W519TC-25-R-A012.pdf
PDF 6 MB Posted
- Attached to
- Repair King Drive - Grade and Pave
- Solicitation number
- W519TC25RA012
About this file
This is a Request for Proposal (RFP) for a construction project to regrade and pave King Drive at the Rock Island Arsenal in Rock Island, Illinois. The U.S. Army Contracting Command - Rock Island is seeking a contractor to perform roadway improvements from the intersection of Rodman Avenue to approximately 1,855 feet west of the Blunt Road intersection. The project is a 100% small business set-aside with a fixed-price contract, and the work includes roadway construction, grading, paving, storm drainage installation, and relocating an existing fiber optic handhole.
Key project details include a 100-working day completion timeline with liquidated damages of $1,000 per working day for delays, and a mandatory site visit scheduled for July 2, 2025. The contract's estimated value is between $1,000,000 and $5,000,000, with the contractor required to submit three past performance references from similar projects completed within the last five years. Contractors must be registered in the System for Award Management (SAM) and will be evaluated on price and past performance, with the lowest-priced, technically acceptable offer expected to be selected.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section A - Solicitation/Contract Form
Repair King Drive - Grade and Pave
1. The United States Army Contracting Command - Rock Island (ACC-RI) requests a proposal on behalf of the United Stated Army Garrison - Rock Island Arsenal (USAG-RIA) consisting of furnishing labor, material and equipment to regrade and pave King Drive from the intersection of Rodman Avenue and ending approximately 1,855 feet west of the Blunt Road intersection on the Rock Island Arsenal, Rock Island, Illinois. All work is to be done in accordance with the Scope of Work (Attachment 0001) for project 2025-2923.
2. The project completion date for this project is 100 working days from the date of the Notice to Proceed. See Section 1.3 of the Scope of work below:
The Base Bid consists of providing all labor, equipment and materials to construct the King Drive roadway corridor from the Rodman Avenue to approximately 1,855 feet west of the Blunt Road intersection. Work includes, but is not limited to construction of the roadway, grading, paving and removing and installing new storm, and relocating an existing fiber optic handhole as identified in the attached plan set in Appendix A.
This project shall be a working day contract. The contractor is allowed 100 working days to complete the project. The definition of a working day is defined in the SUDAS Specifications 1080. Failure in completing the project in the allotted 100 working days will result in a deduction at the liquidated damages rate of $1,000.00 (one thousand dollars) per working day until the project is completed.
3. This requirement will be competed as a 100% Small Business Set Aside.
4. The North American Industry Classification System (NAICS) code is 237310; Highway, Street, and Bridge Construction. The Product Service Code (PCS) is Z2LB, Repair or Alteration of Highways/Roads/Streets/Bridges/Railways.
5. All Offerors MUST be registered in the System for Award Management (SAM) database in accordance with FAR 52.204-7 and Defense Federal Acquisition Regulation Supplement (DFARS) 252.204-7004 when submitting an offer, and shall continue to be registered until time of award, during performance, and through final payment of any contract resulting from this solicitation. Lack of registration in SAM will make an Offeror ineligible for award. Contractors may obtain information on registration and annual confirmation requirements via the SAM website at https://www.sam.gov /SAM/ or by calling 866-606-8220.
6. The Government will award a single Firm-Fixed Price (FFP) and Time-and-Materials (T&M) type contract from this solicitation to the responsive, responsible Offeror with lowest price and an acceptable past performance rating as outlined in paragraph 7. This Request for Proposal (RFP) contains three contract line-item numbers. CLIN 0001 which represents one firm-fixed price base bid and CLIN 0002 and 0003 which represent T&M excavation. The contractor shall provide a bid on all line items, including unit pricing.
7. The contractor shall submit a total of three past performance references for similar projects that are within the last five years and may include subcontractor references.
a. Each reference shall include the information bulleted below:
- Contracting agency/company and technical points of contact with their phone numbers, electronic-mail addresses, and titles.
- Contract number and delivery/task order number, as applicable.
- The original contract award date (for the base period of performance) and the completion (or estimated completion) date (shall reflect all option periods).
W519TC25RA012
- Contract value (value of each performance period shall be identified).
