# Question Answer Posted on FBO
The Section L chart states “Provide organizational Structure and offeror’s teaming agreements to document teams”. Does the
Government require copies of offeror teaming agreements? If not, recommend this language be changed to read “Provide organizational structure, noting each subcontractor and their role on the offeror’s team”. See Original ACCENT RFP Q&A Combined 1-90, question #3. 10/20/2017
2 Is there an incumbant?
The execution of a BOA with any new offerors resulting from the on-boarding process will not replace any previous BOAs. 10/20/2017
Will companies that intend to prime ACCENT still be able to team with and/or sub to other ACCENT primes? If so, should this be done at the
BOA or Task Order level?
There are no limitations on teaming or subcontracting arrangements. This may be done at the BOA or the Task Order level, based on vendor preference. 10/20/2017
Section L.1.4 states "The offeror shall submit its proposal directly to the
ACC-RI Contracting Office via email with attachment or submission of
CD at araka.e.schroeder.civ@mail.mil < Caution-mailto:araka.e.schroeder.civ@mail.mil > with copy to or via postal address at 3055 Rodman Ave, Bldg 62, Rock Island Arsenal, Rock Island
IL 61299 Attn: Araka Schroeder" Are we required to copy the email submission to anyone else besides Araka Schroeder? (no name is provided after "with copy to") And are we required to submit a printed copy to ACC-RI, or will our email submission suffice?
This was a typographical error. It will be amended to state "The offeror shall submit its proposal directly to the ACC-RI Contracting Office via email with attachment or submission of CD at araka.e.schroeder.civ@mail.mil with copy to mary.m.robacker.civ@mail.mil or via postal address at 3055 Rodman Ave, Bldg 62, Rock Island Arsenal, Rock Island IL 61299 Attn: Araka Schroeder." 10/20/2017
After the award of a BOA to an Offeror, can an Offeror add additional
DoD-PA certified team members to their team? Yes. 10/20/2017
If yes to the above question, what is the process, and frequency, for
BOA-awarded Offerors to add DoD-PA certified team members to their team after award of a BOA? See Original ACCENT RFP Q&A Combined 1-90, question #19. 10/20/2017
Is there a service catalogue for all assets within the current customer base for the ADCCP Executive order? The Army has not yet identified all the requirements. 10/26/2017
8 Are their SLAs or performance metrics for all of the assets?
Anything regarding SLAs or performance metrics will be determined at the Task
Order level. 10/26/2017
Is the IaaS at the hypervisor level or operational system level? Please advise.
The IaaS requirements will be determined by the requirement at the Task Order level. 10/26/2017
Are offerors allowed to add other items in the headers and footers such as the solicitation name and disclaimers? See Original ACCENT RFP Q&A Combined 1-90, question #24. 10/26/2017
ACCENT On Ramp 1 Q&A
“Offerors may submit questions up to ten (10) days prior to the closing date.” Will the Government confirm that these ten days are calendar days, meaning from November 7th , it would be NLT October 28th? Yes, the ten days are calendar days. 10/26/2017
“Up to 2 pages for cover letter or title page…” Will the Government confirm that the administrative information required on the cover letter
(2 pages max) is separate of the graphical title page that goes on the front of our proposals (not included in page count)?
See Original ACCENT RFP Q&A Combined 1-90, question #38. A graphical title page would be included in the page count. 10/26/2017
Will the Government confirm that separate files for each Section/Factor are allowed but not required? See Original ACCENT RFP Q&A Combined 1-90, question #10. 10/26/2017
Will the Government consider allowing a smaller font size, such as 9 point Arial Narrow, for headers/footers and graphics to allow offerors to adequately fit the information required and necessary? See Original ACCENT RFP Q&A Combined 1-90, question #60. 10/26/2017