SOW KNMD240008 REPLACE RAMP STORMWATER CONTAINMENT VALVE_Final.pdf

PDF 13 MB Posted

Attached to
REPLACE RAMP STORMWATER CONTAINMENT VALVE Federal contract opportunity
Solicitation number
W50SLF24R0022
Issued by
Department of the Army National Guard

About this file

The provided document is a Statement of Work (SOW) for the project to "REPLACE RAMP STORMWATER CONTAINMENT VALVE" for the Hawaii Air National Guard at JBPHH/Hickam AFB, HI 96853.

The key details are:

The Hawaii Air National Guard has a requirement to replace the ramp stormwater containment valve on the Hawaii Air National Guard Campus Aircraft Parking Ramp. The work must be completed as indicated in the attached SOW, the Contract drawings, and in accordance with specifications and codes. The Contractor must coordinate with the 154 CES to access the work site and coordinate with the 154 CES environmental section for any hazardous materials storage/disposal. The Solicitation Number is W50SLF24R0022, and the Federal Contract Opportunity ID is 8306c375fbfe4d63a87acb3ad4dd602f. The procuring agency is the Department of the Army National Guard.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE RAMP STORMWATER CONTAINMENT VALVE, newest first.
File Type Posted
Solicitation W50SLF24R0022.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

1179645641N

Polygonal Line

Callout

Remove existing valve and controls. Cap electrical at grade.

Text Box

DEMO

Remove existing valve and controls. Cap electrical at grade.

DEMO

Furnish/Install new manual type valve. Connect to existing 18" ductile iron storm water pipe

Furnish/Install grated access platform from existing grade to valve

Oval

Rectangle

Line

INSTALL

Furnish/Install new sign (See Appendix B for details)

Furnish/Install grated access platform from existing grade to valve

Furnish/Install new sign

SPILL

CONTAINMENT

VALVE

Font: Helvetica Neue

Sign backing Material: Aluminum

Background: “Oralite 5700-080 Engineer grade, color braun” reflective brown vinyl, or similar

Lettering: “Oralite 5700-010 Engineer grade, color white” reflective white vinyl, or similar

Format: Center vertically and horizontally

Width=24 inches

H ei gh t= in ch es

Slide Number 1

STATEMENT OF WORK

PROJECT NO: KNMD240008

REPLACE RAMP STORMWATER CONTAINMENT VALVE

JBPHH, HI

154th Civil Engineering Squadron

29 April 2024

Hawaii Air National Guard 154th Wing Guard

Bldg 3392 Hickam Air Force Base, Oahu, Hawai‘i

PROJECT NO: KNMD240008- REPLACE RAMP STORMWATER

CONTAINMENT VALVE

SCOPE: This project requires all labor, tools, equipment, transportation, and supervision; as required for the project elements as described for the following work:

Scope includes: Contractor shall remove & dispose of existing gate valve, electronic actuator, and structural supports. Furnish and install new manual valve, metal access platform, and sign with stand.

Background: All stormwater drainage from a nearby aircraft parking ramp is collected and is discharged through a valved, ductile iron drain pipe. The existing valve needs to be replaced. Photos are attached in Appendix A. Actual dimensions and material type to be verified by contractor during site walk.

All work shall be completed as indicated on this SOW, the Contract drawings and in accordance with specifications and codes. The Contractor must coordinate with the 154 CES to access the work site as well as coordinate with the 154 CES environmental section for any hazardous materials storage/disposal.

It will be the responsibility of the Contractor to restore the facilities to their original condition if any damage occurs during construction.

LOCATION: This project is located on the Hawaii Air National Guard Campus Aircraft Parking Ramp, JBPHH/Hickam AFB, HI 96853.

NORMAL HOURS OF OPERATION: 6:00 AM – 4:30 PM, Monday through Friday. The field investigation and subsequent construction can be accomplished anytime during these hours unless the base is closed for a holiday and 5-4-9 “Down Mondays” (Schedule can be provided upon request). Prior coordination, via Contracting Officer is required.

