SOW_FY27_Post Wide_FE 10082 5J_ JOC Contract 1st draft Sources Sought.pdf

PDF 606 KB Posted

Attached to
Job Order Contract (JOC) at Fort Bliss, Texas
Solicitation number
W5168W-27-X-JOC
Issued by

About this file

This Statement of Work (SOW) details a Job Order Contract (JOC) for Fort Bliss, Texas, covering a comprehensive range of construction and repair services for military facilities. The contract supports sustainment, restoration, and modernization projects across various facility types including administrative buildings, barracks, maintenance shops, motor pools, hangars, child development centers, and infrastructure systems such as roads, utilities, bridges, and athletic fields.

The JOC encompasses multiple construction disciplines including asbestos and lead-based paint abatement, foundation work, HVAC, mechanical systems, electrical work, plumbing, roofing, site work, and demolition. The contract will use RSMeans/e-Gordian unit pricing with a contractor-proposed coefficient, and projects will range from small repairs to complex renovations. Task orders will be issued individually, with work to be completed according to specific technical criteria, and the contract includes provisions for non-pre-priced items, quality control, environmental compliance, safety requirements, and detailed documentation processes. The contract is structured as a Firm Fixed Price, Indefinite Delivery-Indefinite Quantity (IDIQ) agreement with a focus on maintaining and improving Fort Bliss infrastructure.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW)

For

Fort Bliss, TX

Job Order Contracting (JOC)

