This is a Performance Work Statement (PWS) for a non-personal services contract to remove and replace outdated warehouse racking in Building 6-1 at Tobyhanna Army Depot (TYAD) in Tobyhanna, Pennsylvania. The contractor must assess the current racking system, select suitable replacement racking, completely remove the old racking and associated concrete bumpers, and install new racking following a provided CAD layout. The work involves two primary phases: Phase I includes demolition, disassembly of existing metal racking, obstruction removal, floor restoration, metal recycling of scrap to the TYAD scrap collection building, and debris clearing. Phase II encompasses procurement and fabrication of new racking units, floor layout marking per CAD drawings with critical emphasis on maintaining the exact physical footprints of the first and last rows, installation of six rows of cantilever racking (Row 1 single-sided at 150 feet long and 20 feet high; Rows 2-5 double-sided at 150 feet long and 20 feet high; Row 6 double-sided at 150 feet long and 20 feet high), and final cleanup of all packaging and debris.
The contractor must deliver fabricated equipment and components within six months of contract award and provide a minimum one-year parts and labor warranty beginning on the official date of delivery acceptance. The contractor is responsible for furnishing all personnel, equipment, supplies, tools, materials, transportation, and supervision, including providing their own dumpster for waste management and arranging off-base disposal at their expense. Key performance requirements include submission of a Quality Control Plan within 10 days of award, a Work Plan within 7 days of award, identification badges for all personnel, contractor identification signage, key control procedures, and compliance with Tobyhanna Army Depot's security, safety, and environmental requirements. The contractor must operate during facility office hours (0700-1700 Monday-Friday) and maintain an adequate workforce for uninterrupted performance. Required training includes DoD IA Cyber Awareness Training within 30 days of start, Anti-Terrorism Level I Training, OPSEC Training, and iWATCH Training. The contractor must report all labor hours via the System for Award Management (SAM) Service Contract Report no later than October 31 of each calendar year.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (Includes associated Performance Requirements Summary (PRS)
PERFORMANCE WORK STATEMENT (PWS)
6-1 Racking Removal and Replacement 02/05/2026
Part 1 General Information
1. General: This is a non-personal service contract to replace the old/damaged racking in 6-1.The government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the contractor who, in turn, is responsible to the government.
1.1 Description of Services/Introduction: The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to design and fabricate the requested items
1.2 Background: Tobyhanna Army Depot’s (TYAD) 6-1 racking is an important part of the Depot’s total ability to meet production goals. This contract is necessary to ensure that 6-1 is able to store the needed capacity of items safely.
1.3 Scope: Contractor will remove the current racking and install new racking. This will be performaned as described in the PWS.
1.4 Objectives: The objective of this contract to provide the following:
· Remove the Current racking
· Purchase and deliver new racking to 6-1
· Install new racking
1.5 General Information:
1.5.1 Quality Control Plan (QCP): The contractor’s existing quality assurance system shall be utilized in accordance with FAR 12.208. The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with (IAW) this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor's QCP is the means by which it assures that the work provided complies with the requirements of the contract.
The Contractor’s Proposed QCP shall be submitted to the Contracting Officer (KO) through the Contracting Officer’s Representative (COR) for review within ten (10) days after date of contract award
The Government will review and either notify the Contractor in writing of acceptance of the plan or return their comments to the Contractor within 10 days. If the Government has provided comments, the Contractor shall then have 10 days to submit a Final QCP. After receipt of the Final QCP, the Contractor may receive the Contracting Officer’s acceptance in writing. Any proposed changes to the accepted QCP are required to be resubmitted for acceptance by the Contracting Officer no later than 10 Days prior to the anticipated change and before implementation by the Contractor. The timeline noted above will apply for review and acceptance for proposed changes. At a minimum, the QCP must include and answer the following to be acceptable:
(a) A chart showing the organizational structure and lines of authority, the names, qualifications, duties, responsibilities, and classification of each member of the Contractor's Quality Control Team;
(b) How the Contractor will monitor work to ensure performance complies with all deliverables (etc. timelines, deadlines, and goals);
(c) How the Contractor will monitor work to ensure performance complies with all specifications and requirements of the contract, including the contract’s clauses;
(d) How the Contractor will monitor and ensure staff qualifications remain current and valid including Department of Defense (DoD) Contractor Personnel Office (DOCPER) processes/approvals throughout contract performance;
(e) How the Contractor will ensure all keys issued will remain controlled items (Paragraph 1.7 Key Control);
(f) How the Contractor will inventory and track maintenance of all Government Provided Equipment / Materials;
(g) How the Contractor will identify, investigate, and correct any non-conforming performance and prevent similar deficiencies in the future; and
(h) How the Contractor will file and save all Quality Control related documents for the life of the contract plus 5 years.
