AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of

2. Amendment/Modification No.

3. Effective Date

4. Requisition/Purchase Req No.

5. Project No. (If applicable)

6. Issued By Code 7. Administered By (If other than Item 6) Code

8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)

9A. Amendment Of Solicitation No.

9B. Dated (See Item 11)

10A. Modification Of Contract/Order No.

10B. Dated (See Item 13) Code Facility Code

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS

It Modifies The Contract/Order No. As Described In Item 14.

A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In

The Contract/Order No. In Item 10A.

B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set

Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).

C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:

D. Other (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.

14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. Name And Title Of Signer (Type or print)

16A. Name And Title Of Contracting Officer (Type or print)

15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed

By (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITIONS UNUSABLE

30-105-02 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

SEE SCHEDULE

X

Cost Plus Fixed Fee

0004 2019OCT24

W52P1J

ARMY CONTRACTING COMMAND - RI

ROCK ISLAND, IL 61299-8000

BLDGS 60 & 62

MATTHEW WARD

EMAIL: MATTHEW.A.WARD58.CIV@MAIL.MIL

W52P1J-19-R-0101

2019SEP11

X

X 2019NOV25 03:00pm

/SIGNED/

2 signed

SEE SECOND PAGE FOR DESCRIPTION

1 40

CONTINUATION SHEET

Reference No. of Document Being Continued Page of

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION A - SUPPLEMENTAL INFORMATION

Buyer Name: MATTHEW WARD

Buyer Office Symbol/Telephone Number: CCRI-VG/(309)782-3752

Type of Contract 1: Cost Plus Fixed Fee

Type of Contract 2: Firm Fixed Price

Kind of Contract: Service Contracts

*** End of Narrative A0000 ***

The purpose of Amendment 0004 is to do the following:

1) The proposal response deadline date has been extened for the Fort Huachuca, AZ requirement. The new submission deadline date is

Monday, November 25, 2019 - 1500 Central Time.

2) The new/revised workload documents have been finalized and are incorporated as part of this amendment. The RFP exhibit and attachment documents will be provided along with this amendment via email directly to those BOA Holders identified as a Service Disabled Veteran

Owned Small Business.

3) The Government encourages BOA Holders to review all documents to identify all changes made to the Fort Huachuca workload. Some of the workload changes include but are not limited to:

a) Updated FLC 1 Hours provided in Section L and Section M narratives.

b) Updated Past Performance Relevancy thresholds in Section M narrative.

c) Updated Attachment 0001 - Performance Work Statement.

d) Updated Exhibit A - FHAZ Technical Data Portfolio:

i) TD-01 Workload document

ii) TD-04 Hours of Operation

iii) TD-06 Key and Specified Non-Key Positions

e) Updated Exhibit B - FHAZ CDRL Portfolio:

i) Updated formats for multiple CDRLs and removed unnecessary tabs

ii) Removed CDRL MMD-02 through MMD-05

f) Updated Attachment 0002 - Staffing/Labor Mix.

g) Updated Attachment 0005 - Cost/Price Matrix (Including Teaming Matrix).

h) Updated Attachment 0016 - CBA to SCA Crosswalk.

4) The Government will not be responding to individual questions submitted regarding the initial RFP release. The new/updated workload documents have addressed errors identified within the initial workload and has rendered the submitted question as overcome by event.

5) All other terms and conditions remain unchanged.

*** END OF NARRATIVE A0005 ***

THIS RFP WILL BE COMPETED AMONGST ONLY THOSE OFFERORS THAT HOLD AN ENHANCED ARMY GLOBAL LOGISTICS ENTERPRISE (EAGLE) BASIC ORDERING

AGREEMENT (BOA) BY THE CLOSING DATE OF THIS RFP.

PLEASE BE SURE TO REVIEW ALL DOCUMENTS AGAIN AS SOME HAVE CHANGED FROM WHEN THE DRAFT RFP WAS ISSUED.

A.1 The U.S. Army Fort Huachuca, AZ has a requirement for logistics support services, including maintenance, supply, and transportation support.

A.2 This is the official RFP for the Fort Huachuca, AZ requirement. Industry feedback received on the DRAFT documents was taken into consideration in the preparation of the final RFP documents. Please note that the Government answers provided in response to the feedback received on the DRAFT documents are not incorporated into this RFP.

2 40

W52P1J-19-R-0101

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

A.3 This RFP is a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside and will be competed among those Offerors that hold an EAGLE Program BOA who can certify small business status under North American Industry Classification System (NAICS) Code 561210 by the closing date of this RFP.

This RFP will result in a single hybrid Cost Plus Fixed Fee / Firm Fixed Price Requirements Task Order with one (1) 12 month base period, to include a 30 day transition-in period, and four (4) 1-year options, for a total of five (5) years if all options are exercised. The evaluated option periods, which will be awarded at the Government's sole discretion, will be based on need and performance of contractors.

A.4 The period of performance for each Contract Line Item Number (CLIN) from Notice to Proceed (NTP) through 1826 Days after NTP is identified below:

CLIN SERVICE PERIOD OF PERFORMANCE:

Base Year PoP: CLINs 0001 - 0008, NTP - 365 days after NTP (includes 30 day Transition-In)

Option Year 1: CLINs 1002 - 1008, 366 days after NTP - 730 days after NTP

Option Year 2: CLINs 2002 - 2008, 731 days after NTP - 1095 days after NTP

Option Year 3: CLINs 3002 - 3008, 1096 days after NTP - 1461 days after NTP

Option Year 4: CLINs 4002 - 4008, 1462 days after NTP - 1826 days after NTP

Transition and Fully Operational Capability (FOC) efforts are part of a single requirement and period of performance. All Transition efforts are still required to be completed within the first 30 days of performance; however, transition to FOC is part of a seamless process. The Contracting Officer may authorize proceeding into FOC as various elements of transition are complete prior to the end of the 30 day Transition period.

A.5 This Best Value/Lowest Price Technically Acceptable (LPTA) source selection process will include an evaluation of the following three (3) factors: (1) Technical, (2) Past Performance, and (3) Cost/Price. A Task Order award under this EAGLE competition will be made to the Offeror determined to be responsible (in accordance with (IAW) Federal Acquisition Regulation (FAR) subpart 9.1) whose proposal conforms to the RFP requirements and is determined to be the lowest evaluated (fair and reasonable) priced proposal that is determined technically Acceptable with Substantial Confidence in Past Performance.

A.6 The Offeror's proposal shall be valid for 180 days from the closing date of the RFP.

A.7 The incumbent contractor is AOC Olgoonik Global Services under contract W52P1J-12-G-0076 Task Order 0001.

A.8 FAR 52.219-14 Limitations on Subcontracting (JAN 2017): Offerors are put on notice that they are required to follow the requirements of FAR 52.219-14 - Limitations on Subcontracting as currently written. Until such time as the FAR is updated to reflect any regulation changes prescribed by Section 1651 of the National Defense Authorizations Act of FY 2013, Offerors must comply with the current FAR Clause as written.

A.9 Government Furnished Facilities and Equipment are identified in the Exhibits/Attachments in Section J of this RFP and identified in the Performance Work Statement (PWS).

A.10 Please note that this RFP contains a Section B, "Supplies or Services and Prices/Costs"; however, Offerors are required to complete and submit the Cost/Price Matrix identified as Attachment 0005.

A.11 The Government intends to conduct a Post Award Conference with the awardee following Task Order award.

A.12 This RFP should not be discussed with any Government employee except the Procuring Contracting Officer (PCO), Ms. Tracey L.

Pickett or Contract Specialist, Mr. Matthew A. Ward, may be contacted at usarmy.RIA.acc.mbx.eagle@mail.mil.

A.13 This RFP and any amendments to this RFP shall be issued electronically. Because of this, the Government is under no obligation to maintain an Offerors mailing list. Any EAGLE BOA holders interested in this requirement must periodically access the FEDBIZOPS at https://www.fbo.gov/ to obtain the RFP and any amendments that may be issued. Failure to provide proposals in accordance with the ____________________________________________________ instructions/format specified in this RFP shall render the Offerors proposal non-compliant. The proposal will not be evaluated and will________________________________________________________________________________________________________________________________________ not be further considered for award.____________________________________

A.14 The Government is not obligated to provide responses to any questions submitted by Offerors, but will consider them and incorporate changes into the RFP as deemed necessary.

A.15 The closing date and time for this RFP is identified on page 1 of this RFP, the Local Time is Central Time. All proposal documents are due at the time set forth in this RFP.

A.16 TheFedBizOpps (FBO.gov) bid response system will be used in this procurement. FBO.gov allows Offerors to electronically submit

3 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

proposals to RFPs posted on FBO - see Paragraph L.3. Note: links to third party cloud file services or a Drop Box are not acceptable for delivery of proposals.

A.17 The DD254 Security Form is provided as Attachment 0012. The Offeror / Subcontractor identified on Attachment 0005, Tab 2 shall have a SECRET Facility Clearance prior to this RFP closing date. In addition, the Offeror / Subcontractors must have a Facilities

Clearance in order for personnel within the company to obtain a SECRET Clearance.

A.18 The Government will compare the Offeror's proposal to Section L in order to perform a compliance review. Failure to provide proposals in accordance with the instructions/format specified in this RFP shall render the Offerors proposal non-compliant. The proposal will not be further evaluated and will not be further considered for award. The Government reserves the right to waive strict compliance review if it is in the Government's best interest.

A.19 The Army Sustainment Command (ASC) will be using a support contractor, SERCO, for assistance in the management and oversight of

EAGLE task orders with a particular emphasis on cost management. To perform these duties, SERCO employees supporting this effort will have access to the following contract information under EAGLE:

Award documents and all modifications to include cost/price information

Invoices

Union Agreements to include labor rates

All Contract Data Requirements Lists submissions

The contracted support provided by SERCO or any other future support contractor is technical in nature, and in no way supplants the

Governments exclusive responsibility for the decision making regarding contract management and oversight. The support contract prohibits the unauthorized use or disclosure of any of the aforementioned information. Further, SERCO has signed a non-compete statement for the

EAGLE program and will not submit a proposal on EAGLE solicitations (as a prime, subcontractor, or advisor) and will not participate in any resultant contract in any aforementioned role IAW FAR 9.507(to prevent any unfair competitive advantage). All awardees will be required to permit this support contractor to have necessary access to the documents outlined above and to enter into an agreement with the support contractor permitting such necessary access, and establishing proper protections (see FAR 9.505-4(b)).

A.20 Organizational conflict of interest (OCI) means a situation in which-

(1) A Government contract requires a contractor to exercise judgment to assist the Government in a matter (such as in drafting specifications or assessing another contractor's proposal or performance) and the contractor or its affiliates have financial or other interests at stake in the matter, so that a reasonable person might have concern that when performing work under the contract, the contractor may be improperly influenced by its own interests rather than the best interests of the Government; or

(2) A contractor could have an unfair competitive advantage in an acquisition as a result of having performed work on a Government contract, under circumstances such as those described in paragraph (1) of this definition that put the contractor in a position to influence the acquisition.

(3) If the Contractor identifies an OCI, the Contractor shall make a prompt and full disclosure in writing to the Procuring Contracting

Officer (PCO). OCI that arise during performance of the contract, as well as newly discovered conflicts that existed before contract award, shall be disclosed.

A.21 Notice of Organizational Conflicts of Interest (OCI): SERCO Inc., and any affiliates, subsidiaries, or subcontractors are precluded from offering a proposal as either a prime or a subcontractor, or from participating as a member of any team competing for this contract and/or any other resultant contracts stemming from this RFP. The Government reserves the right to reject any offer it considers to represent an OCI. Offerors are directed to FAR 9.5 for further information on OCIs for detailed OCI contract restrictions/requirements.

A.22 The Estimated Total Contract Value (ETCV) is TBD (at award). The ETCV amount is NOT a ceiling price, but rather an ESTIMATE of the total five (5) "and a half" years of performance under this contract.

A.23 This is a Requirements Contract IAW FAR 52.216-21 for the services specified in the PWS and workload data, and effective for the period of performance identified in Paragraph A.4.

A.24 If an Amendment is deemed necessary for this RFP, the Amendment notice will be posted electronically to FBO (as stated in A.13).

Please be advised that when an Amendment is posted to FBO, it will be listed on the bottom of the RFP notice.

*** END OF NARRATIVE A0001 ***

4 40

PIIN/SIIN

Page of

Name of Offeror or Contractor:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

Reference No. of Document Being Continued

MOD/AMD

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

9999 DRAFT _____

OFFERORS SHALL SUBMIT PRICES USING ATTACHMENT 0005-

COST/PRICE MATRIX

BILLING INSTRUCTIONS FOR CLIN 0001-0008:

The Contractor is authorized to bill IAW FAR

52.216-7(a)(1).

(End of narrative B001)

5 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

STATEMENT OF WORK: CONTRACTOR MANPOWER REPORTING (CMR)

The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Logistics Support Services for Fort Huachuca, AZ via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/ , and then click on

"Department of the Army CMRA" or the icon of the DoD organization that is receiving or benefitting from the contracted services.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs

October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October

31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk by clicking on Send an email which is located under the Help Resources ribbon on the right side of the login page of the applicable Service/Components CMR website.

C.1 EAGLE BUSINESS RULES - STEP THREE TASK ORDER REQUEST

(a) An Offeror must be a qualified BOA holder by the closing date of the RFP. The Government is under no obligation to place an order against an EAGLE BOA.

(b) A Task Order becomes a binding contract at the time of the Government's acceptance of a Task Order proposal and award of a Task

Order per FAR 16.703(c)(1)(iv).

(c) This Task Order is being competed among EAGLE BOA holders who hold a BOA at the time of the closing date of the RFP. No extensions to the RFP will occur for purposes of allowing interested Offerors additional time to become an EAGLE BOA holder. The Government will confirm that an Offeror is a qualified BOA holder by checking the effective date of an Offerors BOA. Due to the complexity and the wide range of capabilities required by this Task Order, Joint Ventures (JVs) may be utilized; however, a JV offeror must be an approved BOA holder from Step Two in order to propose as a Prime on this Task Order solicitation, and the JV must comply with the applicable requirements of Title 13 of the Code of Federal Regulations (CFR) (see Parts 121.103(h), 124.513, 125.15, 126.616, and 127.506).

(d) In Step Two (i.e. BOA process), BOA holders were required to demonstrate the capability to perform all three functional areas; that technical capability may have been achieved with or without subcontractors. For this Task Order (Step Three), Offerors are not required to propose those same subcontractors that were used to establish technical capability in Step Two; however, the Offeror must propose itself and any subcontractors that are necessary for it to be able to meet the evaluation criteria and successfully perform the requirements of this Task Order.

(e) The contractor shall adhere to the prices proposed and agreed to in this resultant task order issued against its BOA. The contractor is not authorized to begin work on an order issued against the BOA until prices have been established. In the event that the

Contracting Officer requires work to begin prior to establishment of pricing, failure to reach agreement on price may be disputed under the Disputes clause.

(f) The following sections submitted by the Offeror with its BOA proposal will be carried forward and incorporated by reference into this Step Three EAGLE Task Order contract:

BOA RFP L.5.1.5 Property Management Plan

BOA RFP L.5.2.1(c) Resource / Task Order Management

BOA RFP L.5.2.1(d) Flexible Staffing Approach

BOA RFP L.5.2.1(e) Transition-in Approach

BOA RFP L.5.2.3(b)(3) Identification of an onsite independent quality control

(g) Failure to comply with any term of the Task Order, to include meeting small business subcontracting goals, may result in negative past performance that could negatively impact the BOA holder's ability to be successful in future Task Order competitions.

(h) The Contractor may be required to enter into an Associate Contractor Agreement (ACA) with another contractor as part of this task order performance.

(i) Responsibility determinations will be made at Step Three. An otherwise successful Offeror may not be eligible for award if it cannot be determined responsible for any of the reasons in FAR 9.104, including capacity.

(j) RESERVED

(k) Size Standards. SBA's size eligibility standards are found in Title 13 of the Code of Federal Regulations (CFR) Part 121 (13 CFR

Part 121). In order to ensure that an Offeror qualifies as an eligible small business, prospective Offerors are encouraged to review

6 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

this regulation (which was substantially revised in 2016) in its entirety. 13 CFR 121.103 in particular may assist a prospective offeror in assessing whether affiliation could apply; a finding by the SBA of affiliation between entities may result in a determination that the Offeror is other than a small business and therefore ineligible for the Small Business Set Aside Task Order award. An offeror with questions regarding size eligibility standards should contact its legal counsel and/or SBA Office of Government Contracting personnel;

8(a) Program participants may consult the cognizant SBA Business Opportunity Specialist.

The SBA is the sole authority for making determinations of small business status for small business programs; such determinations are binding on the Offeror and on the Contracting Officer. Generally, SBA determines the size status of a concern (including affiliates) as of the date the concern submits a written self-certification that it is small to the procuring agency as part of its initial offer including price. This determination is done at this Task Order level (Step Three) and will apply for the term of the Task Order not to exceed (NTE) five (5) years six (6) months. For task orders that exceed five (5) years, FAR 52.219-28, Post-Award Small Business Program

Representation, applies.

Entities proposing as a JV are encouraged to specifically review 13 CFR 121.103, "How Does SBA Determine Affiliation?" subparagraph (h)

(Affiliation based on joint ventures) prior to submitting a proposal. 13 CFR 121.103 provides several examples that may assist a prospective offeror in assessing whether affiliation could be applied to its JV. Note: In accordance with 13 CFR 121.103, a JV of two

(2) or more business concerns may submit an offer as a small business without regard to affiliation so long as each concern is mall under the size standard for NAICS 561210. In order for this affiliation exception to apply, however, the following conditions must be met: there must be a written JV agreement, the JV must do business under its own name and be identified in the System for Award

Management (SAM), and the JV must not have been awarded more than three (3) contracts within a two-year period from the date of award of the first contract (i.e. as of the date that it submits an initial offer that leads to the award of a contract, the JV must not have been awarded any more than two (2) contracts in the previous two (2) years).

Offerors proposing subcontracting arrangements at this Task Order level (Step Three) are encouraged to specifically review 13 CFR

121.103, "How Does SBA Determine Affiliation?" (subparagraph (h)(4)) prior to submitting a proposal. A finding by the SBA of affiliation between an offeror and its subcontractor(s) may result in a determination that the Offeror is other than a small business and therefore ineligible for the SBSA Task Order award. For SBSA solicitations, Offerors proposing subcontracting arrangements at the Task Order level

(Step Three) may be required to explain which of its subcontractors are similarly situated subcontractors pursuant to the definition provided in 13 CFR 125.1 for purposes of determining whether the arrangement includes the use of any ostensible subcontractors and thus treated as a JV and the entities considered affiliated.

(l) Limitations on Subcontracting (Subject to Change with Pending Legislation)

Offerors must be cognizant of FAR 52.219-14, "Limitations on Subcontracting." This clause is mandatory for all set-aside acquisitions.

When an Offeror self-certifies in Section K of the solicitation that it is a small business, the Offeror is also self-certifying it will comply with FAR 52.219-14, which means that with the submission of an offer and execution of a contract, the offeror agrees that in the case of a contract for Services, at least percent fifty (50%) of the cost of contract performance incurred for personnel shall be expended for employees of the concern. Any indication on the face of the proposal that the offeror will not or cannot comply with the

Limitations on Subcontracting clause will render the proposal unacceptable and the offeror ineligible for award; that is a decision that will be made during the evaluation of the proposal, not during a responsibility determination, and thus does not go to the SBA for final review.