April 21, 2025

Table of Contents

GENERAL

CONTRACT DESCRIPTION

SCOPE OF WORK

WORK RESPONSIBILITY

4.1 Work Hours

4.2 Federal Holidays

4.3 Installation Closures

4.4 Inclement Weather Delay

CONTRACTOR RESPONSIBILITY

5.1 Task Order Coordination

5.2 Commencement

5.3 Work Execution

5.4 Deliverables

ORDERING PROCEDURES

6.1 Responsiveness

PROPOSALS

7.1 Contingency

7.2 Cost Estimating Requirements

7.3 Waste and Excess Quantities Included

7.4 UPB Vendor Clarifications

7.5 UPB Application – Specific Considerations

7.6 Coefficients

7.7 Project Schedules

7.8 Time Extensions

7.9 Weather Related Time Extensions

7.10 Liquidated Damages

TASK ORDER DOCUMENTS

8.1 Task Order Work Files

8.2 Notice of Completion of Task Order

8.3 Real Property Documents Required Before TO Close-Out

PERSONNEL

9.1 Key Personnel

9.1.5 On-Site Staff

PRE-CONSTRUCTION ORIENTATION

REQUIRED CONTRACTOR PLANS

11.1 Accident Prevention Plan

11.2 Asbestos and Lead Management Plan

11.3 Contractor Quality Control (CQC) Plan

11.4 Management Plan

11.5 Site Safety and Health Plan (SSHP)

11.6 Spill Plan

11.7 Traffic Control Plan

CONTRACTOR QUALITY CONTROL SYSTEM

12.1 Quality Control (QC)

12.2 Coordination Meeting

12.3 Inspections

12.4 Performance Evaluation Meetings

12.5 Notification of Noncompliance

12.6 QCM’s Completion Inspection

12.7 Pre-Final Inspection

12.8 Final Acceptance

12.9 Testing Procedures

12.10 Files and Reports

FACILITIES

13.1 Closure Inspections

13.2 Secure Areas

13.3 Conditions of Occupancy

13.4 Elevators

13.5 Equipment on the Site

13.6 Office Trailer

13.7 Construction Site Maintenance

13.8 Permits, Fees, and Licenses (Non-Environmental)

13.9 Excavation and Utility Permits

13.10 Vehicular Access to Construction Sites

13.11 Discovery of Unexploded Ordnance (UXO)

13.12 Historical, Architectural, and Landscaping Requirements

13.14 Site Security

13.15 Security Awareness

13.16 Construction Project Site Sign

SAFETY

14.1 Pre-Construction Safety Meeting

14.2 Safety Hazards

14.3 Materials and Equipment

14.4 Safety Data Sheets (SDS)

14.5 Medical Surveillance

14.6 Confined Space Entry Procedures

14.7 Noise Control

14.8 Required Seatbelt Use

14.9 Trucking

14.10 Construction Hazard Communication

14.11 Fire Prevention and Protection

14.12 Radiation Permits and Authorizations

14.13 Hazardous Materials

14.14 Polychlorinated Biphenyl (PCB)

ENVIRONMENTAL REQUIREMENTS

15.1 Environmental Protection Considerations

15.2 Green Procurement

15.3 Environmental Compliance

15.4 Record of Environmental Consideration (REC)

15.5 Citations

15.7 Sampling

15.8 Land Resources

15.9 Water Resources

15.10 Biological Resources (Fish and Wildlife)

15.11 Air Resources

15.12 Cultural Resources

15.13 Waste Disposal

15.15 Recycling

15.16 Wastewater Discharges

15.17 Contamination Discovery

15.18 Construction Cleanup

15.19 Restoration of Landscape Damage

15.20 Maintenance of Pollution Facilities

15.27 Sustainable Acquisition Requirements

15.28 Applicable Laws, Regulations, Statutes, and Acts

15.29 Chain of Custody Procedures

CLEAN-UP AND WASTE MANAGEMENT

16.1 Construction & Demolition (C&D) Debris

16.2 Salvageable and Unsalvageable Materials

16.3 Disposal of Asbestos

16.4 Disposal of Hazardous Materials

16.5 Disposal of Solid, Liquid, and Gaseous Contaminants

SPECIFICATIONS

17.1 JOC Technical Specifications

17.2 Documents

SUBMITTALS

18.1 Material Approval Submittals

18.2 Environmental Compliance

18.3 Drawings

CONTRACTOR REPORTS

19.1 Abatement Report

19.2 Accident Reporting

19.3 Construction and Demolition Debris Reports

19.4 Damage Reports

19.5 Environmental Compliance Reporting

19.6 Progress Charts

19.7 Quality Control Reports (QCR)

19.8 Solid Waste Management Report

19.9 Warranty Item Report

19.10 Adverse Weather Log

Special Contract Requirements

20.1 Work by the Government

20.2 Security Requirements

20.3 Anti-Terrorism (AT) Training

20.4 Operations Security (OPSEC) Training

20.5 Access and General Protection, Security Policy, and Procedures

20.6 Contractor Employees Requiring Access to Government Information Systems 67

20.7 Contractor Employees Requiring a Common Access Card (CAC)

20.8 Government Furnished Material (GFM), Property (GFP), and Equipment (GFE)

20.9 Contractor-Furnished Property (CFP) and Equipment (CFE)

ACRONYMS AND DEFINITIONS

21.1 Acronyms

21.2 Definitions

APPLICABLE DIRECTIVES AND PUBLICATIONS

22.1 General

22.2 Technical Publications, Codes, and Standards

22.3 Codes and Standards

22.3.3 Federal Environmental Statutes

22.3.4 Federal Standard (Fed. Std.)

22.4. Army Regulations (AR)

22.5 Department of the Army Pamphlets

22.6 Department of the Army, Corps of Engineers Manual (EM), Engineers Technical Letter (ETL)

22.7 Other Documents

22.8 Building Codes

23.0 ADDITIONAL CONTRACT TERMS AND CONDITIONS

24.0 SAMPLE EXHIBITS

GENERAL

This is a non-personal services contract to provide Job Order Contract (JOC) requirements to Fort Bliss, Texas including all training ranges. The Government shall not exercise any supervision or control over the Contract Service Providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

CONTRACT DESCRIPTION

This is a Firm Fixed Price (FFP) Indefinite Delivery-Indefinite Quantity (IDIQ) Job Order Contracting (JOC) contract for construction work as defined under the North American Classification System (NAICS) 236220 – Commercial and Institutional Building Construction.

This contract is for a broad range of real property repair and construction at Fort Fliss.

Potential projects include, but are not limited to, administrative facilities, barracks, maintenance shops, motor pools, hangars, child development centers, physical fitness centers, maintenance shops, food service facilities, airfield structures including rigid and flexible paving, roads, athletic fields, bridges, underground utilities, overhead utilities, gates, warehouses, and auditoriums. Projects may include incidental design, testing, studies, surveys, mold repair/remediation and abatement for lead-based paint (LBP) or asbestos containing materials (ACM). Facility repairs, renovations, and construction shall conform to the requirements of the technical criteria described in the task order (TO).

The Contractor shall furnish site work as required per the line item in RSMeans/e- Gordian.

The services covered by this contract are for real property repair and construction.

Construction and repair include the following systems and disciplines:

Asbestos and Lead-Based Paint Abatement (as part of repairs)

Foundation and Site work

Minor and General Construction Heating, Ventilation, and Air Conditioning

(HVAC)

Bridge and Culvert Repair Mechanical (to include Systems / Control Systems)

Carpentry Natural Gas Distribution System

Concrete and Masonry Painting Demolition Plumbing (to include Systems)

Site cleanup as part of construction completion

Road Repair (include concrete or asphalt repair)

Doors and Windows Roofing

Drywall Sheet Metal

Electrical Steam Fitting

Electronic System and Security Systems Storm Water Collection Systems

Excavation Thermal and Moister Protection

Finishes Welding

Fire Suppression and Fire Alarm and Mass Notification Systems

Communications / IT

Flooring Mold Remediation (as part of repair)

SCOPE OF WORK

The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and construction services necessary as defined in this SOW.

The JOC will be used to fulfill repair, maintenance, demolition and minor construction requirements on a variety of projects ranging from Sustainment, Restoration, and Modernization (SRM), simplified acquisition of base repair requirements, civil works operations and maintenance, small renovations, real property repair and maintenance with an estimated value more than the micro-purchase threshold (MPT) for acquisitions of construction. At the time of this revision the MPT is $2,000.00 in accordance with (IAW) Federal Acquisition Regulation (FAR) 2.101, Definitions.

Potential projects include, but are not limited to, barracks, administrative facilities, maintenance shops, child development centers (CDC), physical fitness centers, maintenance shops, food service facilities, airfield structure, athletic fields, underground utilities, gates, warehouses, auditoriums, and other general construction work deemed necessary to support the Directorate of Public Works (DPW) Fort Bliss mission requirements. Facility repairs, renovations, and construction shall conform to the requirements of the technical criteria described in the Task Order (TO).

Security training required will be identified on each Task Order (TO). The Contractor’s key personnel shall be responsible for training all Contractor personnel at the Contractor's own expense.

The JOC shall not be used to purchase supplies, services, or Architect and Engineer (A- E) Services.