1.5.1.1 The Contractor shall inform the COR of issues or potential issues that might affect the performance within 3 hours of identifying those issues. Verbal reports shall be followed up by written reports within 7 days
1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.) deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.
1.5.3.1 U.S. Holidays: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer. When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
| New Year’s Day January 1st | M. L. King Memorial Day 3rd Monday in Jan | |
| Presidents Day 3rd Monday in February | Memorial Day last Monday in May |
Juneteenth June 19th Independence Day July 4th Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th
1.5.3.2 Host Nation Holidays: NA
1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.4.1 Government Facility Office Hours: The Government facility office hours are open 0700 to 1700, on days Monday through Friday, except U.S. Holidays identified in paragraph 1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.4.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 0600 to 1800, days Monday through Saturday. The Government facility is open for operations during the recognized U.S. Holidays identified in paragraph 1.5.3.1 above. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the Contracting Officer to the Contractor.
1.5.4.3 Contractor Support Hours: The Contractor shall provide support between the hours of 0700 to 1700, days Monday through Friday.e The Government facility is open for operations during the recognized U.S. Holidays identified in paragraph 1.5.3.1 above. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the Contracting Officer to the Contractor. The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.
1.5.4.3.1 Contractor Work Plan: The Contractor shall prepare and maintain a Work Plan. The plan, as a minimum, shall identify regularly scheduled work (to include location, work to be completed, timeline, etc.). If the need for overtime is anticipated, the Contractor must receive approval from the Contracting Officer at a minimum seven (7) calendar days prior to execution. The Contractor’s proposed Work Plan shall be submitted to the Contracting Officer via the COR for review within 7 days after date of contract award. The Government will review and either accept or return their comments to the Contractor within 10 days. The Contractor shall then have 3 days to submit a Final Work Plan. Any proposed change to the accepted Final Work Plan is required to be resubmitted via the COR for review and acceptance by the Contracting Officer at a minimum thirty (30) days prior to implementation. The timeline noted above shall apply for review and acceptance for proposed changes.
1.5.5 Training Holidays: Tobyhanna Army Depot has historically granted military personnel training holidays as compensation for time that they spent in field training. These are typically combined with regular holiday leave schedules (for example, Christmas half days or day on day off schedules). Training holidays may affect access to military operated facilities. If scheduled work or access to facilities is required, coordination with occupants will be necessary or the work in affected facilities shall be rescheduled after the training holiday. However, announced training holidays or exodus of military personnel may provide the Contractor with an opportunity for unrestricted access to facilities and areas. The Contractor shall take full advantage of such opportunities by planning maintenance or actions that are better accomplished when such areas are vacant.
1.5.6 Place of Performance: The work to be performed under this contract will be performed in Building IOF Plating Shop, Tobyhanna, PA.
1.6 Security Requirements: Please reference Attachment C for information on Tobyhanna Army Depot’s security requirements.
1.7 Key Control: The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. The Contractor shall develop procedures covering key control that shall be included in the Contractor’s Security Plan and the Quality Control Plan. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas. The Contractor shall immediately report any incidents of lost or duplicate keys to the Contracting Officer. In the event keys, other than master keys, are lost or duplicated, the Contractor shall, upon direction of the Contracting Officer, re-key or replace the affected lock or locks; however, the Government, at its option, may replace the affected lock or locks or perform re-keying. When the replacement of locks or re-keying is performed by the Government, the total cost of re-keying or the replacement of the lock or locks shall be deducted from payment due to the Contractor. In the event a master key is lost or duplicated, all locks and keys for that system shall be replaced by the Government and the total cost deducted from the payment due to the Contractor. The Contractor shall prohibit the use of Government issued keys by any persons other than the Contractor’s employees. The Contractor shall prohibit the opening of locked areas by Contractor employees to permit entrance of persons other than Contractor employees engaged in the performance of assigned work in those areas, or personnel authorized entrance by the Contracting Officer. The Contractor shall establish and implement methods of ensuring that all lock combinations are not revealed to unauthorized persons. The Contractor shall ensure that lock combinations are changed when personnel having access to the combinations no longer have a need to know such combinations. These procedures shall be included in the Quality Control Plan.