Contractor shall comply with the following regulations, codes, and any sub-codes contained therein:

ASTM

National Fire Code

NARA

NFPA

OSHA

ANSI

EPA

Labor and Industry Standards National Electric Code (commercial and residential building codes are applicable) ANGETL 15-01, Air National Guard Design Policy ANGETL 15-01-04, Mechanical Engineering DD 254 Handbook, HQDA G-2 Contract Documents

References:

• MATOC Div 1

• AFI 10-701 24 July 2019 (OPSEC)

• Appendix C (OPSEC)

• UFGS Division 00 Section 01000 (General Requirements)

• UFGS Division 01 Section 015719.0120 (Environmental Requirements)

• AFI34-266

• UFC Division 9 sections 096813 and 096519

• UFC 3-600-01

• UFC 3-410-01

• Resiliency Center Requirements (Appendix A)

Contractor shall field verify all dimensions prior to bidding. Contractor will provide qualified onsite Supervision with proof of 5-years minimum experience, managing similar type and size projects, for approval, prior to commencement of work.

ADMINISTRATIVE REQUIREMENTS:

Contractor will be required to file and attain the following approvals prior to project mobilization:

1. Contractor shall be responsible for obtaining base passes for all employees to include and associated subcontractors. All contract employees shall be subjected to backgrounds checks before base passes are issued and shall follow all base security procedures. A temporary construction waiver for the duration of the project.

2. Project shall commence not later than thirty (30) calendar days after Notice to Proceed (NTP) and shall be completed within One hundred and twenty (120) calendar days.

3. Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS), or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative.

http://jko.jten.mil/

4. Contractor shall be responsible for obtaining and submitting Operation Security training (OPSEC) certificates of completion for all contractors and subcontractors. The required training can be completed online at https://www.cdse.edu/catalog/elearning/GS130.html

OPSEC Control Plan (OCP): All contractors (including subcontractors) identified in the Operations Security (OPSEC) Plan under Appendix C of the Statement of Work shall supplement their current security practices by requiring any personnel involved in executing the KNMD230008 contract to complete Government-sponsored and administered Operations Security (OPSEC) training. Upon contract award, all identified contractors (including subcontractors) shall sign the contractor's conformance statement contained within the Operations Security (OPSEC) Plan and submit it to the [Government agency] contracting officer thereby acknowledging that they will meet the requirements of the KNMD230008 PMO generated OPSEC Plan. The contractor specialist security officer (CSSO) shall contact the contracting officer or designated contracting officer's representative (COR) in accordance with the OPSEC Plan to schedule key employees to attend the Government-sponsored OPSEC training.

The contractor must immediately notify the Government upon the discovery of any nonconformance with the OPSEC Plan.

PRINCIPLE ELEMENTS OF WORK:

The Contractor shall field verify all dimensions, materials required, and locations prior to bidding.

1. Remove/dispose existing gate valve

a. Terminate wires, cap existing electrical conduit flush with existing grade

b. Remove existing structural supports, junction boxes, and controls

2. Furnish/install new valve

a. Install new valve onto existing ductile iron pipe

b. Valve shall be serviceable, manual (hand operated), and able to be actuated with no tools required

c. Install fitting to allow contained water to be pumped from above

3. Furnish/install new metal platform accessway and sign

a. Install metal grated platform flush with existing concrete to provide access to valve

b. Platform supports shall be strut type material (Unistrut or similar)

c. Metal strut and fasteners shall be uniform material and corrosion resistant (316 stainless steel or galvanized). If galvanized, material will be painted.

d. Install metal sign near valve with dimensions approx. 18”X24”. Reflective vinyl shall be used. Sign will read “SPILL CONTAINMENT VALVE” See Appendix B for sign specifications.

https://www.cdse.edu/catalog/elearning/GS130.html

General Notes:

a. All work will be accomplished in a clean, safe manner with quality workmanship in accordance with accepted Government and construction industry standards & practices.

b. The Contractor shall be responsible for verification of all quantities and dimensions prior to commencement of work.

c. All materials and/or equipment shall be of high quality, installed in accordance with manufacture’s recommendations and accomplished by workman skilled in this type of work, using standard trade practices.

d. There shall be no deviations or substitutions without prior Government approval. Unless indicated otherwise, all Equipment and Material shall be new, undamaged and meet the requirements of Underwriter's Laboratories, Inc. (UL). Where UL requirements are not applicable, equipment and material shall be identified as such by Contractor and approved by Owner before purchase and installation.

e. All products and materials/equipment installed shall be approved by AF Form 3000 material approval submittal.