- Scope of work.
b. If applicable, the submittal in this section shall also list any contract or purchase order under which either a cure notice or show cause letter was received, or any contractor purchase order that was terminated for cause by the Government within the past three years. The contractor must briefly explain the facts and circumstances in each such instance.
c. The Government will evaluate past performance as acceptable/unacceptable. The Government will contact all contract references provided and conduct research into Government Databases on past performance (PPIRs, CPARs, etc.) to determine past performance to be relevant and recent and to determine that past performance to be acceptable.
- Relevant past performance efforts involve similar scope and magnitude of effort and complexities this RFP requires.
- Recent past performance is within the past 5 years.
Past Performance Acceptable/Unacceptable Rating Method is as follows:
Adjectiv al Rating
Description
Accepta ble
Based on the offeror's performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror's performance record is unknown (See note below).
Unaccep table
Based on the offeror's performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.
In the case of an offeror without a record of recent/relevant past performance no meaningful confidence assessment rating can be reasonably assigned.
The Offeror will be given an acceptable rating.
8. The Government anticipates price competition; therefore, certified cost or pricing data is not required to be submitted with the Offeror's proposal. However, the Government reserves the right to request certified cost or pricing data in the event price competition does not exist.
9. The Government will review prices to determine whether they are so low that they reflect a lack of technical understanding which could result in the proposal not being considered for award.
10. A Notice to Proceed (NTP) will be issued at the Pre-Construction conference, which will be scheduled after the approval of Performance and Payment Bonds. The awardee shall prepare and submit a practicable schedule and Quality Control Plan (QCP) to the Contracting Officer for approval within 15 days after the NTP. The remaining pre-submittals are due within 30 days after issuance of the NTP, with commencement of physical work to begin 45 days after NTP. Per allowance provided within FAR Clause 52.236-15,titled "Schedules for Construction Contracts (APR 1984)", the Contracting Officer has authorized a revision to paragraph (a) of the clause. FAR clause 52.236-15 as revised is included in its entirety below.
52.236-15 SCHEDULES for CONSTRUCTION CONTRACTS (APR 1984)
(a) The Contractor shall, within 15 days after issuance of the notice to proceed, submit three copies of a practicable schedule to the Contracting Officer and Contracting Officer Representative for approval. The schedule shall show the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified within the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
11. Contractor shall obtain all licenses and certifications required by Federal, State, and Local environmental laws and regulations necessary to adhere to the specifications of this contract. The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority and/or agency as necessary to adhere to the specifications of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws and/or regulations shall be considered a contract deliverable upon award. See FAR Clause 52.236-7.
12. Contractor shall adhere to FAR 52.219-14, Limitations on Subcontracting. Please see the full text clause incorporated in this solicitation for further details.
13. The Government reserves the right to reject any or all proposals and make no award if such action is in the best interest of the Government.
14. There will be a site visit held on Wednesday, July 2, 2025 at 9:00 a.m. CST to ensure all contractors have a clear understanding of the site and scope of work. Please see Attachment 0007, King Drive Project Site Visit Location for the site visit attendee meeting location.
******PLEASE READ CAREFULLY FOR IMPORTANT SITE VISIT INFORMATION
ALL ATTENDEES MUST ACCESS THE ISLAND THROUGH THE MOLINE GATE AND STOP AT BUILDING 23, VISITOR CONTROL CENTER, TO GAIN ACCESS TO THE ISLAND UNLESS YOU HAVE AN EXISTING BADGE TO GAIN ACCESS. YOU WILL NEED TO SHOW A VALID DRIVERS LICENSE. PLEASE ALLOW 60 MINUTES PRIOR TO THE SITE VISIT FOR PROCESSING.
MANDATORY REGISTRATION - PLEASE EMAIL THE NAMES OF THE ATTENDEES FROM YOUR COMPANY TO lindsay.p.park.
civ@army.mil.
15. Offerors are cautioned to ensure their proposals are fully complete, including fill-ins and blanks in the solicitation. Any Offeror submitting a proposal agrees by submission that their proposal and the prices contained therein will be valid for 60 days after receipt of final proposals.
16. This solicitation is subject to availability of funds; therefore this solicitation is currently unfunded. The Government reserves the right to not fund any work listed in the solicitation. See FAR clause 52.232-18.