1.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.8.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter. Meetings may start or end outside of regular duty hours.
1.9 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.10 Key Personnel: The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 7:00 a.m. to 4:30p.m., Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons
1.11 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.12.1 Contractor workspace (staging site, on-site office, desk or work area, etc.) shall contain a sign signifying the space is occupied by Contractor employee(s) to ensure that Government employees and the public know that they are not Government employees. The proposed sign shall be submitted to the Contracting Officer via the COR for review and acceptance within 10 calendar days after contract award. Workspace sign location shall be coordinated with the COR. Contractor employees shall identify themselves by name and company affiliation when answering the telephone, presenting briefings, conducting or attending meetings, and seminars. All Contractor correspondence (written, facsimile, and email display) shall include their company name. Requirements for Contractor vehicles is addressed under Part 4 paragraph 4.4.
1.12.2 Contractor Identification Badges: Contractor personnel shall be easily identifiable through the display of badges IAW Contractor Identification (AE Reg. 27-715). (For services at Child, Youth, and School Services where children are present, recommend personnel wear identification when children are present.) Contractor and sub contractor personell will be provided a with some form of identification with that will show that the they are allowed on base. Personell must have provided identification on display on their person at all times in a way that can be clearly seen. Companies with U.S. Government contracts will require their employees to wear these badges visibly when performing work at Government workplaces unless this would be impractical because of mission or safety considerations. The Contractor shall collect all ID Badges upon completion of the contract or termination of employee. A listing of issued ID cards shall be furnished to the Contracting Officer prior to the contract performance date and updated as needed to reflect Contractor personnel changes
1.13 Contractor Travel: The Contractor may be authorized travel expenses at rates no higher than the substantive provisions of the Joint Travel Regulation (JTR), IAW FAR Part 31.205-46, and the limitation of funds specified in this contract. All travel requires Government approval and authorization 10 days prior to scheduled travel.
1.14 Other Direct Costs (ODCs): Inclusion of ODCs must be preapproved by the Contracting Officer. This category includes travel (outlined in 1.13), printing and shipping expenses associated with training activities and visits to Contractor facilities, this could also entail the renting of suitable training venues. Inclusion of ODCs in this PWS must be preapproved by the Contracting Office, if there is uncertainty as to what counts as a ODCs consult the COR.
1.15 Data Rights: The Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.16 Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. The Contractor and Contractor personnel, shall not divulge or release data or information developed, or obtained under performance of this PWS, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.
1.17 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/ , the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.
1.18 Non-Disclosure Statements: NA
1.19 Organizational Conflict of Interest (OCI): Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCI as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s OCI Mitigation Plan will be determined to be acceptable solely at the discretion of the Contracting Officer. In the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.20 Phase In /Phase Out Period: NA
1.21 Safety: Please reference Attachment A for information on Tobyhanna Army Depot’s safety requirements.
1.22 Environmental Compliance: Please reference Attachment B for information on Tobyhanna Army Depot’s environmental compliance requirements.
1.23 Required Training: The following provides information on training requirements.
1.23.1 Anti-Terrorism (AT) Level I Training: Please reference Attachment C for information on the training and Tobyhanna Army Depot’s security requirements.
1.23.2 OPSEC Training: Please reference Attachment C for information on the training and Tobyhanna Army Depot’s security requirements.
1.23.3 iWATCH Training: Please reference Attachment C for information on the training and Tobyhanna Army Depot’s security requirements.
1.23.4 Information Assurance (IA) Training
1.23.4.1 All Contractor employees, including subcontractors, requiring access to Government information systems shall complete the DoD IA Cyber Awareness Training within 30 days after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, or 15 days after employment of new personnel. Verification of the training shall be provided to the COR within 5 days after completion of the training.
1.23.4.2 All Contractor employees, including subcontractors, working information technology (IT)/IA functions shall comply with DoD and Army training requirements per Information Assurance Training Certification and Workforce Management DoD Directive (DoDD) 8570.01, Information Assurance Workforce Improvement Program DoD 8570.01-M, and Information Assurance AR 25-2 within thirty (30) calendar days of employment. Training is available at https://ia.signal.army.mil/DoDIAA/default.asp .
1.23.4.3 All Contractor employees, including subcontractors, performing services under this contract with access to a Government information system must be registered in the Army Training Certification Tracking System (ATCTS), the web address is p (requires CAC to access. Verification of registration shall be provided to the COR within 5 days after registration. Contractor personnel must complete refresher training every twelve (12) months. Verification of the training shall be provided to the COR within 5 days after completion of the training.
1.23.5 Personally Identifiable Information (PII): NA
1.24 Authorization to Perform Services in Germany: NA
1.25 Notice to Proceed: NA
1.26 Electromagnetic Compatibility Directive: NA
1.27 Government Property and Services: NA
1.28 Conventional Forces Europe (CFE) Treaty Verification Inspection: NA
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.
Contracting Officer – means a person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”
Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
Contractor-acquired Property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract and to which the Government has title.
Day – means, unless otherwise specified, a calendar day.
Defective Service – means a service output that does not meet the standard of performance associated with the Performance Work Statement.
Deliverable – means anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
Government-furnished Property – As reflected in FAR 52.245-1, Government-furnished Property “means property in the possession of, or directly acquired by, the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes contractor-acquired property if the contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract
Government Property - means all property owned or leased by the Government.Government property includes both Government-furnishedand Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.
Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.
High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.
Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.
Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.
Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
Work Day - The number of hours per day the Contractor provides services in accordance with the contract.
Work Week - Monday through Friday, unless otherwise specified.
2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.
| ACOR | Alternate Contracting Officer's Representative | |
| AE | Army in Europe | |
| AFARS | Army Federal Acquisition Regulation Supplement | |
| AHA | Activity Hazard Analysis | |
| AOR | Area of Responsibility | |
| AR | Army Regulation | |
| AT | Anti-terrorism | |
| ATCTS | Army Training Certification Tracking System | |
| CAC | Common Access Card | |
| CCE | Contracting Center of Excellence | |
| CFE | Conventional Forces Europe | |
| CFR | Code of Federal Regulations | |
| CONUS | Continental United States (excludes Alaska and Hawaii) | |
| COR | Contracting Officer’s Representative | |
| COTS | Commercial-Off-the-Shelf | |
| DA | Department of the Army | |
| DD250 | Department of Defense Form 250 (Receiving Report) | |
| DD254 | Department of Defense Contract Security Requirement List | |
| DFARS | Defense Federal Acquisition Regulation Supplement | |
| DMDC | Defense Manpower Data Center | |
| DoD | Department of Defense | |
| FAR | Federal Acquisition Regulation | |
| FRG | Federal Republic of Germany | |
| GFP | Government Furnished Property | |
| HLO | High Level Objective | |
| HIPAA | Health Insurance Portability and Accountability Act of 1996 | |
| IA | Information Awareness | |
| IAC | Installation Access Control | |
| IACO | Installation Access Control Office | |
| ID | Identification | |
| IGCE | Independent Government Cost Estimate | |
| IT | Information Technology | |
| JTR | Joint Travel Regulation | |
| JPAS | Joint Personnel Adjudication System | |
| KO | Contracting Officer | |
| OCI | Organizational Conflict of Interest | |
| OCONUS | Outside Continental United States (includes Alaska and Hawaii) | |
| ODC | Other Direct Costs | |
| OPSEC | Operations Security | |
| PA | Property Administrator | |
| PII | Personally Identifiable Information | |
| PIPO | Phase In/Phase Out | |
| POC | Point of Contact | |
| PRS | Performance Requirements Summary | |
| PWS | Performance Work Statement | |
| QA | Quality Assurance | |
| QAP | Quality Assurance Program | |
| QASP | Quality Assurance Surveillance Plan | |
| QC | Quality Control | |
| QCP | Quality Control Program | |
| RA | Requiring Activity | |
| RCO | Regional Contracting Office | |
| SIGE | Safety and Health Protection Plan | |
| TE | Technical Exhibit | |
| TYAD | Tobyhanna Army Depot |
USAG United States Army Garrison
| USAREUR | United States Army Europe | |
| UOM | Unit of Measure |
PART 3
GOVERNMENT PROPERTY (GP) AND SERVICES
3. Government Property and Services
3.1 Services: The Government will provide guidance as needed to assist in the removal and installation of a racking.
3.2 Facilities: NA
3.3 Utilities: The Government will provide access to water and electric outlets to assist with the process of maintenance. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves, light switches, etc. after using the required amount to accomplish tasks requiring the use of the utilities.
3.4 Equipment: NA
3.5 Special Tooling and Test Equipment: NA
3.6 Materials: NA
3.7 Training: NA
3.8 Common Access Cards (CAC): The Government will provide Common Access Cards (CAC) via the Trusted Associate Sponsorship System (TASS) (Web site https://www.dmdc.osd.mil/tass/ ).
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Property and Services
4.1 General: The Contractor shall furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform services as described in the PWS and associated contract documents, except for those items specified in Part 3 Government Property and Services
4.2 Secret Facility Clearance: N/A
4.3 Materials: N/A
4.4 Vehicles and Equipment: N/A
4.5 Background Checks): The Contractor shall provide Background Checks in accordance with this PWS and as determined by the Government.
PART 5
SPECIFIC TASKS
5.1 Basic Services: The Contractor shall assess the current racking, choose a suitable replacement of the racking, and then remove the old racking and install new racking in building 6-1 Tobyhanna Army Depot, Tobyhanna, PA. The Government shall not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
5.2 Tasks:
Tobyhanna Army Depot (TYAD) requires the complete removal, disposal, and replacement of outdated warehouse racking within building 6-1. The current racking system is obsolete and presents maneuverability hazards for 6-1 personnel due to the narrow aisles. To Resolve our issues with the aisles spacing we have created a new layout that removes one row of racking and distributes the extra space to the remaining aisles. Due to the possibility of hitting overhead hazards while moving inventory we cannot increase the total area the racks cover. We ask that the contractor follows the drawing “BLDG_6-1 Racking Updated.pdf” as closely as possible while prioritizing that the distance between the first and last row is the exact same as the current racks.
5.2.1 Technical Specifications & Layout
The contractor must reference the attached document "Racking storage OldvNew.pdf" to determine the exact number of storage levels required for each specific row.
| Parameter |
| Row 1 (Single-Sided) |
| Rows 2 through 5 (Double-Sided) |
| Row 6 (Double-Sided) |
| Row Length |
| 150 feet |
| 150 feet |
| 150 feet |
| Height |
| 20 feet |
| 20 feet |
| 20 feet |
| Arm Configuration |
| Single-sided cantilever arms |
| Double-sided cantilever arms |
| Double-sided cantilever arms |
| Arm Length |
| Approximately 4 feet |
| Approximately 4 feet (per side) |
| Approximately 2 feet (per side) |
| Arm Load Capacity |
| 4,000 lbs. (per arm) |
| 4,000 lbs. (per arm) |
| 2,000 lbs. (per arm) |
| Decking Requirement |
| Wire mesh deck (4,000 lbs. capacity) |
| Wire mesh deck (4,000 lbs. capacity) |
| None Required |
| Vertical Levels |
| See "Racking storage OldvNew.pdf" |
| See "Racking storage OldvNew.pdf" |
| See "Racking storage OldvNew.pdf" |
The contractor is responsible for executing the project in two primary phases: Demolition/Prep and Procurement/Installation.
5.2.2 Phase I: Removal and Site Preparation
| Task |
| Description |
| Demolition |
| Uninstall and completely disassemble all existing metal racking. |
| Obstruction Removal |
| Remove existing concrete bumpers located at the ends of the aisles. |
| Floor Restoration |
| Repair the concrete floor where bumpers were removed, filling anchor holes and patching any damage sustained during disassembly. |
| Metal Recycling |
| Transport all decommissioned metal racking scrap to the designated TYAD scrap collection building. |
| Debris Clearing |
| Remove all remaining trash and project debris to establish a clean slate for the new installation. |
5.2.3 Phase II: Procurement and Installation
| Task |
| Description |
| Logistics |
| Procure, fabricate, and transport all new racking units and hardware to TYAD. |
| Layout & Spacing (CRITICAL) |
| Mark the floor layout referencing the provided CAD drawing. Because real-world conditions may vary slightly from the drawing, the first row (Row 1, single-sided) and the last row (Row 6, double-sided) must be installed in the exact physical footprints of the previous first and last rows. |
| Interior Row Spacing |
| Distribute the remaining four (4) double-sided interior rows (Rows 2–5) to maximize aisle space as depicted in the CAD drawing, ensuring clearance from the overhead emergency water pipe is maintained. |
| Installation |
| Erect and securely anchor the new racking system in accordance with manufacturer specifications and the provided design attachments. |
| Final Clean-up |
| Remove and properly dispose of all packaging, shipping materials, and installation debris. |
5.2.4 Logistics, Equipment, and Warranty
| Provision |
| Details |
| Government Furnished Property |
| No material, tools, or vehicles (e.g., forklifts, lifts) will be provided by the Government. |
| Waste Management |
| The contractor must provide their own dumpster. Scrap metal must be transported to the TYAD scrap collection building; all other trash/debris must be disposed of off-base at the contractor's expense. |
| Delivery Timeline |
| Fabricated equipment and components must be delivered within six (6) months of contract award. |
| Delivery Address |
| Tobyhanna Army Depot11 Hap Arnold Blvd.Tobyhanna, PA 18466Bldg. IOF Plating Shop |
| Warranty |
| Minimum one (1) year parts and labor warranty, beginning on the official date of delivery acceptance. |
5.3 Service Contract Reporting:
5.3.1 System for Award Management (SAM) Service Contract Report (SCR): The Contractor shall report ALL Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the via a secure data collection site. The Contractor is required to completely fill in all required data fields through the following web address: www.sam.gov. Reporting inputs will be for the labor executed during the period of performance during each Government FY, which runs from October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk by clicking “View Assistance for SAM.gov” which is located at the top of the SAM.gov website. From there, you can the select “Contact Our Service Desk” which will allow you to contact SAM.gov directly. If contract period of performance ends prior to September 30, the Contractor has 30 calendar days from end date of the contract to complete the SAM SCR requirement.
Steps for Submitting a Service Contract Report (SCR)
1. Go to www.sam.gov and log in.
2. Select Entity Registrations and then select Service Contract Reporting.
3. SAM displays your entities which have service contracts and meet the reporting criteria. Select View by entity to see the service contracts for each entity.
4. Next, select Add for the service contract against which you want to create a Service Contract Report. Each service contract which meets the FAR Subpart 4.1703 reporting thresholds is displayed.
5. You will be taken to the Complete Service Contract Report page. SAM displays the contract details and allows you to report. You are required to enter the following information:
· Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous Government fiscal year under the contract (this amount should include the prime and any subcontract amount).
· Prime Contractor Hours Expended: Prime contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 hours to calculate a Full Time Employee (FTE) equivalent, displayed under the Prime Contractor Hours Expended as Prime Contractor FTEs.
6. Report any required Tier 1 subcontractor information by selecting the Add Tier 1 Subcontract Information button.
7. When you are ready to submit the report, select Submit. This saves your report and returns you to the Select Service Contract page where you can create other SCRs or edit an existing SCR.
Steps for Editing a Submitted Report
1. Follow steps 1-4 above. Any previously submitted SCR will have a View/Edit button instead of an Add button.
2. Select View/Edit. You will be able to view the current SCR, edit available fields, and resubmit the record. You can also delete previously entered information altogether.
STD: All information provided by the Contractor shall be accurate, complete, and not exceed suspense dates noted in corresponding paragraph above.
AQL: 100% Compliant
PART 6
APPLICABLE PUBLICATIONS
6. Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.
| 6.1.1 | Department Of Defense Contract Security Classification Specification (DD Form 254) |
| 6.1.2 | Department of Defense Security Agreement (DD Form 441) |
| 6.1.3 | National Industrial Security Program Operating Manual (DoD 5220.22-M) |
| 6.1.4 | Installation Access Control (AE Reg 190-16) |
| 6.1.5 | The Army Physical Security Program (AR 190-13) |
| 6.1.6 | Contractor Identification (AE Reg 27-715) |
| 6.1.7 | U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1) |
| 6.1.8 | Information Assurance Workforce Improvement Program (DoD 8570-M) |
| 6.1.9 | Information Assurance Training Certification and Workforce Management Directive (DoDD 8570.01) |
| 6.1.10 | Information Assurance (AR 25-2) |
| 6.1.11 | Electromagnetic Compatibility Directive (2004/108/EC) |
| 6.1.12 | Policies and Procedures for Property Accountability (AR 735-5) |
PART 7
ATTACHMENT AND TECHNICAL EXHIBIT LISTING
7. Attachment and Technical Exhibit List
7.1 Attachment A - SERVICE OR EQUIPMENT INSTALLATION CONTRACTOR SAFETY STANDARD MARCH 2024
7.2 Attachment B - TYAD Environmental
7.3 Attachment C - TYAD Security Requirements
AUG 22
File details come from the government source that posted it. Updated .