For example, the following items are not authorized for acquisition under this JOC contract:

• Fuels

• Utilities (Contractor is to perform any incidental work to the point of connection of primary utilities)

• Construction equipment

• Administrative equipment

• Furnishings

• Construction materials only (lumber, concrete, etc.), for other than valid JOC projects

• A-E Services (Brooks Act)

• Administrative services such as typing, transportation, reproduction, graphics, and interior design services not part of a JOC Contractor construction proposal

• Maintenance, overhaul, or repair of equipment

• Housekeeping Services

• Purchase of supplies

• No Design (Contractor is to produce shop drawings incidental to the job, reflecting the plan of action and the completed project)

• For the sole purpose of abatement of lead-based paint and/or asbestos

Note: IAW Army Federal Acquisition Regulation Supplement (AFARS) 5117.9002(b), The Requiring Activity’s reoccurring facilities engineering support services, such as utility plant operation, custodial, grounds maintenance, refuse collection and disposal, and similar work shall not be acquired using a JOC. Architect-engineer services as defined in FAR 36.102 and Design-Build requirements as defined in FAR 36.3 shall not be acquired under a JOC.

WORK RESPONSIBILITY

The Contractor shall perform repair and construction as defined in each TO. Individual SOWs will vary in size and complexity depending on the nature of the work. The Contracting Officer (KO) will issue to the Contractor a Request for Task Order Proposal (RTOP) detailing the task to be accomplished. The Contractor shall estimate the level of effort required to perform the requested work and shall submit a detailed proposal of items required to accomplish the work within the time frame stated in the RTOP. The proposal shall be of sufficient detail and broken out by item, so the Government can readily identify the estimated quantities and level of effort for each task and subtask. The Contractor shall provide supervision, labor, materials, equipment, and supplies, unless otherwise specified as Government-furnished in each TO.

The KO will identify any security training required before the start of work. The Contractor’s key personnel shall train all Contractor personnel at the Contractor's own expense.

The Contractor shall use cost estimating software RSMeans/e-Gordian as prescribed by the Government. The Contractor shall furnish work as required per the Line-item in RSMeans/e-Gordian. The Contractor shall provide as-built drawings, which conform to one (1) copy in CADD-MicroStation, one (1) copy in PDF, and one (1) mylar 3 mil engineering film printout in 24” x 36” size specified per TO. The Contractor shall perform IAW current OPORDS, most current codes including National Fire Protection Association (NFPA) codes, ARMY Standards and Industry and Trade Organization standards.

4.1 Work Hours

The Government's regular (normal) hours are from 0700 – 1600 hours, excluding Federal Holidays or when the Government Facility is closed due to local or national emergencies, administrative closings, or similar Government directed Facility closings. Work outside normal duty hours shall be coordinated with and approved by the Contracting Officer’s Representative (COR). Projects outside of normal work hours will be identified per Task Order (TO). A separate coefficient shall be used for work identified as outside of normal work hours.

4.2 Federal Holidays

The Contractor’s performance shall not be required on the Federal public holidays listed below. However, that requirement is subject to mission execution requirements; and work on Holidays, when required, will be annotated on the individual TO.

New Year’s Day 1st day of January Martin Luther King Jr.'s Birthday 3rd Monday of January Presidents Day 3rd Monday of February Memorial Day Last Monday of May Juneteenth 19th day of June Independence Day 4th day of July Labor Day 1st Monday of September Columbus Day 2nd Monday of October Veterans Day 11th day of November Thanksgiving Day 4th Thursday of November Christmas Day 25th day of December

NOTE: When a holiday falls on a Sunday, the following Monday will be observed as a holiday, and, when a holiday falls on a Friday or Saturday, the preceding Thursday is observed as a holiday by United States (U.S.) Government Agencies. Federal holidays also include any Presidential or Congressionally designated days off other than the holidays listed above.

4.3 Installation Closures.

When an unforeseen Installation closure occurs on a regularly scheduled day of work, the Contractor shall:

a. Reschedule the work to be performed the following day unless the following day is a Saturday, Sunday, a legal public holiday, and when routine work is not scheduled for that day; or

b. Reschedule the work on any day mutually satisfactory.

4.4 Inclement Weather Delay.

If the Contractor determines unsafe weather conditions for continued operations, the Contractor shall notify the KO/COR of inclement weather within one (1) hour of suspension of work. The Contractor shall resume operations with KO/COR approval.

4.5 Physical Security.

The Contractor shall be responsible for safeguarding all Government equipment, information and property provided for Contractor use IAW AR 190-13, The Army

Physical Security Program. At the close of each work period, Government facilities, equipment and materials shall be secured by the Contractor.

CONTRACTOR RESPONSIBILITY

The Contractor shall assume full responsibility and liability for non-compliance with all Federal, State and local laws, regulations, codes, policies, and directives pertaining to the health and safety of personnel during the execution of work and shall hold the Government harmless. The Contractor shall perform all related Contractor administrative services, planning, programming, and management necessary to perform the work, to include but are not limited to, supply, quality control (QC), and maintenance of accurate and complete records, files, and libraries of documents.

At the TO level the Contractor shall provide related services to include, but are not limited to, pre-award project development, project management, QC, and submission of required deliverables necessary to satisfy requirements specified under this contract and individual TOs. The Contractor shall visit and inspect the job site prior to the start of any work. The Contractor shall document (with photos) any damaged areas and turn them into the COR, to preclude any responsibility for damages present that are not a result of the performance of work required in the TO. In the absence of the COR, the Alternate COR (ACOR) will assume responsibility.