17. Offerors should note the provision at FAR 52.215-1, titled "Instructions to Offerors - Competitive Acquisition". The Government intends to award a contract resulting from this solicitation without discussions with Offerors (except clarifications described in FAR 15.306(a)). Therefore, Offeror's initial proposals should contain the best terms. The Government does however, reserve the right to conduct discussions if determined necessary by the Contracting Officer.
18. The prevailing Wage Rate Requirements (Construction) will be incorporated into the resultant contract and will be in effect for the entire period of performance of the resultant contract. The most recent wage rates can be found online at: www.sam.gov or see Attachment 0006, Davis Bacon Wage Determination of this solicitation.
19. Contractor questions regarding this solicitation and work contained within the SOW are due to the solicitation point of contact (POC) no later than 10:00 a.m. CST on Wednesday, July 9, 2025,in order to ensure all questions can be answered and posted for all Offerors' knowledge prior to solicitation closing date and time reflected in box 13 of this document. All questions should be directed in writing by email to Lindsay Park, lindsay.p.
park.civ@army.mil and Kathleen Ward at kathleen.m.ward20.civ@army.mil providing SOLICITATION number W519TC-25-R-A012 in the subject line.
20. Proposal submission deadline is listed in Block 13 of this solicitation. Proposal must be sent electronically to lindsay.p.park.civ@army.mil. No hard copies will be accepted.
- Offerors shall reference solicitation W519TC-25-R-A012 and company name in the proposal email subject line.
- In email body, please request receipt to confirm delivery.
- Our email system standard is an estimated limit of ten (10) megabytes per incoming email.
- Please be aware that large files may require extra time to be delivered into our email system. All proposal documents must be fully delivered into the email system and time-stamped by the Government server no later than the time shown in Block 13 of this document.
21. Contractor Bid Bonds are required to be submitted via electronic mail with the proposal to lindsay.p.park.civ@army.mil and kathleen.m.ward20.
civ@army.mil. If the seal is unrecognizable via electronic mail a request will be made to overnight the original bid bond so the seal can be verified.
22. This executive summary is provided as an administrative convenience and is not intended to alter the terms and conditions of the solicitation in any way. Any inconsistencies between this executive summary and other solicitation provisions shall be resolved in favor or the other solicitation provisions.
23. Clauses and provisions from the FAR and supplements thereto are incorporated into this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were included in full text.
24. This solicitation should not be discussed with any Government employee except the Contracting Officer, Ms. Kathleen Ward, or the Contract Specialist, Ms. Lindsay Park. Failure to adhere to this restriction may be grounds to declare your firm ineligible for consideration of any award resulting from this competitive acquisition.
25. The Government representative for this acquisition is Lindsay Park, lindsay.p.park.civ@army.mil. Comments or questions should be directed in writing to Lindsay Park by email, providing the solicitation number W519TC-25-R-A012 in the subject line.
Section B - Supplies or Services & Prices or Costs
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
Repair King Drive
Product Service Code: Z2LB Pricing Arrangement: Firm Fixed Price
1 Job
Excavation, Class 13, Roadway & Borrow, T&M
Product Service Code: Z2LB Pricing Arrangement: Time and Materials
1,915.3 Cubic Yard
Rock Excavation, T&M
Product Service Code: Z2LB Pricing Arrangement: Time and Materials
50 Cubic Yard
Section C - Description/Specifications/Statement of Work
Requirements This project consists of the regrading and paving of King Drive from the intersection of Rodman Avenue and ending approximately 1,855 feet west of the Blunt Road intersection, on the Rock Island Arsenal, Rock Island, Illinois.
Section E - Inspection and Acceptance
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.246-12 Inspection of Construction. Aug 1996 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements. Aug 1996
Overall Contract Inspection/Acceptance Locations
Inspection and Acceptance Location
Both Destination Instructions: Inspect/Accept address to be updated in system to Bldg 102, 1st Flr, West Wing, Rock Island, IL 61299-5000.
DoDAAC: W91QFD CountryCode: USA
W6B9 USAG ROCK ISLAND ARSENAL
BLDG 90 1ST FLOOR, 1 ROCK ISLAND ARSENAL
ROCK ISLAND, IL 61299-5000
UNITED STATES
Rodell Reed Email: rodell.l.reed.civ@army.mil Telephone: 3097820361
Inspection and Acceptance Location
Both Destination Instructions: Inspect/Accept address to be updated in system to Bldg 102, 1st Flr, West Wing, Rock Island, IL 61299-5000.
