6 - INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES.docx

DOCX document 13 KB Posted

Attached to
SVC A&E_KAB250002 Maui Boundary Survey Federal contract opportunity
Solicitation number
W50SLF25QA006
Issued by
Department of the Army National Guard

About this file

This document is an informational file detailing utility services availability for a federal contract opportunity (Solicitation W50SLF25QA006) for a Maui Boundary Survey. The file specifies that the contractor will be responsible for all temporary utility costs and connection fees. Utility details include: water utility is available with a tie-in requirement and a charge rate of $1.49/KGAL, electricity utility is available with a metered tie-in and a rate of $507.9/MWH, and sewer utility is not available, requiring the contractor to provide sewage services independently. The contractor must install backflow preventers, plan for electrical outages, and manage utility meter installations and removals, with all utility usage to be invoiced by the government.

View the file

Other files for this federal contract opportunity

Other files attached to SVC A&E_KAB250002 Maui Boundary Survey, newest first.
File Type Posted
5 - GIS Data Format Specifications.pdf PDF
2 - PWS_KABD250002 Maui Boundary Survey.pdf PDF
4 - Map Maui 2019-01-04-123243.pdf PDF
3 - Service Contract Act WD 2015-5739.txt TXT text file
4 - Lease Maui.pdf PDF
1-Solicitation - W50SLF25QA006.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. INFORMATION REGARDING AVAILABILITY OF UTILITY SERVICES

It has been determined that all temporary utilities shall be the responsibility of the contractor. The contractor will pay all charges (hook up fees, metering, monthly usage, etc.) resulting from temporary utilities. The offerors shall take this into consideration when computing their offers. (FAR Clause 52.236-14, Availability and Use of Utility Services.)

Water Utility. This utility is available for the contractor to tie-in to. For this, the Contractor is to install a backflow preventer with meter from the fire hydrant. The meter will determine water usage that the Govt will invoice the contractor for. For planning/budgeting purposes, the charge rate is $1.49/KGAL.

Electricity Utility. This utility is available for the contractor to tie-in to. For this, the Contractor is to plan for outage, plan for tie-install, and subsequent removal. The tie-in is to be equipped with a meter. The meter will determine electrical usage that the Govt will invoice the contractor for. For planning/budgeting purposes, the charge rate is $507.9/MWH.

Sewer Utility. This utility is not available. Contractor to provide for the sewage.