5.1 Task Order Coordination

The signed, issued TO constitutes the Contractor’s Notice to Proceed (NTP) unless a separate NTP is specified in the TO. Prior to scheduling work for a TO, the Contractor shall coordinate with the COR to agree on a sequence of procedure, means of access to premises/building, space for storage of materials and equipment, delivery of materials, and use of corridors, stairways, elevators, eating spaces, and restrooms for Contractor personnel.

5.2 Commencement

The Contractor shall be required to commence work IAW the TO notice to proceed (NTP) date.

5.3 Work Execution

The time stated for entire completion of work specified in the TO, unless a separate NTP is issued shall include final cleanup of the premises and submission of all deliverables.

TOs shall be considered separate projects, and any decision by the Contractor to utilize a limited number of subcontractors on multiple orders shall not constitute grounds for non-performance, time extensions, avoidance of liquidated damages, or other reductions for cause. The Contractor shall work, so far as practicable, in definite sections or divisions and confined to limited areas which shall be completed before starting on other sections or divisions.

5.3.1 Construction Related Changes

The Contractor shall document and obtain authorization from the KO before making any requirement changes to the SOW. Construction-related requests from building occupants shall be directed to the KO/COR prior to taking any action. Any job site changes made by construction employees, either direct or subcontracted, shall be subject to removal and corrected at no additional cost to the Government. Contractor shall inform all employees to include the subcontractor of this requirement.

5.4 Deliverables

The Contractor shall submit to the KO and COR a complete package of pre-construction deliverables which include, but are not limited to, Government approvals, permits, notices of award of subcontracts, performance schedules, and material or product submittals no later than (NLT) fourteen (14) calendar days after TO award. The Government will make every attempt to respond to the pre-construction deliverables within fourteen (14) calendar days after the Contractor’s submissions are received.

Post-completion deliverables such as completed warranties certificates, completed Department of Defense (DD) Form 1354, Transfer and Acceptance of DoD Real Property, as-built drawings, room key inventory list, installed building equipment list, operation and maintenance (O&M) manuals, payrolls, Release of Claims, BUILDER Sustainment, and environmental closure documents shall be submitted to the KO and COR prior to requesting final payment.

5.4.1 Construction/Project Management Software

Task Order management requires utilization of a formal construction project management software beyond the capabilities of manual, paper-based, or email correspondence to automate the project management process.

The Contractor shall be responsible for purchasing and maintaining cost estimating software with the most up-to-date version throughout the contract performance period.

5.4.2 Correspondence Identification

The Contractor shall use a contract number and TO number on all correspondence sent to the KO and COR. The Contractor shall provide one (1) electronically with one (1) paper copy of all Serial Letters and Bonds. All other correspondence to be electronic only.

ORDERING PROCEDURES

The Government will issue and furnish a RTOP to the Contractor. The Contractor shall then prepare a proposal for the accomplishment of the task within the time limit specified in the RTOP. The RTOP will identify an existing requirement based on SOW and designs as applicable to the Task Order to be provided by the Government and will include as built or sketches as applicable for the SOW to be accomplished.

6.1 Responsiveness

As specified in the RTOP, the Contractor shall respond to the needs of the Government.

The Contractor shall perform a site visit with the COR. The Contractor shall review the construction requirements and discuss problems, unclear items, access, etc. The Contractor shall prepare a site visit memorandum, listing all pertinent items discussed during the site visit. The site visit is considered essential to the preparation of a complete and accurate proposal of the project desired by the DPW. The site visit memorandum shall be submitted with the Contractor’s proposal. Failure to visit the site and discuss the project requirements with the COR, shall not constitute an acceptable excuse for omissions or errors in proposals. The Contractor shall review the drawings, sketches, and any changes in the SOW that resulted from the site visit. The Contractor shall then prepare a proposal for the TO.

PROPOSALS

The Contractor shall prepare a detailed cost estimate using the approved RSMeans/e- Gordian. RSMeans/e-Gordian software shall be utilized for all applicable pricing under this contract. The Contractor shall purchase the most current RSMeans/e-Gordian software to support the contract requirements within seven (7) calendar days of contract award. The Contractor shall both always have the most current version of the software and databases.

Upon the Government’s request, the Contractor shall be prepared to provide a detailed breakdown of the proposal, to include all pricing documentation to demonstrate that it is fair and reasonable cost.

In the development of a price proposal, site visits will be considered as incidental to the work and included in the Contractor’s coefficient.

The Contractor shall submit proposals electronically and include a printout of all proposed RSMeans items, quantities, extended prices, and total proposed costs. Significant components of work and all Non-Pre-Priced (NPP) items shall be identified in the price proposal.

The Contractor’s proposal shall be supported by documentation and include, but not be limited to, product submittals, plans, special conditions, specifications, proposed completion period, name of the Project Manager (PM), and a copy of the initial RTOP form with notations on any agreed upon item changes. This will be incorporated in the final SOW to be issued with the TO and the TO proposal cost estimates which is comprised of the following three (3) sections:

a. Section 1, Division Summary: This section shall include the RSMeans/E-Gordian divisions, Trades, Assemblies, and NPP items. This section shall make up the Bare Total. No markups shall be applied at this level. The Contractor shall apply the City Cost Indexes (CCIs).