DoDAAC: W91QFD CountryCode: USA
W6B9 USAG ROCK ISLAND ARSENAL
BLDG 90 1ST FLOOR, 1 ROCK ISLAND ARSENAL
ROCK ISLAND, IL 61299-5000
UNITED STATES
Rodell Reed Email: rodell.l.reed.civ@army.mil Telephone: 3097820361
Inspection and Acceptance Location
Both Destination Instructions: Inspect/Accept address to be updated in system to Bldg 102, 1st Flr, West Wing, Rock Island, IL 61299-5000.
DoDAAC: W91QFD CountryCode: USA
W6B9 USAG ROCK ISLAND ARSENAL
BLDG 90 1ST FLOOR, 1 ROCK ISLAND ARSENAL
ROCK ISLAND, IL 61299-5000
UNITED STATES
Rodell Reed Email: rodell.l.reed.civ@army.mil Telephone: 3097820361
Section F - Deliveries or Performance
Overall Contract Delivery Period
From 08 Oct 2025 to 04 Mar 2026
From date of lead time event to beginning of performance 45 Calendar Days Date of Notice to Proceed Receipt
From date of lead time event to completion of performance 148 Calendar Days Date of Notice to Proceed Receipt
Line Item Delivery Schedule Quantity Address and POC
Period of Performance From 08 Oct 2025 To 04 Mar 2026
1 Job
Period of Performance From 08 Oct 2025 To 04 Mar 2026
1,915.3 Cubic Yard
Period of Performance From 08 Oct 2025 To 04 Mar 2026
50 Cubic Yard
Section G - Contract Administration Data
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.201-7000 Contracting Officer's Representative. Dec 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018 252.236-7000 Modification Proposals--Price Breakdown. Dec 1991
DFARS Clauses Incorporated by Full Text
252.232-7006 Wide Area WorkFlow Payment Instructions. (Jan 2023)
WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)
(a) As used in this clause- Definitions.
"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.
"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.
"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as Electronic invoicing.
authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) To access WAWF, the Contractor shall- WAWF access.
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.
(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice WAWF training.
Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/
(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer WAWF methods of document submission.
Protocol.
(f) The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF payment instructions.
WAWF for this contract or task or delivery order:
(1) The Contractor shall submit payment requests using the following document type(s): Document type.
(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.
(ii) For fixed price line items-
(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.
(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)
(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.
CONSTRUCTION
(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)
(iii) For customary progress payments based on costs incurred, submit a progress payment request.
(iv) For performance based payments, submit a performance based payment request.
(v) For commercial financing, submit a commercial financing request.
(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.
[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]
(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF Document routing.
when creating payment requests and receiving reports in the system.
Routing Data Table*
Field Name in WAWF Data to be entered in WAWF
Pay Official DoDAAC HQ0490
Issue By DoDAAC W519TC
Admin DoDAAC W519TC
Inspect By DoDAAC W91QFD
Service Approver (DoDAAC) W91QFD
Service Acceptor (DoDAAC) W91QFD
(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")
(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)
(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in Payment request.
accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.
(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.
(g) WAWF point of contact.
(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
rodell.l.reed.civ@army.mil, lindsay.p.park.civ@army.mil
(Contracting Officer: Insert applicable information or "Not applicable.")
(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.
(End of clause)
Section I - Contract Clauses
FAR Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
52.202-1 Definitions. Jun 2020 52.203-3 Gratuities. Apr 1984 52.203-5 Covenant Against Contingent Fees. May 2014 52.203-6 Restrictions on Subcontractor Sales to the Government. Jun 2020 52.203-7 Anti-Kickback Procedures. Jun 2020
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity.
May 2014
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. May 2014 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. Jun 2020
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.
Jan 2017
52.204-2 Security Requirements. (Alternate II) Mar 2021 Alternate II Apr 1984 52.204-9 Personal Identity Verification of Contractor Personnel. Jan 2011 52.204-13 System for Award Management Maintenance. Oct 2018 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities.