DESIGN SUBMISSIONS (DESIGN NOT REQUIRED FOR THIS PROJECT

Two (2) submissions are required: a draft submission and a final (100% design) submission. The project PE must review the 100% design submission of plans, specifications, submittal register and certify in writing that the design is in compliance with this UFC and all applicable criteria. This certification letter must be submitted with the 100% submission.

Level of Development: In addition to other submission requirements, which may be specified in this contract, the following is required. The draft submission shall depict the program of requirements. The final submission shall include all disciplines required for the project.

Drawings: Sheets shall include, but not be limited to, architectural, structural, mechanical, fire protection, electrical, and life safety drawings.

Calculations: Calculations shall be provided by the contractor.

Registration Seals: At the Final Document Submission each drawing, shop drawing and submitted specification and calculation document shall be signed by, bear the seal of, and show the State Certificate Number of the Architect and/or Engineer who prepared the document and/or is responsible for its preparation.

Quality Control Plan (QCP): The QCP shall be submitted to the Government as a complete document which addresses all types of inspections/tests for work covered by the Final Document submissions.

Content: For each performance and installation requirement, the QCP shall clearly identify:

• Item/system to be tested,

• Exact test(s) to be performed,

• Measured parameters,

• Inspection/testing organization, and

• The stage of construction development when tests are to be performed.

• Each inspection/test shall be included in the overall construction schedule. The Contractor is not relieved from required performance tests should these not be included in the plan. The QCP is intended to document those inspections/tests necessary to assure the Government that product delivery, quality and performance are as required. It also serves as an inspection coordination tool between the Contractor and the Government. The QCP shall be prepared and submitted to the Government for acceptance during final design development.

Updating: During construction, the Contractor must update the QCP if any changes are necessary due to any changes or schedule constraints. The Government's Contracting Officer and Contracting Officer's Representative (COR) must be notified immediately by the contractor of any schedule and/or procedural changes.

Specifications/Calculations: Calculations shall be titled with each analysis clearly indicating subject/problem being studied, applied references, assumptions, and analysis of answer. All numerical references to length, temperature, pressure, energy, mass, weight, work, power, etc. shall be presented in English units.

Drawings: Drawing levels of detail and quality of representation shall adhere to the AIA guideline "Architectural Graphic Standards" and A/E/C CAD Standard Release 6.0 All original drawings shall be at least 11” x 17”, with each sheet offering North-arrows, Key Plans and graphic scales.

Minimum lettering height shall be 0.4 centimeters (5/32 inch). All numerical references to length, temperature, pressure, energy, mass, weight, work, power, etc. shall be presented in metric units with English units immediately following in brackets. Site/Floor layout and Elevations shall be at least 1:100 (1/8" = 1'0") scale.

Quantities: The Contractor shall provide the Government via DoD SAFE https://safe.apps.mil/ electronic copies of all drawings, specifications, calculations, etc. for each required submission.

User guide for DoD SAFE is located at https://safe.apps.mil/.

Procedures: Design submissions shall be made directly to the Contracting Officer and COR Submissions shall be made in accordance with the schedule represented within the Contractor's accepted schedule, having an allowance that the Government will take two (2) weeks to review each submission, and respond to the contractor with comments or acceptance.

DESIGN/SUBMISSION REVIEWS

https://safe.apps.mil/ https://safe.apps.mil/

Reviews will be made by the Contracting Officer and COR. As part of its review, the Government may offer submission reviews to other governing functional managers.

Review Period: The Government shall be allowed two (2) weeks to review these submission materials from the date of receipt from the contractor.