NPP items will be submitted with two (2) or more offerors, IAW 15.404-1(b)(2)(i) and 15.403-1(c)(1)(i)). The independent price vendor shall include line-item number, description, material, labor, and equipment breakdowns. The Contractor shall list the supplier names and telephone numbers for each NPP item

b. Section 2, Totaling Components: This section includes totaling components setup for all applicable markups, including Contractor coefficients. CCIs shall be applied.

c. Section 3, Line-item Estimate: This section shall include all line items. The report shall include a sequential Line-item number, Line-item description, full UPB item number, unit of measure, quantity, bare unit cost, and total amount (quantity multiplied by bare unit cost). The report will print: Pre-Priced line items by division for all UPB Pre-Priced line items found in the RSMeans/e-Gordian, with division breaks and division subtotals, and a listing of the Trades, Assemblies, and NPP items. CCIs shall be applied.

7.1 Contingency (RESERVED)

7.2 Cost Estimating Requirements

The Government-approved UPB for this contract shall be the sole source of Pre-Priced costs. Work tasks required for the completion of specific project requirements that are not considered part of the complete-in-place construction of the RSMeans/e-Gordian items or are not otherwise contained in the RSMeans/e-Gordian are called NPP and their use is defined herein. Any difference between actual prices and UPB pricing shall not constitute grounds for failure to perform nor shall be grounds for any equitable adjustments in the price for the TO.

7.2.1 What Is Included

Prices in RSMeans/e-Gordian will include the following: direct labor through the foreman level at current Davis-Bacon Act for the area, equipment costs for the region, tools and material costs including delivery, sales tax and all incidentals. Incidentals include, but are not limited to, nails, screws, welds, and connectors. All prices in RSMeans/e-Gordian are for complete-in-place construction unless explicitly described otherwise.

Since RSMeans/e-Gordian are constructed from averaging cost data from projects nationally, there is variance in incidental options or accessories provided by equipment Manufacturers and incorporated into the costs. Therefore, the Government reserves the right to require incidental options or accessories without additional cost, except where the required additions are spelled out as a modifier within RSMeans/e-Gordian.

7.3 Waste and Excess Quantities Included

All prices in RSMeans/e-Gordian are for the complete-in-place construction unless explicitly described otherwise. The unit prices include delivery of materials to the job site.

Waste or excess material quantities are incidental costs which are included within the contract coefficient unless explicitly stated otherwise in RSMeans/e-Gordian. Quantities used on TO proposals shall be for in place quantities taken from field measurements or design plans, as appropriate, without allowance for waste or incidental extra materials.

Incidental nails, screws, weldments, and connectors are included in RSMeans/e-Gordian line items. Unless a connector or fastener is specifically stated as not being included, it is included in the price. Example: Installation of a suspended ceiling grid system includes connectors, fasteners, and wire for the hanging system.

7.4 Vendor Clarifications

Any time clarifications are required regarding content or scope of a RSMeans/e-Gordian Line-item and the issue is not covered elsewhere in this contract, the KO will act as the sole liaison with the Vendor for obtaining the necessary clarifications.

7.5 Application – Specific Considerations

7.5.1 Demolition

Ancillary components attached to an affected item or equipment that is scheduled for demolition shall not be priced out separately unless the ancillary component must be removed to complete the TO. Line-item demolition includes all attached appurtenances and ancillary components attached to an affected item or equipment that is scheduled for demolition. If the item being demolished is attached to another item being removed and can be removed as one item, then that item shall not be priced as a separate demolition task, unless the component alone must be demolished. For example, demolition of a wood door includes hinges, hardware, closures, kick plates, etc., and removing pipe includes all in-line fittings and valves. Unless explicitly required in the SOW.

Demolition prices in RSMeans/e-Gordian shall cover the cost of removal and disposal of the items. Demolition shall include the removal of the item, handling, disassembly, loading in a truck or dumpster, and disposal of demolished items, whether salvageable or non-salvageable, unless specified otherwise by RSMeans/e-Gordian task. Unit prices for demolition exclude costs for hauling.

7.5.2 Assembly Pricing

Assembly pricing shall take precedence over individual component unit pricing.

7.5.3 Line-item Cost Adjustments

The only adjustment of price for the construction line items is the Contractor coefficient.

All prices in RSMeans/e-Gordian are for complete-in-place construction unless explicitly described otherwise. Incidental fasteners (nails, screws, weldments, adhesives or other connectors), incidental options, accessories, and small tools required for a normal installation are included in the line-item cost unless the Line-item description specifically states otherwise. Line-item prices include all work required unless the Line-item description specifically states otherwise. Equipment costs include normal operating expendables and servicing including routine parts. All Line-item prices are valid to perform the work described to a height up to fourteen (14) feet above finished floor or grade level without the allowance for scaffolding or lift equipment, unless the Line-item description specifically states otherwise. Testing, adjusting, balancing, and start-up of installed equipment (normal commissioning) and up to four (4) hours of familiarization training for operation and maintenance of that equipment, shall be included unless the Line-item description specifically states otherwise. Scaffolding, lifts, staging, etc. shall be allowed only on a TO basis (per job), not per subcontractor or discipline.

7.5.4 Price Adjustment Modifiers

RSMeans/e-Gordian incorporated in this contract contains unit pricing data to be used by the Contractor in development of price proposals for each TO. The pricing data is presented as basic items and as price adjustment modifiers to the basic item. Price adjustment modifiers provide a method for adding to or deducting from the basic item prices for optional materials, and methods of installation. One (1) or more modifiers can be utilized to adjust the basic item price as listed by the appropriate suffix number of the basic line item.