Dec 2023
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
Nov 2021
52.204-27 Prohibition on a ByteDance Covered Application. Jun 2023
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded
Jan 2025
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters. Oct 2018 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. Nov 2015 52.215-2 Audit and Records-Negotiation. Jun 2020 52.215-8 Order of Precedence-Uniform Contract Format. Oct 1997 52.219-6 Notice of Total Small Business Set-Aside. Nov 2020 52.222-3 Convict Labor. Jun 2003 52.222-4 Contract Work Hours and Safety Standards -Overtime Compensation. May 2018 52.222-6 Construction Wage Rate Requirements. Aug 2018 52.222-7 Withholding of Funds. May 2014 52.222-9 Apprentices and Trainees. (DEVIATION 2025-O0003) Jul 2005 Deviation 2025-O0003 Mar 2025 52.222-10 Compliance with Copeland Act Requirements. Feb 1988 52.222-11 Subcontracts (Labor Standards). May 2014 52.222-12 Contract Termination-Debarment. May 2014
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.
May 2014
52.222-14 Disputes Concerning Labor Standards. Feb 1988 52.222-15 Certification of Eligibility. May 2014 52.222-35 Equal Opportunity for Veterans. Jun 2020 52.222-36 Equal Opportunity for Workers with Disabilities. Jun 2020 52.222-37 Employment Reports on Veterans. Jun 2020 52.222-40 Notification of Employee Rights Under the National Labor Relations Act. Dec 2010 52.222-50 Combating Trafficking in Persons. Nov 2021 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. Jan 2022 52.222-62 Paid Sick Leave Under Executive Order 13706. Jan 2022 52.223-5 Pollution Prevention and Right-to-Know Information. May 2024 52.223-21 Foams. May 2024 52.223-23 Sustainable Products and Services. May 2024 52.225-13 Restrictions on Certain Foreign Purchases. Feb 2021 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving. May 2024 52.227-1 Authorization and Consent. Jun 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. Jun 2020 52.227-4 Patent Indemnity-Construction Contracts. Dec 2007 52.228-2 Additional Bond Security. Oct 1997 52.228-5 Insurance-Work on a Government Installation. Jan 1997 52.228-11 Individual Surety-Pledge of Assets. Feb 2021 52.228-12 Prospective Subcontractor Requests for Bonds. Dec 2022 52.228-14 Irrevocable Letter of Credit. Nov 2014 52.228-15 Performance and Payment Bonds-Construction. Jun 2020 52.229-3 Federal, State, and Local Taxes. Feb 2013 52.229-12 Tax on Certain Foreign Procurements. Feb 2021
52.232-8 Discounts for Prompt Payment. Feb 2002 52.232-18 Availability of Funds. Apr 1984 52.232-23 Assignment of Claims. May 2014 52.232-27 Prompt Payment for Construction Contracts. Jan 2017 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. Mar 2023 52.233-1 Disputes. May 2014 52.233-3 Protest after Award. Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004 52.236-2 Differing Site Conditions. Apr 1984 52.236-3 Site Investigation and Conditions Affecting the Work. Apr 1984 52.236-5 Material and Workmanship. Apr 1984 52.236-6 Superintendence by the Contractor. Apr 1984 52.236-7 Permits and Responsibilities. Nov 1991 52.236-8 Other Contracts. Apr 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
Apr 1984
52.236-10 Operations and Storage Areas. Apr 1984 52.236-11 Use and Possession Prior to Completion. Apr 1984 52.236-12 Cleaning Up. Apr 1984 52.236-13 Accident Prevention. Nov 1991 52.236-14 Availability and Use of Utility Services. Apr 1984 52.236-15 Schedules for Construction Contracts. Apr 1984 52.236-17 Layout of Work. Apr 1984 52.236-21 Specifications and Drawings for Construction. Feb 1997 52.236-26 Preconstruction Conference. Feb 1995
52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities.
Nov 2024
52.242-13 Bankruptcy. Jul 1995 52.242-14 Suspension of Work. Apr 1984 52.243-4 Changes. Jun 2007 52.243-5 Changes and Changed Conditions. Apr 1984 52.244-6 Subcontracts for Commercial Products and Commercial Services. Jan 2025 52.245-1 Government Property. Sep 2021 52.245-9 Use and Charges. Apr 2012 52.246-21 Warranty of Construction. Mar 1994 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form). Apr 1984 52.249-2 Termination for Convenience of the Government (Fixed-Price). (Alternate I) Apr 2012 Alternate I Sep 1996 52.249-10 Default (Fixed-Price Construction). Apr 1984
DFARS Clauses Incorporated by Reference
Number Title Effective Date
Alternate/ Deviation
Variation Effective Date
252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense-Contract-Related Felonies. Jan 2023 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Dec 2022 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. Jan 2023 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. May 2024
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.
