The document is an information sheet regarding utility services for a federal contract opportunity (Solicitation W50SLF25QA007) for a boundary survey at the Keaukaha Air National Guard station in Hilo, Hawaii. The utility details specify that the contractor will be responsible for all temporary utility costs, with specific provisions for water and electricity utilities. Water utility is available with a tie-in requirement and a rate of $1.49/KGAL, while electricity utility is available with a tie-in and removal plan, priced at $507.9/MWH. Notably, sewer utility is not available, and the contractor must provide sewage services independently. These utility service details are intended to help contractors accurately budget and plan for utility expenses during the project's estimated 90-day performance period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES

It has been determined that all temporary utilities shall be the responsibility of the contractor. The contractor will pay all charges (hook up fees, metering, monthly usage, etc.) resulting from temporary utilities. The offerors shall take this into consideration when computing their offers. (FAR Clause 52.236-14, Availability and Use of Utility Services.)

Water Utility. This utility is available for the contractor to tie-in to. For this, the Contractor is to install a backflow preventer with meter from the fire hydrant. The meter will determine water usage that the Govt will invoice the contractor for. For planning/budgeting purposes, the charge rate is $1.49/KGAL.

Electricity Utility. This utility is available for the contractor to tie-in to. For this, the Contractor is to plan for outage, plan for tie-install, and subsequent removal. The tie-in is to be equipped with a meter. The meter will determine electrical usage that the Govt will invoice the contractor for. For planning/budgeting purposes, the charge rate is $507.9/MWH.

Sewer Utility. This utility is not available. Contractor to provide for the sewage.