7.5.5 Non-Standard Work (Non-Pre-Priced)

Non-pre-priced (NPP) work is categorized as facilities construction activity that is not specifically included in RSMeans/e-Gordian, but is within the basic intent and general scope of the contract, requiring substantial adjustment due to material differences in factors from those typically encountered in the construction industry. Items of work not covered by this contract’s pre-priced items, but within the scope and general intent, may be negotiated by the KO and added to a TO at any time during the contract term. NPP items shall only be allowed if the Government deems an appropriate line item is not provided by the pre-priced RSMeans/e-Gordian. To permit recurrent use, a NPP item shall be incorporated by supplemental agreement into RSMeans/e-Gordian and may be done at any time during the contract period.

NPP work to be included in a TO shall be proposed by the Contractor in a format acceptable to the Government. NPP line items added to a TO shall be complete, including materials and labor and shall be for specific tasks, and not for general labor hours for example. NPP work or items shall be negotiated with the Pre-Priced items in the proposal at the negotiation meeting. Additional items may be added to the basic tasks defined in RSMeans/e-Gordian as new pre-priced items. If new pre-priced items are added, the prices will be in effect on the date of TO award.

7.5.6 Include Recurring NPP items to RSMeans/e-Gordian

The Contractor and the Government shall discuss material, labor, and equipment costs based on the unit of measure for an item. The Contractor shall justify costs with cost and pricing data (Vendor quotes, labor standards, etc.). This will be referred to as the bare cost of the NPP. Once the bare cost of the NPP item has been decided, the item can be added to a TO by adding the Contractor’s overhead costs for NPP items from the bid schedule or it may be modified into RSMeans/e-Gordian for use on all TOs. To be modified into RSMeans/e-Gordian, the bare cost must be economically adjusted to the date of the development of the RSMeans/e-Gordian and then must be adjusted to be consistent with the Contractor's coefficient.

The project shall not be executed under this contract if the value of the NPP work exceeds 10% of the Pre-Priced cost of the TO unless it’s determined by the KO to be a good business decision in the best interest of the Government IAW AFARS 5117.9004-3(c)(1).

TO cost and the NPP work shall not be considered incidental. Only NPP work that is incidental to Pre-Priced work shall be considered to be within the scope of this contract.

Incidental NPP will be discussed and established on a work item-by-work item basis. The Pre-Priced coefficient is not applied to NPP items. The NPP overhead and profit rate will be applied to the agreed to bare costs of NPP items after the bare costs of these items have been established.

7.5.7 NPP Contractor Material and Equipment Costs

The Contractor shall receive the cost of the material plus the applicable coefficient as a handling fee. Material costs may include freight but shall not include any other overhead or associated costs. Equipment costs may only be included if the equipment is used solely as a result of inclusion of the NPP item.

7.6 Coefficients

Coefficients are location-specific multiplier(s) developed and proposed by the Contractor, to be applied against the published UPB cost line items for the purpose of providing consideration to the Contractor. The Contractor shall factor in potential risks of inflation into the proposed coefficients.

Offerors shall provide indirect costs, NPP overhead and profit rate.

The Contractor’s negotiated coefficient schedule will be incorporated into the contract and utilized by the Government in determining the value of issued TOs throughout the life of the awarded contract.

The Contractor's price coefficient shall include all products within RSMeans/e-Gordian, including the following:

• Contractor's overhead and profit

• General and administrative and other overhead costs

• Bonding and alternative payment protection costs

• Protective clothing

• Subcontractors' overhead and profit

• Insurance

• Costs associated with bonding (specifically including bond premiums)

• Employee payroll taxes, insurance, and fringe benefits

• Business taxes, contributions, memberships, corporate

• Headquarters support (legal, financial, etc.)

• Waste and excess material

• Gross receipt and sales tax on material and equipment costs

• Clean up

• Mobilization and close out for the total contract and each TO

• Compliance with environmental laws (overhead {indirect} costs associated with performing work in compliance with Environmental Protection Agency (EPA), Occupational Safety and Health Administration (OSHA) regulations, including obtaining any necessary licenses and permits, reporting requirements, etc.)

• Compliance with protection and safety laws such as safety rails, face and clothing protection

• Close out for the total contract and each TO

• Traffic and work site signs and barriers

• Project management and supervision

• Protection of and moving of Government Property

• QC

• Office Management and equipment

• Depreciation of mobile office(s)

• Interest associated with funding of equipment and payroll

• Submittal preparation

• As built drawings

• Permits, licenses, and fees

• Other risks of doing business such as risk of a lower-than-expected contract dollar value, risk of a high inflation cost if factors are bid for option years, risk of poor subcontractor performance and re-performance

• UPB costs confidence to include issues regarding how the cost data are captured and the size and types of projects

• Contingencies

• Travel

• Depreciation of equipment or facilities

• Variances in subcontractor or worker availability

• Other local market conditions for each site not addressed by UPB location factors

• Other risks of doing business, acceptance testing, work-site security, etc.

7.7 Project Schedules

The Contractor shall prepare and submit a Project Schedule for approval, as specified in each TO. Schedules shall be provided at no additional cost to the Government. The schedule shall indicate all work activities, milestones, and clearly show the critical path of the job. The schedule shall include activities for submittal approval, as-built drawings, final clean up and inspection, correction of punch list items and final payroll submittal, and operation and maintenance manuals. The schedule shall indicate the sequence in which the Contractor proposes to perform the work and dates on which the Contractor proposes to start and complete all scheduled activities. The Contractor shall schedule the entire project from the award date. The Contractor shall use the approved project schedule to measure the progress of the work.

Revisions of the schedule shall be re-submitted with each modification proposal for approval. The revised TO schedule shall clearly reflect the added and/or deleted items of work; and reflect the increase or decrease in time required to execute the project and the modification. The Contractor shall immediately contact the KO for further direction if a Government Representative requests a change to the SOW.

Construction project schedules shall be submitted electronically. The Contractor shall provide an approved electronic version, readable without providing a copy of the software, to the KO and COR.

7.8 Time Extensions

Time extensions for TO modifications will be awarded if the additional work required by the modification delays on-going construction activities or if additional time is required to accomplish the added work requirements. Time shall not be extended to correct insufficient progress prior to the modification. (FAR 52.211-13, Time Extensions)

7.9 Weather Related Time Extensions

Time extensions may result from unusually severe weather for exterior projects. The KO may award a time extension only if the following conditions are satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather must cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

Unusually severe is defined as weather that is abnormal compared to the past weather at the same location for the same time of year. Since the weather causing the delay must be abnormal for the same time of year and location, the fact that a Contractor encounters even extremely harsh weather, which in fact prevents them from working, is alone insufficient for finding an excusable delay if such weather is normal for the contract site.

Adverse weather which at the time of year in which it occurred is unusual for the place in which it occurred. No matter how severe or destructive, if the weather is not unusual for the particular time and place, or if a Contractor should have reasonable anticipated it, the Contractor is not entitled to relief. A mere showing that there was rain, high wind velocity, or other unsettled weather conditions which interfered and prevented performance of work is not sufficient to bring those weather conditions within the meaning of the terms "unusually severe" weather.

7.9.1 Anticipated Weather Delays

Anticipated weather delays are typically based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and shall constitute the base line for monthly weather evaluations as specified in the TO. The Contractor’s progress schedule shall reflect these anticipated adverse weather delays for weather-dependent activities.

7.10 Liquidated Damages

The Contractor shall pay liquidated damages to the Government if the Contractor fails to complete the work within the time specified. The amount to be paid by the Contractor shall be determined at the TO level for each calendar day of delay until the work is completed or accepted.

If the Government terminates the Contractor’s right to proceed, the resulting damage will consist of liquidated damages until such reasonable time as may be required for final completion of the work together with any increased costs the Government incurred to complete the work. (FAR 52.211-12, Liquidated Damages).

TASK ORDER DOCUMENTS

The Contractor’s proposal will be reviewed by the Government for accuracy and completeness. The Government will discuss all items with the Contractor. A TO will then be issued by the KO using DD Form 1155, Order for Supplies or Services.

Some circumstances such as change in work or funding priorities may prohibit the Government from issuing a TO after the receipt of the Contractor's proposal. If such circumstances arise, the Government shall not be obligated to reimburse the Contractor for any costs incurred in the preparation of the proposal. The Government reserves the right to cancel a proposed TO before or after receipt of the Contractor’s proposal.

All TOs are subject to the terms and conditions of this contract. In the event of a conflict between a TO and this contract, this contract shall prevail. If the Contractor is awarded multiple TOs, the work shall be completed concurrently unless otherwise specified in a

TO.

8.1 Task Order Work Files

The Contractor shall retain the working file on each TO for the duration of the contract period and shall make these files available for the KO's review. All forms submitted shall be accurately filled out. The Contractor shall retain copies of any material including, but not limited to, receipts, TOs, sales slips, and invoices relating to the TO. The Contractor shall provide the KO access to the Contractor maintained files during the term of the contract.

8.2 Notice of Completion of Task Order

The Contractor shall notify the KO and COR upon completion of each individual TO. The Contractor shall give the Government five (5) calendar days’ minimum advance notice of the date the work will be fully completed and ready for final inspection.

8.3 Real Property Documents Required Before TO Close-Out

As indicated per TO and prior to final acceptance of TO work shall contact the COR for any project-specific information necessary to complete the DD Form 1354, Transfer and Acceptance of DoD Real Property at no cost to the Government.

8.3.1 Interim DD Form 1354, Transfer and Acceptance of DoD Real Property At a minimum of fourteen (14) calendar days prior to final acceptance of the work or as specified on each TO, the Contractor shall complete and submit an accounting of all installed property. Refer to Unified Facilities Criteria (UFC) 1-300-08, Criteria for Transfer and Acceptance of DoD Real Property, for instruction on completing the DD Form 1354.

8.3.2 Final DD Form 1354 (RESERVED)

8.3.3 BUILDER Sustainment Management System (SMS)

Contractor shall provide a list, including salient data, on all replaced components/systems (e.g. description of component/system, Manufacturer, Model Number, Serial Number, Voltage, CFM, RPM, etc.).

Contractor shall provide a list, including salient data, on all newly installed components/systems (e.g. description of component/system, Manufacturer, Model Number, Serial Number, Voltage, CFM, RPM, etc.).

Contractor shall physically tag all newly installed component/equipment/systems.

Tagging shall state the Model Number, Serial Number, and installation date.

PERSONNEL

The Contractor shall provide the necessary personnel to accomplish all work within the time frames specified for each TO. The Contractor’s staff shall meet or exceed the position requirements as stated in the TO. The Contractor shall provide experienced and knowledgeable personnel in civil, structural, architectural, mechanical, and electrical engineering disciplines. The replacement and alternate staff shall meet or exceed the same minimum qualifications as stated in the TO. The Contractor’s staff shall be able to understand, speak, read, and write the English language fluently.

9.1 Key Personnel

Key personnel include the Program Manager (PM), Superintendent, Site Safety Health Officer (SSHO) and Quality Control Manager (QCM). The Contractor shall provide key personnel resumes to the KO for review and acceptance. The Contractor shall designate these individuals in writing and provide cell phone numbers to the KO prior to performance. The Government has the right to reject the Contractor’s choice of key personnel for failure to meet the qualification standards incorporated into the contract. If key personnel is to be replaced, the Contractor shall notify the KO within 24 hours and the alternate Program Manager or QCM shall be identified. The alternates shall meet or exceed the same qualifications as the initial Program Manager and QCM.

9.1.1 Program Manager (PM)

The Contractor shall provide a Program Manager (PM) with full authority to contractually commit the Contractor for prompt action on matters pertaining to Contractor administration of the contract. The Contractor shall provide a PM with a minimum of five

(5) years of experience supervising construction projects like those required by this contract. The PM shall have full authority to act for the Contractor on all contracting, construction, scheduling, resourcing, and/or personnel matters and issues brought to attention by the Government and provide answers or decisions within the limits of the Contract and Job Order specifications.

The Contractor shall provide a qualified on-site Project Manager (PM) responsible for the overall management, coordination, and performance of all work under the TO. The PM shall resolve construction problems in addition to coordinating with subcontractors, construction personnel, and Government personnel. The PM shall have full authority to order supplies, to direct Contractor employees to enter or leave job sites, sign all TO submittal transmittal sheets, and to contractually commit the Contractor for prompt action.

On a temporary basis only, another individual may be designated to act for the on-site PM. However, one (1) workday advanced written notice of such change shall be provided to the KO other than illness or emergency.

The PM shall maintain a file at the job site and available to the KO upon request. The file shall include, but not be limited to, current project documents, executed TO, RTOP, contract drawings, contract specifications, Quality Control Plan (QCP), as-built drawings, and modifications.

9.1.2 Superintendent

The Contractor shall provide a qualified on-site Superintendent and shall be designated in writing (listing name, address, and 24-hour telephone number) to the COR. The Superintendent shall have a minimum of five (5) years of experience supervising and managing Commercial or Federal construction projects similar in scope to those that will be required by this contract (i.e. – more than 5 projects simultaneously). The Superintendent shall be responsible for the overall performance, management, and coordination of the TO and shall be the central point of contact with the DPW for the performance of all work under each TO. Another individual may be designated to act for the Superintendent; however, advanced notice in writing of such change shall be provided to the COR within ten (10) workdays of the proposed change. The Superintendent or Alternate Superintendent shall be physically present at the on-site location while work is being performed, except on Federal Holidays.

The Government has the right to direct the Contractor to replace any individual functioning as Superintendent if the individual fails to perform IAW the requirements of contract. Any replacement Superintendent shall meet the criteria stated in the Contractor's proposal that was evaluated for award of the contract.

The Superintendent shall maintain a file at the job site and available to the KO upon request. The file shall include, but not be limited to, current project documents, executed TO, RTOP, contract drawings, contract specifications, Quality Control Plan (QCP), as-built drawings, and modifications.

The PM and designated Site Superintendent shall have the following:

a. The applicable skills and qualifications as specified in each TO.

b. A minimum of five (5) years of experience in building construction and PM experience with JOC supervisory positions, e.g., PM or construction superintendent, five (5) years of which are experience as a PM for JOC.

c. The qualifications to direct work requiring extensive understanding of and intimate familiarity with the principles, methods, and techniques of architectural, civil, mechanical, fire sprinkler, alarms, and electrical engineering, with no one discipline predominating.

d. Sufficient technical capabilities to coordinate, acquire, and respond to the Government’s requirements for technical design as it relates to the production of final record drawings.

e. The qualifications to negotiate and manage multiple projects at the same time.

f. The qualifications to recruit and manage qualified subcontractors in all construction disciplines.

g. The qualifications to respond in a timely manner to all contractual agreements, instructions, and inquiries from authorized Government personnel.

h. Demonstrated success in Government JOC construction requirements, completely familiar with Federal, State, and local laws, policies, procedures, and regulations pertaining to construction.

i. The qualifications to prepare project proposals and authorized to negotiate

9.1.3 Site Safety and Health Officer (SSHO)

The SSHO shall have a minimum of five (5) years of experience in managing and inspecting construction projects. Shall have the following current certifications and trainings: OSHA30, and First Aid and Cardiopulmonary resuscitation (CPR) certified.

9.1.4 Quality Control Manager (QCM)

The Contractor shall provide a QCM to implement and enforce the Contractor Quality Control (CQC) Plan. The QCM is required at the TO level.

The QCM shall be responsible for the overall quality of work performed under this contract and shall certify that all submittals are in compliance with the contract requirements. The QCM shall have the authority to act in all CQC matters for the Contractor. The QCM shall remain autonomous and not be influenced by other on-site staff members.

The QCM shall be physically present on the installation (Fort Bliss) at all times throughout the construction period during the hours of 0700 – 1600, Monday through Friday, except on Federal Government holidays. This individual shall be a full-time, dedicated employee of the prime Contractor, and be directly accountable to the corporate level QCM only.

The QCM, at a minimum, shall have the following:

a. A minimum of five (5) years of experience in managing and inspecting construction projects.

b. Formal QC education or training in building construction inspection.

c. A minimum of five (5) years of experience in construction QC with Department of Defense (DOD) agency.

d. The minimum experience for the Contractor’s QC Manager without an…