Purpose: The Government will review Contractor design submissions to verify adherence to contract requirements. Design reviews by the Government are not to be interpreted as resulting in an approval of the Contractor's apparent progress toward meeting contract requirements but are intended to discover any information which can be brought to the Contractor's attention which might prevent costly errors and misdirection. The Contractor shall remain completely responsible for designing, constructing the project in full compliance with the requirements of this contract.

Resolution of Comments: The Contractor shall resolve all design review comments in writing, indicating one of the following:

• Adoption and action taken,

• Adoption with Modifications and action taken,

• Alternative Resolution and action taken, or

• Rejection

In cases other than unqualified adoption, the Contractor shall provide a statement as to why the reviewer's objection and/or recommendation are inappropriate. Design review comments shall not relieve the Contractor from compliance with terms and conditions of this contract. Contractor's comment resolution shall be transmitted to the Government within 14 calendar days of comment receipt.

SHOP DRAWINGS/PRODUCT DATA

Submissions: Shop Drawing/product data submissions to the Government shall be made after review and approval by the Contractor's designer of record. This is in addition to and separate from specification submission material. Product data shall be delivered to the Government within 30 calendar days following the Government's review of Final Document design and/or the Contractor's establishment of subcontract agreements to provide involved work: Shop drawings shall be provided within 60 days of these occurrences. Shop drawing and product data submissions shall be made to the Contracting Officer and the Contracting Officer's Representative in an electronic format.

Material samples shall be sent to USPFO-HI and HIANG BCE offices.

Reviews: Reviews of shop drawings and product data by the Government are not to be interpreted as an approval or acceptance of the Contractor's selections or progress toward meeting contract requirements but are intended to discover problems/errors which may avoid costly redirection during construction. The Contractor shall remain completely responsible for design and construction in accordance with contract requirements. The Government shall be allowed two (2) weeks to review these submission materials from the date of receipt from the contractor.

Changes: Should shop drawing and/or product changes take place after initial Government review, the Contractor shall resubmit the altered product data material and shop drawings within two (2) weeks of the change.

Manuals: The Contractor shall combine all product data submission material into hard copy manuals for reference during all phases of construction. Shop drawings shall be bound with product data or separately bound in drawing racks. The Contractor shall maintain duplicate copies for the Government.

INSPECTIONS AND TESTS

The Contractor shall perform inspections and tests throughout the design and construction process, including: design support (existing conditions/needs assessments), construction installation (placement/qualification measurements), and final inspections/tests (commissioning/performance certification). Periodic "Quantity" inspections shall also be conducted to support progress payment requests.

Government Witness: All inspections and tests called for in this RFP and/or required to verify documented contract assumptions, to establish work accomplishment, or to certify performance attainment shall be witnessed by the Government and coordinated through the Quality Control Plan (QCP). The contractor shall notify the Contracting Officer in writing at least two (2) weeks prior to conducting.

SITE MAINTENANCE

The contractor shall dispose of all trash and debris generated during the contract. Disposal shall be by sanitary landfill or other approved methods and shall conform to all local, state, and federal & JBPHH guidelines and regulations.

The contractor shall store all refuse in appropriate trash containers on the jobsite. Location of a dumpster at the site shall be as directed by the Contracting Officer or Contracting Officer Representative. The dumpster shall be covered to prevent possible use by base personnel. The contractor shall have all refuse removal trucks covered and secured prior to entering or leaving the jobsite. If any materials are observed falling off the trucks, the truck shall be stopped and reloaded to prevent damage. The contractor shall bear the monetary responsibility to repair all damage associated with falling debris. The contractor’s dumpster shall be removed prior to Final Inspection.

The contractor shall repair any damage the dumpster causes to concrete, asphalt paving or lawns.

All mud, dirt, debris, foreign objects, or spills of any kind from contractor operations (including subcontractors and suppliers) on the aircraft parking apron or streets and parking lots used as access to the work or staging areas, shall be cleaned off the same day. Taxiways, runways, parking aprons, and hard surfaces used as access to the work or staging areas shall be kept clean at all times by the contractor.