Jan 2023
252.204-7020 NIST SP 800-171 DoD Assessment Requirements. Nov 2023
252.209-7004 Subcontracting with Firms that are Owned or Controlled by the Government of a Country that is a State Sponsor of Terrorism.
May 2019
252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium. Jan 2023 252.225-7001 Buy American and Balance of Payments Program. Feb 2024 252.225-7012 Preference for Certain Domestic Commodities. Apr 2022 252.225-7048 Export-Controlled Items. Jun 2013 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime. Jan 2023 252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. Jun 2023 252.227-7016 Rights in Bid or Proposal Information. Jan 2025 252.232-7010 Levies on Contract Payments. Dec 2006 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.243-7002 Requests for Equitable Adjustment. Dec 2022 252.244-7000 Subcontracts for Commercial Products or Commercial Services. Nov 2023 252.245-7003 Contractor Property Management System Administration Jan 2025 252.245-7005 Management and Reporting of Government Property. Jan 2024 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations. Oct 2010
252.247-7023 Transportation of Supplies by Sea. Oct 2024
FAR Clauses Incorporated by Full Text
52.204-1 Approval of Contract. (Dec 1989)
Approval of Contract (Dec 1989)
This contract is subject to the written approval of and shall not be binding until so approved.the contracting officer
(End of clause)
52.211-10 Commencement, Prosecution, and Completion of Work. (Apr 1984)
Commencement, Prosecution, and Completion of Work (Apr 1984)
The Contractor shall be required to (a) commence work under this contract within calendar days after the date the Contractor receives the notice to 45 proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than .* The time stated for 100 working days completion shall include final cleanup of the premises.
* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.
(End of clause)
52.211-12 Liquidated Damages-Construction. (Sep 2000)
Liquidated Damages-Construction (Sept 2000)
If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the (a) Government in the amount of for each calendar day of delay until the work is completed or accepted.$1,000
If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These (b) liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.216-7 Allowable Cost and Payment. (Aug 2018)
Allowable Cost and Payment (Aug 2018)
(a) Invoicing.
(1) The Government will make payments to the Contractor when requested as work progresses, but (except for small business concerns) not more often than once every 2 weeks, in amounts determined to be allowable by the Contracting Officer in accordance with Federal Acquisition Regulation (FAR) subpart 31.2 in effect on the date of this contract and the terms of this contract. The Contractor may submit to an authorized representative of the Contracting Officer, in such form and reasonable detail as the representative may require, an invoice or voucher supported by a statement of the claimed allowable cost for performing this contract.
(2) Contract financing payments are not subject to the interest penalty provisions of the Prompt Payment Act. Interim payments made prior to the final payment under the contract are contract financing payments, except interim payments if this contract contains Alternate I to the clause at 52.232-25.
(3) The designated payment office will make interim payments for contract financing on the ____[Contracting Officer insert day as prescribed by agency head; if not prescribed, insert "30th"] day after the designated billing office receives a proper payment request. In the event that the Government requires an audit or other review of a specific payment request to ensure compliance with the terms and conditions of the contract, the designated payment office is not compelled to make payment by the specified due date.
(b) Reimbursing costs.
(1) For the purpose of reimbursing allowable costs (except as provided in paragraph (b)(2) of this clause, with respect to pension, deferred profit sharing, and employee stock ownership plan contributions), the term "costs" includes only-
(i) Those recorded costs that, at the time of the request for reimbursement, the Contractor has paid by cash, check, or other form of actual payment for items or services purchased directly for the contract;
(ii) When the Contractor is not delinquent in paying costs of contract performance in the ordinary course of business, costs incurred, but not necessarily paid, for-
(A) Supplies and services purchased directly for the contract and associated financing payments to subcontractors, provided payments determined due will be made-
(1) In accordance with the terms and conditions of a subcontract or invoice; and
(2) Ordinarily within 30 days of the submission of the Contractor's payment request to the Government;
(B) Materials issued from the Contractor's inventory and placed in the production process for use on the contract;
(C) Direct labor;
(D) Direct travel;
(E) Other direct in-house costs; and
(F) Properly allocable and allowable indirect costs, as shown in the records maintained by the Contractor for purposes of obtaining reimbursement under Government contracts; and
(iii) The amount of financing payments that have been paid by cash, check, or other forms of payment to subcontractors.
