions of the work required by the colttract. The Governnrent may duplicate, use, arrd disclose in any manner and fol alty purpose shop drawings delivered under this colttract.

(e) If this contract t'equires shop drawings, the Contractor shall coordinate all such drawings, and review thern for accuracy, completeness, and compliance with corltract requirenrents and shall indicate its approval tlrereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contlactor's approval may be returned for resubnrission. The Contracting Officer will indicate an approval or disapproval ofthe shop drawings and if not apploved as submitted shall indicate the Goverrrrneut's reasorrs therefor.

Any work done before such approval shall be at the Conttactor's risk. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from lesponsibility for complying with the requiretlents of this contract, except with respect to variations described and approved in accordance with (f) below.

(f) Ifshop drawings show variations from the contract requirernents, the Contractor shall describe such variations in writing, separate fronr the drawings, atthe time of subnrission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, ifthe variation is ttrinor or does not involve a change in price or in tirne of perforntance, a rnodification need not be issued.

(g) The Contt'actor shall suburit to the Contracting Officer for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings ofthese specifications. Three sets (unless otherwise indicated) of all shop drawings, will be retained by the Contracting Officer and one set will be returned to the Contractor.

(End ofclause)

52.252-2 CLAUSES TNCORPORATED By REFERENCE (FEB 1998)

This contract incorporates one or more clauses by leference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

hups://www.acqui sition. gov

Page I 9 of28

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 20t8)

(a) Definitions. As used in this clause-

"Depal'tment of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organ ization.

"Document type" ltteaus the lype of payrrent request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment celtification when payment certification is done external to the entitlement system.

"Paymetrt request" and "receiving report" are defined in the clause at252.232-7003, Electronic Submission of Paynrent Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electlonically process vendor paynrent requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payntent Requests and Receiving Reports.

(c) WAWF access. To access WAWF. the Contractor shall-

(l) Have a designated electronic busirtess point of contact in the Systenr for Award Managenrent at https://www.sarn.gov; and I

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payrnent requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF nrethods of docuntent submission. Docunrent subnrissions nray be via web entry, Electronic Data Interchange, ol File Transfer Protocol.

(0 WAWF payment instructions. The Contractor shall use the following information when sublnitting payment requests and receiving reports in wAWF for this contract or task or delivery order:

( I) Document type. The Contractor shall submit paynlent requests using the following docunrent type(s):

(i) For cost-type line items, including labor-houl or tinre-and-materials, subnrit a cost voucher.

(ii) For fixed price line itenrs-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer': Insert applicable invoice and leceiving report docunrent type(s) for'fixed price line itelns that require shipment of a deliverable.)

Page 20 of28

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in l, which rneets the requirenrents for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contlacting Officer'.

(Contracting Officer: Insett either "lnvoice 2in l" or the applicable invoice and receiving report document type(s) for fixed price line itents for services.)

(iii) For custontary progress payments based on costs incurred, submit a progress paynlent request.

(iv) For performance based paylrents, subnrit a performance based paylrent request.

(v) For conrmercial itern financing, subntit a contmercial item financing request.

(2)FastPayrequestsareonlyperrnittedwhenFederal AcquisitionRegulation(FAR) 52.213-l isincludedinthe contract.

fNote: The Colltl'actor may use a WAWF "conrbo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAIVF Data to be enlered in '|V4LVF

Pay Official DoDAAC

Issue By DoDAAC

Adrrin DoDAAC** w52PlJ w52P tJ w9rQFD

HQ0490

Ship To Code w9rQFD

N/AShip Flonr Code"M;.kF"aC;d; -iNrn

Service Approver (DoDAAC) w9rQFD

Service Acceptor (DoDAAC) WgIQFD

(4) Payrnent request. The Corrtlactor shall ensure a payrxent request includes docurrrentation appropliate to the type of payrnent request in accordance with the paynrerlt clause, contract firrarrcing clause, or Fedet.al AcqLrisition Regulation 52.216-7, Allowable Cost and Payrnent, as applicable.

(5) Receiving leport. The Contractor shall ensure a leceivirrg report lneets the requirernents of DFARS Apperrdix F.

Accept at Othel DoDAAC

LPO DoDAAC

DCAA Auditot DoDAAC

Other DoDAAC(s)

N/A

N/A

N/A

Page 2l of28

(g) WAWF point of contact.

( l) The Contractor nray obtain clarification regarding invoicing in WAWF fi'om the following contracting activity's WAWF point of contact.

(2) Contact the WAWF helpdesk at866-618-5988, if assistance is needed.

(End ofclause)

252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)

(a) The Governnrent will provide to tlre Contractor, without charge, one set of contract drawings and specifications, except publications incol'porated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.

(b) The Contractor shall--

( l) Check all drawings furnished immediately upon receipt;

(2) Compare all drawings and verifl the figures before laying out the work;

(3) Promptly notif, the Contlacting Officer of any discrepancres,

(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and

(5) Reproduce and print contract drawings and specifications as needed.

