Attachment_0001_-_Price_Matrix_-_Piston_Plate_Assemblies.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Piston Plate Assembly
- Solicitation number
- W52P1J-17-R-3026
About this file
Attachment 0001 - Price Matrix - Piston Plate Assembly
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W52P1J-17-R-3026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
ATTACHMENT 0001
| OFFEROR: | Contractor Fill-In | |
| CAGE CODE: | Government Fill-In | |
| ITEM: | Piston Plate Assemblies | |
| SOLICITATION: | W52P1J-17-R-3026 |
| ORDERING PERIODS: | Begins | Ends |
| ORDERING PERIOD 1: | Date of basic contract award | 31-Dec-17 |
| ORDERING PERIOD 2: | 1-Jan-18 | 31-Dec-18 |
| ORDERING PERIOD 3: | 1-Jan-19 | 31-Dec-19 |
| ORDERING PERIOD 4: | 1-Jan-20 | 31-Dec-20 |
| ORDERING PERIOD 5: | 1-Jan-21 | 31-Dec-21 |
| NOTE: Each ordering period runs from the beginning through ending dates identified above. |
Guaranteed Minimum 15,500 EA
| Ordering Period 1 | Ordering Period 2 | Ordering Period 3 | Ordering Period 4 | Ordering Period 5 | |||||||||
| Quantity Ranges (Each) | Price Per Each | Weight | Price Per Each | Weight | Price Per Each | Weight | Price Per Each | Weight | Price Per Each | Weight | |||
| 1,000 | - | 6,250 | $0.00 | 10% | $0.00 | 10% | $0.00 | 10% | $0.00 | 10% | $0.00 | 10% | |
| 6,251 | - | 12,500 | $0.00 | 30% | $0.00 | 40% | $0.00 | 40% | $0.00 | 40% | $0.00 | 40% | |
| 12,501 | - | 18,750 | $0.00 | 40% | $0.00 | 30% | $0.00 | 30% | $0.00 | 30% | $0.00 | 30% | |
| 18,751 | - | 25,000 | $0.00 | 20% | $0.00 | 20% | $0.00 | 20% | $0.00 | 20% | $0.00 | 20% | |
| 100% | 100% | 100% | 100% | 100% | |||||||||
| Ordering Period | |||||||||||||
| Evaluated Price | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
TOTAL EVALUATED PRICE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ - 0
The offeror is required to fill in only the blue shaded boxes The Total Evaluated Price is calculated as follows:
1. The Ordering Period Evaluated Price is the sum of the following calculation at each quantity range: for each quantity range the Price Per Pound will be multiplied by the upper limit of the quantity range then multiplied by the respective weight.
2. The Total Evaluated Price is the sum of the Ordering Period Evaluated price.