(m) ORGANIZATIONAL CONFLICT OF INTEREST

The EAGLE contractor grants authority for Government officials to release necessary proprietary information to the ASC support contractor (currently SERCO, Inc.) to assist ASC in the management and oversight of EAGLE task orders. The EAGLE contractor shall immediately upon award negotiate and execute an agreement with the support contractor to permit access to necessary proprietary information and to protect against improper release of such information by the support contractor in accordance with FAR 9.505-4. The

EAGLE contractor shall ensure that this authority covers any proprietary information that may be required of subcontractors as well.

C.2 CONTRACTOR PERFORMANCE MANAGEMENT REVIEW

(a) All tasks under this contract will be subject to periodic (not less than quarterly) performance management reviews (PMR). The PMR can be either positive, outlining best practices or cost savings, or negative in the event the contractor fails to perform as outlined in the PWS, applicable regulations, or PCO direction. PMRs will be provided to the contractor not less than quarterly or as deemed necessary by the COR, Government Program Manager or PCO. The Contractor will receive briefings on the PMR reports and be allowed the opportunity to submit a response. Contract Deficiency Reports (CDRs) and/or Corrective Action Request (CARs) will be reviewed during the

PMR, if the Government deems them material. The contractor will present its independent assessment of performance during the PMR.

Contractor's presentation will consist of work accomplished, evaluation of work against applicable program metrics (to include schedule), cost savings, lessons learned, forecasted staffing requirements based on anticipated workload, self-evaluations/inspection results, corrective actions, funding levels/contractor performance report (financial), contractor-employee utilization rates and must address all CARs, CDRs or other notices issued by the PCO.

(b) Contractor Performance Assessment: Currently, the Government uses an escalating system of deficiency reporting: local (on-site) and

7 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

PCO issued contract discrepancy report (CDR; DA Form 5479). Local deficiency reporting consists of: verbal notification and CAR. Verbal notification is primarily used for non-repeating, minor non-conformance/discrepancies of tasks that can be re-performed at no additional cost to the government and with minimal impact to the effort. A CAR will be issued by COR when previous verbal notifications failed to result in corrective actions or when more/major non-conformance or significant deficiencies exist/occur. The CAR will be issued to the contractor by the COR and forwarded to the PCO through the government program management office/COR for tracking/action. Un-resolved

CARs or significant deficiencies will result in the PCO issuing a formal CDR. CDRs are provided to the contractor's corporate office(s) for action with an assigned suspense date. CDRs are a significant indicator of performance and will be used to substantiate the

Government's CPARS input. Performance deficiencies may include any government-identified noncompliance with contract requirements; an activity or action did not take place, or did not take place to the standards of timeliness or quality required. Note, that while the contractor will be given the opportunity for re-performance when possible, significant deficiencies will nevertheless be documented. Use of this escalating deficiency reporting procedure does not, in any way, limit the Government's ability to take corrective action up to and including termination.

(c) Contractor's Fixed Fee will be assessed for validated negative PMRs, unresolved CDRs or as determined by the PCO IAW FAR 52.246-5 using the following schedule:

Critical Nonconformance - Contractor's fee will be assessed not less than 10% (ten percent) of the monthly fixed fee in which the critical nonconformance occurred. PCO determination will address the exact fee decrement based on severity, impact to the effort, contractor willingness to resolve and any other factors as deemed relevant by the PCO.

Unresolved CDRs - Contractor's fee will be assessed not less than 5% (five percent) of the daily fixed fee starting with first day of delinquency in resolution. Fee reduction percentages are assigned as follows; however, the PCO has the discretion to apply whatever percentage it deems reasonable based on severity, impact to the effort, contractor willingness to resolve and any other factors as deemed relevant by the PCO.

Percentage of Fee:

Critical: 10% and above (monthly) Major: 7-10% (daily)

Minor: 5-7% (daily)

The Contractor will be given the opportunity to comment and respond to issued CARs and/or CDRs during the PMR prior to the Government executing a fee decrement.

Definitions:

Critical nonconformance - a nonconformance that is likely to result in hazardous or unsafe conditions for individuals using, maintaining, or depending upon the supplies or services; or is likely to prevent performance of a vital agency mission. Repeated or unresolved major nonconformance will result in re-designation as critical nonconformance.

Major nonconformance - a nonconformance, other than critical, that is likely to result in failure of the supplies or services, or to materially reduce the usability of the supplies or services for their intended purpose. Repeated or unresolved minor nonconformance will result in re-designation as major nonconformance.

Minor nonconformance - a nonconformance that is not likely to materially reduce the usability of the supplies or services for their intended purpose, or is a departure from established standards having little bearing on the effective use or operation of the supplies or services.

Unresolved CDR - a CDR remaining unresolved, or unacknowledged, past the PCO established suspense date may be re-designated as minor, major or critical based on the PCO independent determination.

Daily Fee - The yearly fixed fee amount divided by 12 months divided by 30 days.

C.3 PURCHASING AND INVOICING PROCEDURES

(a) The Government and Contractor shall utilize the procedures outlined in the Purchasing and Invoicing Guide (Attachment 0009). This guide details the process that the United States Government (USG) will use to conduct and oversee contractor purchasing and invoicing on this task order. Each step in the process will be described in detail along with the responsibilities of each individual position. It is the intent of the Government that the process will be sufficient for detailed cost accounting and approval without negatively impacting the contractor's ability to provide Maintenance services at Fort Huachuca, AZ. If the process is found to negatively impact operations it will be re-evaluated by the USG and updated appropriately to achieve the desired effect.

(b) Final invoice for the Transition-In CLIN shall be submitted no later than 7 days after the end of CLIN 0001's period of performance.

C.4 GOVERNMENT PROPERTY

8 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

(a) In the event that Government property accountable to this contract is lost, damaged, destroyed or stolen, the Contractor shall promptly perform an investigation and provide a report to the Contracting Officer or the Contracting Officers representative IAW FAR

52.245-1(f)(1)(vi) and DFARS 252.245-7002 Reporting Loss of Government Property. The Contracting Officer shall review the Contractor's report and, if the Contracting Officer deems necessary, may perform an additional independent investigation in accordance with FAR

52.245-1 (g). In accordance with FAR 52.245-1 (g) (3) should it be determined by the Government that the Contractors (or subcontractors) property management practices are inadequate or not acceptable for the effective management and control of Government property under this contract, or present an undue risk to the Government, the Contractor shall prepare a corrective action plan and take all necessary corrective actions as specified by the schedule within the corrective action plan. The Contracting Officer may, in writing, revoke the

Governments assumption of risk for loss, theft, damage or destruction, due to a determination under FAR 52.245-1 (g) that the

Contractors property management practices are inadequate, and/or present an undue risk to the Government, and the Contractor failed to take timely corrective action. If the Contracting Officer revokes the Government's assumption of liability and holds the Contractor liable, the Contractor may not charge the Government for the loss, theft, damage or destruction of Government property or any costs associated thereof except as provided in accordance with FAR 52.245-1 (h) (1) (iii). The Contracting Officer may delegate the investigation to an appropriate Government representative of the Contracting Officer's choosing.

C.5 COST/PRICE CONTRACT EXECUTION

(a) If the Offerors and/or Subcontractors proposals include indirect expense rate(s) which were determined by the Government to be not fully supported, those rates will be capped at the proposed rates for evaluation purposes and for the life of the task order contract, including any additional workload outside the original estimate pursuant to the Requirements clause FAR 52.216-21. In the event a rate(s) is capped, the following statements will be included in the award document, as applicable.

CAPPED RATES: TBD

INDIRECT RATE(s): TBD

PRIME: KTR NAME TBD

KTR NAME proposal dated TBD included indirect rates which were determined by the Government to be not fully supported. As such, the following rates are hereby CAPPED for the life of this requirements task order (52.216-21) in accordance with M.5.3.3(a) of the solicitation:

TBD% for CAPPED RATE(S) by period

Example: update accordingly if applicable

Overhead = Base - 3%, OY1 3.25%, OY2- 3.5%, OY3 3.75% OY4 4%, and

G&A = Base - 3%, OY1 3.25%, OY2- 3.5%, OY3 3.75% OY4 4%, SUBCONTRACTOR: KTR NAME

The Cost/Price proposal dated TBD independently submitted by Subcontractor, KTR NAME, included indirect rates which were determined by the Government to be not fully supported. As such, the following rates are hereby CAPPED for the life of this requirements task order

(52.216-21) in accordance with M.5.3.3(a) of the solicitation:

TBD% for CAPPED RATE(S) by period

Example: update accordingly if applicable

Overhead = Base - 3%, OY1 3.25%, OY2- 3.5%, OY3 3.75% OY4 4%, and

G&A = Base - 3%, OY1 3.25%, OY2- 3.5%, OY3 3.75% OY4 4%,

(b) Fee Rates: Contractor name proposal dated TBD included a fee rate(s) of TBD% which is hereby capped as proposed for the life of this task order in accordance with M.5.3.3(b) of the Solicitation.

C.6 AbilityOne Program and/or 8(a) Contracts

(a) Notwithstanding the inclusion of FAR 52.216-21 in this task order, any maintenance, supply, and transportation tasks currently being performed by an AbilityOne contractor or an 8(a) contractor at Fort Huachuca, AZ, or subsequently determined appropriate for performance by an AbilityOne contractor or an 8(a) contractor, are not included within the scope of this EAGLE requirements Task Order.

C.7 POST - AWARD CONFERENCE:

The Contractor agrees to attend any post-award conference convened by the contracting activity or contract administration office IAW FAR subpart 42.5.

9 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

*** END OF NARRATIVE C0001 ***

10 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 BILLING INSTRUCTIONS FOR CLIN 0001-0008:

The Contractor is authorized to bill in IAW FAR 52.216-7(a)(1).