(c) In general--

( l) Large-scale drawings shall govern small-scale drawings; and

(2) The Contt'actor shall follow figures rnarked on drawings in prefelence to scale measurements.

(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestty necessary to carry out the intent ofthe drawings and specifications, or that are custontarily performed, shall not t'elieve the Contractol'fi'om perfolming such omitted or misdescribed details of the work. The Contractor shall perfornt such details as iffully and correctly setforth and described in the drawings and specifications.

(e) The work shall confornr to the specifications and the contract drawings identified on the following index of drawings:

Solicitation - W52P 1J20R5002 Attachment 0001 - Scope of Work dated l8 Decernber 2019 Attachment 0002 - Appendix A - Specifications Attachme nt 0003 - Appendix B - plans dated 2l February 2020

1l w52P I J20C5003

Page22 of28

Attachment 0004 - Davis Bacon Wage Determinations dated 05 December 2019 Attachment 0005 - Access Control Record Check Request Form

Page 23 of28

Section 00 73 00 - Supplernentary Conditions

CONTRACTOR PERFORMANCE

CONTRACTOR PERFORMANCE INFORMATION

The successful offeror/bidder under this solicitation is advised that after contract award its perfornrance under this contractwill besubjecttoanassessment(s) inaccordancewithFAR42.l5andAFARS5l42.l503-90. The Department of Defense (DoD) Contractors Perforrnance Assessntent Reporting Systenr (CPARS) will be used to maintain the pelfolmance repolt(s) generated on this contract. The rating system to be used in this assessment shall be as follows:

Exceptional (Dark Blue) - Perforrnance nleets contractual requirernents and exceeds many to the Government's benefit. Tlre contractual perfolmance of the element ol sub element being assessed was accomplished with few rninor problents for which corrective actions taken by the contractor were highly effective.

Very Good (Purple) - Performance meets contractual requirerrrerrts aud exceeds some to the Government's benefit. The contractual perforntance of the elemerrt or sub elenrent being assessed was accomplished with sonte lninor problems for which corrective actions taken by the colttractor were effective.

Satisfactory (Green) - Perfortnance rneets contractual requirernents. The contractual performance ofthe element ot' sub element contaius some minor ploblenrs for which corrective actions taken by the contractor appear or were satisfactory.

Marginal (Yellow) - Performance does not rneet sorre contractual requirements. The contractual perforttratrce of the elernent or sub elerrent being assessed reflects a serious problem fol which the contractor has not yet identified cot'rective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactoly (Red) - Perfortnance does not Ineet most contractual requiremeuts and recovery is not likely in atimely Iranner. The contractual performance of the element or sub element contains serious problern(s) for which the contractor's corrective actions appear or were ineffective.

The evaluation procedures to be used in this assessnrent, whiclr include coordination with the contractor, are detailed in AFARS 5142.1503-90.

SUPPLEMENTARY CONDITIONS

AMC PROTEST

If you have complaints about this procurelnent, it is preferable that you first aftempt to resolve those concerns with the responsible Contracting Officer. However, you can also protest to Headquarters, AMC. The HQ, AMC-Level Pl'otest Progratr is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forutr, rather than filing a protest with Genelal Accounting Office or other external forttm. Contract award or perfornrance is suspended during the protest to the sarne extent, and within the same time periods, as if filed atthe GAO. To be tinrely, protests nrust be filed within the periods specified in FAR 33.103.

Send protests (other than protests to the Contracting Officer) to:

Headquarters U.S. Army Materiel Command Office of Cornrnand Counsel-Deputy Commaltd Counsel 4400 Martin Road Rm:A6SE040.001 Redstone Arsenal. AL 35898-5000 Fax: (256) 450-8840 e-rnail:

The AMC-level protest procedures are found at:

If lnternet access is not available, contact the Contracting Officer or HQ, AMC Office of Command Counsel to obtain the AMC-Level Protest Procedures.

ROCK ISLAND ARSENAL SECURITY, LAW ENFORCEMENT, FIRE PREVENTION, AND SAFETY

REQUIREMENTS

Any contractor personnel entering Rock Island Arsenal (RIA) as the result of this order/cotltract are required to adhere to all regulations govelning safety, law enforcenrent, security, and fire prevention in effect at the time of entrance. Failure to comply with said regulations rray result in irnmediate removal frorn RIA. The contractor shall bear full responsibility ofthe consequences ofsaid renroval. Further clalifications ofRIA regulations are available from the Contracting Officer for this order/contract.

E,mergency Phone Number for Rock Island Arsenal. Dial 9-l-l FOR POLICE, FIRE - AMBULANCE. State your ltame, location, nature of enrergency and answet any questions the dispatcher rnay have. Stay on the line with the dispatcher until you are told you can hang up. Ifcalling from a cell phone, tell the dispatcher that you are calling fronr the Rock Island Arsenal.

OPERATIONS SECURITY (OPSEC) REVIEW:

I'…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .