Deliverable Time Line Rectifier Control Upgrade.pdf

PDF 342 KB Posted

Attached to
Replacement Rectifier Federal contract opportunity
Solicitation number
W519TC24Q2353
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

This document is a timeline of deliverables for a contract to upgrade the rectifier and controls on Tank 127 at Rock Island Arsenal. The timeline outlines key events and milestones, including equipment delivery within 60 days of contract award, delivery of manuals within 30 days, equipment installation within 90 days, and operator/maintenance training within 105 days. The final acceptance is scheduled for 135 days after contract award.

The related federal contract opportunity is a solicitation (W519TC24Q2353) for the replacement of a rectifier at Rock Island Arsenal, to be awarded as a firm fixed price (FFP) purchase order using Lowest Price Technically Acceptable (LPTA) source selection procedures. Quotes are due by 6 PM on August 21st, 2024, with payment to be made via Wide Area Work Flow (WAWF). The contracting agency is the Department of the Army Materiel Command Contracting Command Rock Island Arsenal.

View the file

Other files for this federal contract opportunity

Other files attached to Replacement Rectifier, newest first.
File Type Posted
RIPD E4000-24-3-24 - B212 Rectifier Controls Replace Upgrade Chrome Tank 127.pdf PDF
24-3-24 CDRL - Bld 212 Plating Replacement Rectifier Tank 127.pdf PDF
24-Q-2353 Solicitation.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCK ISLAND ARSENAL DATE: 21 June 2024

PROJECT: RIPD E4000-24-3-24

TIMELINE OF DELIVERIES

TANK 127 RECTIFIER & CONTROLS UPGRADE

The following proposed timeline for Project RIPD E4000-23-9-48 is based upon the contract award date and the number of calendar days between events. Time allocations are maximums for each stage. It is acceptable to complete a stage in fewer days than shown on the timeline and move on to the next stage.

The timeline for this project is as follows:

Contract Award Contract Award Equipment Delivery Contract Award + 60 Days Manuals Contract Award + 30 Days Equipment Installation Contract Award + 90 Days Training (Operator, Maintenance) Contract Award + 105 Days Final Acceptance Contract Award + 135 Days

Total Maximum Time from Award to Acceptance Contract Award + 135-days

Metallographic Cut Saw for Lab in support of AM