G.2 Fixed Fee Withholds:

In accordance with FAR Clause 52.216-8 Fixed Fee, the Government will withhold $TBD (five (5) percent or $100,000.00, whichever is less, of the total fixed fee applicable to the current period of performance). However, based on information known, the Contracting Officer has the authority to raise the withhold to fifteen (15) percent or $100,000.00, whichever is less, of the total fixed fee applicable to the current period of performance if the Contracting Officer determines it is in the Government's best interest to do so. The contractor is authorized to invoice fixed fee applicable to the current period of performance up to an amount not to exceed $TBD per month (1/11th of the Max Fee able to be invoiced for the Base Year and 1/12th of the Max Fee able to be invoiced for Option Years). In total the contractor is not authorized to invoice fixed fee above $TBD (the difference of total fixed fee for the current period of performance less the Government withhold). See Attachment TBD for the specific fee amounts applicable to the current period of performance. The Contracting Officer shall release 75 percent of all fee withholds under this contract after receipt of an adequate certified final indirect cost rate proposal covering the year of physical completion of this contract, provided the Contractor has satisfied all other contract terms and conditions, including the submission of the final patent and royalty reports, and is not delinquent in submitting final vouchers on prior years' settlements. The Contracting Officer may release up to 90 percent of the fee withholds under this contract based on the Contractor's past performance related to the submission and settlement of final indirect cost rate proposals IAW FAR 52.216-7(h)(1). Upon approval of a completion invoice or voucher submitted by the Contractor IAW FAR 52.216-

7(d)(5), and upon the Contractors compliance with all terms of this contract, the Government shall promptly pay any balance of allowable costs and that part of the fee (if any) not previously paid.

G.3 The direct labor rates contained in this contract (to include those included by way of incorporation of the contractor's proposal) are considered binding to the following extent. The contractor shall inform the Contracting Officer of any change in rates prior to submitting an invoice containing rates other than those agreed to previously. If the Contracting Officer determines the submitted rate(s) to be unreasonable the contractor shall not execute any action(s) to increase the previously agree to rate(s) and shall not submit invoice(s) containing rates other than those agreed to previously.

*** END OF NARRATIVE G0001 ***

11 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION H - SPECIAL CONTRACT REQUIREMENTS

CONTRACTOR PERFORMANCE INFORMATION

The successful offeror/bidder under this solicitation is advised that after contract award its performance under this contract will be subject to an assessment(s) in accordance with FAR subpart 42.15 and AFARS 5142.1503-90. DoD CPARS will be used to maintain the performance report(s) generated on this contract. The rating system to be used in this assessment shall be as follows:

Exceptional (Dark Blue) Performance meets contractual requirements and exceeds many to the Governments benefit. The contractual performance of the element or sub element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good (Purple) Performance meets contractual requirements and exceeds some to the Governments benefit. The contractual performance of the element or sub element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory (Green) Performance meets contractual requirements. The contractual performance of the element or sub element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal (Yellow) Performance does not meet some contractual requirements. The contractual performance of the element or sub element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractors proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory (Red) Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub element contains serious problem(s) for which the contractors corrective actions appear or were ineffective.

The evaluation procedures to be used in this assessment, which include coordination with the contractor, are detailed in AFARS 5142.1503-

90.

REQUIRED INSURANCE

Pursuant to FAR 52.228-5(a), "Insurance Work on a Government Installation", or FAR 52.228-7, "Insurance Liability to Third Persons", the

Contractor shall procure and maintain the following insurance during the entire period of performance under this contract:

TYPE AMOUNT____ ______

Workers Compensation As required by Law

Employers Liability Minimum liability limit $100,000

General Liability Minimum bodily injury limits, $500,000 peroccurrence

Automobile Liability Minimum liability of $200,000 per person, $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage

Aircraft Public and Passenger Liability Coverage required when contract performance involves use of aircraft: Minimum liability of $200,000 per person, $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Passenger liability shall be at least $200,000 multiplied by the number of seats or number of passengers, whichever is greater.

Vessel Collision Liability Coverage required when contract performance involves use of vessels: Minimum liability of $5,000,000 or the market value of the property being shipped by vessel, whichever is greater.

*** END OF NARRATIVE H0001 ***

12 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION J - LIST OF ATTACHMENTS

List of Number List of Number

Addenda Title Date of Pages Transmitted By Addenda Title Date of Pages Transmitted By________________ ____________________________________________________________ _______________ ____________ _______________________________ ____________________________________________________________ _______________ ____________ _______________