(2) Accrued costs of Contractor contributions under employee pension plans shall be excluded until actually paid unless-
(i) The Contractor's practice is to make contributions to the retirement fund quarterly or more frequently; and
(ii) The contribution does not remain unpaid 30 days after the end of the applicable quarter or shorter payment period (any contribution remaining unpaid shall be excluded from the Contractor's indirect costs for payment purposes).
(3) Notwithstanding the audit and adjustment of invoices or vouchers under paragraph (g) of this clause, allowable indirect costs under this contract shall be obtained by applying indirect cost rates established in accordance with paragraph (d) of this clause.
(4) Any statements in specifications or other documents incorporated in this contract by reference designating performance of services or furnishing of materials at the Contractor's expense or at no cost to the Government shall be disregarded for purposes of cost-reimbursement under this clause.
(c) Small business concerns. A small business concern may receive more frequent payments than every 2 weeks.
(d) Final indirect cost rates.
(1) Final annual indirect cost rates and the appropriate bases shall be established in accordance with subpart 42.7 of the Federal Acquisition Regulation (FAR) in effect for the period covered by the indirect cost rate proposal.
(2)
(i) The Contractor shall submit an adequate final indirect cost rate proposal to the Contracting Officer (or cognizant Federal agency official) and auditor within the 6-month period following the expiration of each of its fiscal years. Reasonable extensions, for exceptional circumstances only, may be requested in writing by the Contractor and granted in writing by the Contracting Officer. The Contractor shall support its proposal with adequate supporting data.
(ii) The proposed rates shall be based on the Contractor's actual cost experience for that period. The appropriate Government representative and the Contractor shall establish the final indirect cost rates as promptly as practical after receipt of the Contractor's proposal.
(iii) An adequate indirect cost rate proposal shall include the following data unless otherwise specified by the cognizant Federal agency official:
(A) Summary of all claimed indirect expense rates, including pool, base, and calculated indirect rate.
(B) General and Administrative expenses (final indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts).
(C) Overhead expenses (final indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts) for each final indirect cost pool.
(D) Occupancy expenses (intermediate indirect cost pool). Schedule of claimed expenses by element of cost as identified in accounting records (Chart of Accounts) and expense reallocation to final indirect cost pools.
(E) Claimed allocation bases, by element of cost, used to distribute indirect costs.
(F) Facilities capital cost of money factors computation.
(G) Reconciliation of books of account (i.e., General Ledger) and claimed direct costs by major cost element.
(H) Schedule of direct costs by contract and subcontract and indirect expense applied at claimed rates, as well as a subsidiary schedule of Government participation percentages in each of the allocation base amounts.
(I) Schedule of cumulative direct and indirect costs claimed and billed by contract and subcontract.
(J) Subcontract information. Listing of subcontracts awarded to companies for which the contractor is the prime or upper-tier contractor (include prime and subcontract numbers; subcontract value and award type; amount claimed during the fiscal year; and the subcontractor name, address, and point of contact information).
(K) Summary of each time-and-materials and labor-hour contract information, including labor categories, labor rates, hours, and amounts; direct materials; other direct costs; and, indirect expense applied at claimed rates.
(L) Reconciliation of total payroll per IRS form 941 to total labor costs distribution.
(M) Listing of decisions/agreements/approvals and description of accounting/organizational changes.
(N) Certificate of final indirect costs (see 52.242-4, Certification of Final Indirect Costs).
(O) Contract closing information for contracts physically completed in this fiscal year (include contract number, period of performance, contract ceiling amounts, contract fee computations, level of effort, and indicate if the contract is ready to close).
(iv) The following supplemental information is not required to determine if a proposal is adequate, but may be required during the audit process:
(A) Comparative analysis of indirect expense pools detailed by account to prior fiscal year and budgetary data.
(B) General organizational information and limitation on allowability of compensation for certain contractor personnel. See 31.205-6(p). Additional salary reference information is available at https://www.whitehouse.gov/wp-content/uploads/2017/11 /ContractorCompensationCapContractsAwardedBeforeJune24.pdf and https://www.whitehouse.gov/wp-content/uploads/2017/11 /ContractorCompensationCapContractsAwardedafterJune24.pdf.