The base refuse contract supplies dumpsters for Government produced refuse only. The contractor shall not dump refuse from this project in the Government dumpsters. If the Contracting Officer discovers project refuse in Government dumpsters, he may instruct the contractor to immediately remove the refuse, or have Government resources remove it at the contractor’s expense.

Protection of Contractor’s Equipment: All contractor supplied equipment is the sole responsibility of the contractor. The Government is not liable for the theft, vandalism, or damage of any contractor supplies, equipment or property. The contractor shall secure his materials and protect all equipment from damage. Any equipment/material the contractor removes and which requires reinstallation as part of the job requirements shall be the responsibility of the contractor.

WARRANTY

In addition to any other warranties in this contract, work performed under this contract shall conform to the contract requirements and is free of any defect in equipment, material, or workmanship performed by the Contractor or any subcontractor or supplier at any tier. This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date that the Government takes possession.

The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of (1) The Contractor’s failure to conform to contract requirements; (2) Any defect of equipment, material or workmanship; or (3) Contractor negligence. The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause.

With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall obtain all warranties that would be given in normal commercial practice: Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and enforce all warranties for the benefit of the Government, if directed by the Contracting Officer. In the event the Contractor’s warranty has expired, the Government may bring suit at its expense to enforce a subcontractor, manufacturer or supplier warranty.

SUBMITTALS

Contractor shall provide a design including “sealed” drawings, “sealed” calculations and specifications for review to ensure compliance with this SOW. Materials that do not comply with criteria listed in this SOW may be considered non-adherent or unacceptable. Non-adherent or unacceptable materials shall not be used in the performance of this SOW. All deviations from this statement of work must be specifically requested in writing by the contractor and receive formal acceptance from the Contracting Officer before commencing with installation or work. Design Build contractor shall provide a completed master submittal schedule in AF Form 66 format for review and acceptance by the Contracting Officer within ten days of the receipt of the Notice to Proceed.

Submittals shall include, but not be limited to

- Product data sheet for valve

- Product data sheet for strut and platform

- Paint sample and Safety Data Sheet (if used)

- Shop drawing from sign maker

- Operations and maintenance documents from valve manufacturer

CLOSE OUT DELIVERABLES

Closeout pursuant to ANG Engineering Technical Letter (ANGETL) 09-11, Project Closeout Process and any other requirements called out by the Contracting Officer.

APPENDIX A- Site photos (see attached to this PDF document) APPENDIX B- Sign Specifications (attached to this PDF document)

APPENDIX C

GENERAL CONTRACTOR OPSEC REQUIREMENTS

During the course of this contract, in addition to those restrictions, instructions and guidelines delineated in the contract Statement of Work and/or other references provided, the contractor will adhere to the following minimum requirements in support of the 154 CES OPSEC Program:

Antiterrorism Awareness Level I Training (AT Level I). This standard language is for contractor employees with an area of performance within a US Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS), or Joint Knowledge Online at http://jko.jten.mil. Tracking for each contractor or subcontractor employee is the responsibility of the COR or unit AT Representative

a. Awareness Training. Initial training may be provided by both computer-based training and live training. OPSEC training is required initially within 90 days of assignment and annually thereafter.

Each individual will submit a certificate of training within 30 days of signing this document. The computer-based training can be found through the following link:

https://www.cdse.edu/catalog/elearning/GS130.html The contractor is required to maintain individual training records for compliance purposes.

b. Introduction of personnel electronic devices into government spaces, laptops, tablet PCs, cellular phones, cameras, recording devices, and data recording/storage devices is STRICTLY controlled and forbidden in most cases. Company issued equipment required for the performance of work must be approved by the Contracting Officer Representative (COR). Photography and recording is not allowed except for official use and by permit only. (Unless otherwise stipulated in the contract, contact the COR for approval.) Photographs will be reviewed by Security to ensure sensitive and/or classified information is not revealed. Secure electronic transmission and storage of critical information. Critical information must be transmitted and stored in accordance with the SOW.