Exhibit A FHAZ TECHNICAL DATA PORTFOLIO 04-OCT-2019

Exhibit B FHAZ CDRL PORTFOLIO 04-OCT-2019

Attachment 0001 PERFORMANCE WORK STATEMENT 30-SEP-2019 059

Attachment 0002 STAFFING/LABOR MIX 04-OCT-2019

Attachment 0003 PAST PERFORMANCE QUESTIONNAIRE 19-JUN-2019 001

Attachment 0004 LETTER OF CONSENT 19-JUN-2019 001

Attachment 0005 COST/PRICE MATRIX (INCLUDING TEAMING MATRIX) 22-OCT-2019

Attachment 0006 SF 1408 PREAWARD SURVEY 19-JUN-2019 002

Attachment 0007 DEPARTMENT OF LABOR WAGE DETERMINATION 02-AUG-2019 018

Attachment 0008 COLLECTIVE BARGAINING AGREEMENT 12-APR-2017 029

Attachment 0009 PURCHASING & INVOICING GUIDE 19-JUN-2019 010

Attachment 0010 BLOCK FILE EXTENSIONS 21-JAN-2016 001

Attachment 0011 CONTRACT REFERENCE SPREADSHEET 19-JUN-2019

Attachment 0012 DD254 - CONTRACT SECURITY CLASSIFICATION SPECIFICATION 20-JUN-2019

Attachment 0013 MISSION ESSENTIAL CONTRACTOR SERVICES 02-MAY-2019 002

Attachment 0014 RESERVED

Attachment 0015 SUBCONTRACTOR COST INFORMATION SUBMISSION 19-JUN-2019 001

Attachment 0016 CBA TO SCA CROSSWALK 04-OCT-2019

Attachment 0017 RESERVED

Attachment 0018 RESERVED

13 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

AMC-LEVEL PROTEST PROGRAM

If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible

Contracting Officer. However, you can also protest to Headquarters, AMC. The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with General Accounting Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO. To be timely, protests must be filed within the periods specified in FAR 33.103. Send protests (other than protests to the Contracting Officer) to:

Headquarters U.S. Army Materiel Command

Office of Command Counsel-Deputy Command Counsel

4400 Martin Road

Rm: A6SE040.001

Redstone Arsenal, AL 35898-5000

Fax: (256) 450-8840 e-mail: usarmy.redstone.usamc.mbx.protests@mail.mil

The AMC-level protest procedures are found at:

https://www.amc.army.mil/amc/commandcounsel.html

If Internet access is not available, contact the Contracting Officer or HQ, AMC Office of Command Counsel to obtain the AMC-Level

Protest Procedures.

*** END OF NARRATIVE L0002 ***

L.1 GENERAL INSTRUCTIONS:

L.1.1 These instructions are a guide for preparing a proposal. These instructions describe the type and extent of information required, and emphasizes the significant areas to be addressed in the proposal. Review the Performance Work Statement (PWS) contained in this

Request for Proposal (RFP) for further insight into the areas that must be addressed within the proposal. Include detailed information sufficient to enable the Government evaluators to conduct a meaningful review and make a determination relative to the Offeror's understanding of the requirements in each of the evaluated areas. It is the Government's intent to award a single combination Cost-Plus

Fixed Fee / Firm Fixed Price (Transition-In CLIN and PMO CLINs only) Requirements contract with some non-fee bearing cost elements

(e.g., Other Direct Costs) which are ancillary to the services provided.

L.1.2 In accordance with (IAW) FAR 52.215-1, Instructions to Offerors - Competitive Acquisition (Jan 2017), the Government intends to award a contract without discussions. Offerors are cautioned to examine this RFP in its entirety and to ensure that proposals contain all necessary information, provide all required documentation, and are complete in all respects. The Government is not obligated to make another request for the required information nor does the Government assume the duty to search for data to cure problems it finds in proposals. The Government reserves the right to conduct discussions in the evaluation process and to permit Offerors to revise proposals, if deemed necessary. During the evaluation process, the Government may request clarifications as needed. Clarifications do not constitute discussions and an Offeror is not allowed to change its proposal in response to a request for clarification. In accordance with FAR 15.306(c)(2), if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Any Offeror eliminated from further consideration will be notified in writing.

L.1.3 Offerors shall submit proposals that will remain valid for not less than 180 days from the required submission date.

L.1.4 Proposals, modifications, revisions, or withdrawals of proposals received after the date established in this RFP for receipt of proposals will be handled IAW FAR Clause 52.215-1.

L.1.5 An Offeror is defined as the prime BOA Holder submitting a proposal under this RFP.

L.1.6 For the purposes of this Task Order RFP, a Joint Venture (JV) is defined as a team of two or more firms that have entered into a legally binding JV agreement. A firm proposing as a JV will be referred to as the Offeror.

L.1.7 Updates related to this Task Order RFP, to include the RFP, amendments, notices, and other information, will be made available on the FBO.gov website. Offerors are advised to continuously monitor the FBO.gov website for new information. Offerors are deemed to have knowledge of all information that is posted to the FBO.gov website.

L.2 PROPOSAL PREPARATION:

14 40

Name of Offeror or Contractor:

PIIN/SIIN MOD/AMD

L.2.1 The proposal must be prepared in a clear and legible manner. In addition, the Offeror shall write the proposal in English and the proposal must be specific and complete as described in these instructions. Offerors shall not specifically prepare samples or descriptive literature for submission with the proposal. Adherence to the prescribed format is required.

This is the start of the file's text. The full file is on GovTribe.