(C) Identification of prime contracts under which the contractor performs as a subcontractor.
(D) Description of accounting system (excludes contractors required to submit a CAS Disclosure Statement or contractors where the description of the accounting system has not changed from the previous year's submission).
(E) Procedures for identifying and excluding unallowable costs from the costs claimed and billed (excludes contractors where the procedures have not changed from the previous year's submission).
(F) Certified financial statements and other financial data (e.g., trial balance, compilation, review, etc.).
(G) Management letter from outside CPAs concerning any internal control weaknesses.
(H) Actions that have been and/or will be implemented to correct the weaknesses described in the management letter from subparagraph (G) of this section.
(I) List of all internal audit reports issued since the last disclosure of internal audit reports to the Government.
(J) Annual internal audit plan of scheduled audits to be performed in the fiscal year when the final indirect cost rate submission is made.
(K) Federal and State income tax returns.
(L) Securities and Exchange Commission 10-K annual report.
(M) Minutes from board of directors meetings.
(N) Listing of delay claims and termination claims submitted which contain costs relating to the subject fiscal year.
(O) Contract briefings, which generally include a synopsis of all pertinent contract provisions, such as: contract type, contract amount, product or service(s) to be provided, contract performance period, rate ceilings, advance approval requirements, pre-contract cost allowability limitations, and billing limitations.
(v) The Contractor shall update the billings on all contracts to reflect the final settled rates and update the schedule of cumulative direct and indirect costs claimed and billed, as required in paragraph (d)(2)(iii)(I) of this section, within 60 days after settlement of final indirect cost rates.
(3) The Contractor and the appropriate Government representative shall execute a written understanding setting forth the final indirect cost rates. The understanding shall specify (i) the agreed-upon final annual indirect cost rates, (ii) the bases to which the rates apply, (iii) the periods for which the rates apply, (iv) any specific indirect cost items treated as direct costs in the settlement, and (v) the affected contract and/or subcontract, identifying any with advance agreements or special terms and the applicable rates. The understanding shall not change any monetary ceiling, contract obligation, or specific cost allowance or disallowance provided for in this contract. The understanding is incorporated into this contract upon execution.
(4) Failure by the parties to agree on a final annual indirect cost rate shall be a dispute within the meaning of the Disputes clause.
(5) Within 120 days (or longer period if approved in writing by the Contracting Officer) after settlement of the final annual indirect cost rates for all years of a physically complete contract, the Contractor shall submit a completion invoice or voucher to reflect the settled amounts and rates. The completion invoice or voucher shall include settled subcontract amounts and rates. The prime contractor is responsible for settling subcontractor amounts and rates included in the completion invoice or voucher and providing status of subcontractor audits to the contracting officer upon request.
(6)
(i) If the Contractor fails to submit a completion invoice or voucher within the time specified in paragraph (d)(5) of this clause, the Contracting Officer may-
(A) Determine the amounts due to the Contractor under the contract; and
(B) Record this determination in a unilateral modification to the contract.
(ii) This determination constitutes the final decision of the Contracting Officer in accordance with the Disputes clause.
(e) Billing rates. Until final annual indirect cost rates are established for any period, the Government shall reimburse the Contractor at billing rates established by the Contracting Officer or by an authorized representative (the cognizant auditor), subject to adjustment when the final rates are established. These billing rates-
(1) Shall be the anticipated final rates; and
(2) May be prospectively or retroactively revised by mutual agreement, at either party's request, to prevent substantial overpayment or underpayment.
(f) Quick-closeout procedures. Quick-closeout procedures are applicable when the conditions in FAR 42.708(a) are satisfied.
(g) Audit. At any time or times before final payment, the Contracting Officer may have the Contractor's invoices or vouchers and statements of cost audited. Any payment may be-
(1) Reduced by amounts found by the Contracting Officer not to constitute allowable costs; or
(2) Adjusted for prior overpayments or underpayments.
(h) Final payment.
(1) Upon approval of a completion invoice or voucher submitted by the Contractor in accordance with paragraph (d)(5) of this clause, and upon the Contractor's compliance with all terms of this contract, the Government shall…
This is the start of the file's text. The full file is on GovTribe.