Secure storage of hardcopy critical information. Critical information in hardcopy form must be stored in secure areas and/or containers in accordance with the SOW.

c. Contractor personnel shall not discuss government operations in public or over unprotected or unencrypted communications. Official Business, controlled unclassified information may only be transmitted as directed in the SOW.

d. The Contractor shall not post to company websites, publications, newsletters or other media any images, data or information that reveal sensitive government operations, personnel, equipment, and/or classified or controlled unclassified information. When in doubt, company press releases related to this contract should be coordinated through the COR. Pre-publication procedures are established to ensure no public release concerning program information occurs without the prior written approval of the OPSEC Coordinator.

e. Because observation of events, operations, physical changes, etc. may reveal National Security information, specific restrictions are needed to preclude unintentional release of this information to http://jko.jten.mil/ https://www.cdse.edu/catalog/elearning/GS130.html unauthorized parties. (Unauthorized disclosure and transfer of National Security Information is punishable under 18 USC § 793.) Therefore, contractor personnel shall not disclose to unauthorized third parties, post to unofficial sites (including Social Networking sites) any images, data or information, or observed events that reveal sensitive government operations, personnel, equipment, including, but not limited to:

(1) Tactics, techniques and procedures, production or work schedules, any visible or concealed modifications, upgrades, additions to aircraft, weapons or equipment; increases, change, or decreases in work/deployment frequency or government personnel, vehicle, vessel or aircraft movements;

specialized equipment orders, deliveries, shipments, etc., unauthorized disclosures and attempts to solicit this type of information by unauthorized third parties or others not affiliated with this contract shall be reported to the COR.

f. Service. Non-Disclosure requirements remain in effect during the duration of this contract and indefinitely thereafter. See Annex A.

g. Government issued badges, identification shall be removed and/or concealed from plain sight when off station and shall not be left in vehicles or unprotected. Badges and passes may not be duplicated or copied or loaned to others. Lost or stolen identification badges, vehicle passes etc. will be immediately reported to the COR.

h. Contract personnel must mark and protect related internal production schedules, deliverables, inventories and shortages and identified vulnerabilities related to production of government material. Internal company markings e.g., Business Sensitive, etc., are appropriate for identifying the aforementioned as sensitive information. Specific Government-provided information, drawings etc., will be protected in accordance with guidance in applicable paragraphs of the SOW/PWS and clauses included in the solicitation/contract.

i. All government information must be destroyed at contract termination or returned to the government at the government’s discretion. Critical information must be disposed of by cross-cut shredder or burning. Critical information shall not be disposed of in trash receptacles.

j. Visitor Control. All visitors are required to process through established checkpoints for verification of identity, citizenship, personnel security clearances, appropriate certification of purpose of visit, issuance of badges, and inspection of articles being brought into and out of the facilities and other such measures to assure proper visitor control.

k. Escort Procedures. Escorts for visitors shall be advised of proper escort procedures, limitation on disclosure, and other applicable controls involved in the visit.

l. Unauthorized Personnel. Program personnel shall be alerted when visitors or other unauthorized personnel are admitted to work areas. Personnel shall refrain from inadvertent release of information by visual and aural means when visitors are present. Activities of visitors and nonassigned personnel in the program areas shall be observed to determine that their presence is required by business needs and that no suspicious activities are detected which may pose a threat to the security of information.

m. Conference Rooms. During meetings, attendees will be reminded of conference room procedures to be followed when discussing critical information.

SITE MAINTENANCE

Contractor shall provide a design including “sealed” drawings, “sealed” calculations and specifications for review to ensure compliance with this SOW. Materials that do not comply with criteria listed in this SOW may be considered non-adherent or una...

Submittals shall include, but not be limited to

- Product data sheet for valve

- Product data sheet for strut and platform

- Paint sample and Safety Data Sheet (if used)

- Shop drawing from sign maker

- Operations and maintenance documents from valve manufacturer

CLOSE OUT DELIVERABLES

Closeout pursuant to ANG Engineering Technical Letter (ANGETL) 09-11, Project Closeout Process and any other requirements called out by the Contracting Officer.

procedures to be followed when discussing critical information.

File details come from the government source that posted it. Updated .