RFI list BOM for building 117.pdf
PDF 110 KB Posted
- Attached to
- Construction building material purchase for building renovation located on Camp Murray, WA
- Solicitation number
- W50S9E26QA003
- Issued by
-
Department of the Army National Guard
About this file
This document contains Questions and Answers (Q&A) for a 114 Bill of Materials (BOM) procurement related to construction and renovation materials and supplies.
The clarifications address packaging and quantity discrepancies for HVAC materials (4" R-6 insulated flexible duct instead of 3"), copper fittings (3/4" or 3/8" slip couplings), joint compound (4.5-gallon buckets acceptable if total volume meets or exceeds requirement), fiberglass insulation (2,600 sq ft acceptable instead of 2,340 sq ft), and Stone Plastic Composite flooring (23.64 sq ft per box, 16 boxes totaling 378.24 sq ft). Masking materials clarification confirms that 12" and 48" masking film can be combined. For signage, the "Room and Price Fitness Center" signage requires 5" letters in a font similar to Friz Quadrata. Additional clarifications specify counter dimensions of 3'11" with a 19" round sink; disregard primer coat specifications; 72" x 84" double metal exterior doors (quantity of 2); exterior trim specifications including J-Channel (220 LF), siding trim (80 LF), base guard (40 LF), and head flashing (18 LF); weatherproofing materials with specific quantities (house wrap, flashing tape, polyurethane sealant, and expanding foam); masking materials totaling 200' widths at both 12" and 48", 60 yards of 2" tape in 10 rolls, and canvas drop cloths (9'x12', quantity 10); copper couplings (4 of each 3/4" and 3/8" size); 25' of 18/5 wire; and pipe fittings (15' of pipe, 8 ninety-degree elbows, 4 couplings). Item 142 requesting custom signage is disregarded as custom signs will be ordered at project completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bldg_117_Proposal_v1.pdf | ||
| W50S9E26QA003.pdf | ||
| BOM_Bldg 114 Gym Renovation Pricing Request.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI’s for 114 BOM
• Q1: Clarification: 3" R-6 Insulated Flexible Duct, 25' - what we have here is the smallest size of 4" 25 ft. R-6 Insulated Round Flexible Duct?
• A1: Yes, it should be 4”
• Q2: Copper Couplings (3/4" and 3/8" slip fittings): Are these 3/4" and 3/8" each or are they 3/4" or 3/8"?
• A2: ¾” or 3/8”
• Q3: Joint Compound, Pre-mixed, 5-gal bucket: What we have in our packaging is 4.5 Gal.
• A3: This is fine as long as we get the same or slightly more total (5 gal x 5=25 gal, 4.5 gal x 6= 27gal
• Q4: Vinyl-Faced Fiberglass Insulation: We have individual packs of 40 sq ft (15 in W x 32 ft L) individual packs, totaling 2,600 sq ft instead of 2,340 sq ft
• A4: Yes that is acceptable
• Q5: Stone Plastic Composite (SPC) flooring: What we have in our packaging is 23.64 sq. ft. per box, so we labelled it per box. 16 boxes total, 378.24 sq ft.
• A5: Yes that is acceptable
• Q6: Masking materials: painter's tape, 12" and 48" masking film for windows/doors, and drop cloths. We want to clarify if the two film sizes should be separated as they were in separate orders.
• A6: They can be together
• Q7: the Room and Price Fitness Center signage, I would like to confirm your preferred size and font
• A7: 5” letters. Not sure of the font, AI says “Friz Quadrata.” However, it looks a little different to
me. Example below
Q8: Item 9, What are the dimensions of the counter requested for the wall hung sink w/counter?
A8: Current dimensions of counter are 3’11” with a 19” round sink. Per current drawings.
Q9: Item 31, Kilz primer does not specify any variation of its Primer as 1 coat, what is meant by this requirement? Same with item 38 request for paint, two coats.
A9: Disregard 1 coat verbiage
Q10: Item 50, This is requested as a “lot” but it is not clear how many of each item is being requested as well as the requested dimensions (are these intended for metal interior door listed above)?
A10: 2 of each. It is a 72” x 84” double metal exterior door.
Q11: Item 51, What dimensions/quantities are being requested for each item?
A11: J-Channel 220 LF (24 pieces of 10'); Siding Trim 80 LF (8 pieces of 10' or 12'); Base Guard 40 LF (4 pieces of 10'); Head Flashing 18 LF (3 pieces of 10')
Q12: Item 53, Color matched to what?
A12: Disregard color match.
Q13: Item 54, This appears to be a list of items, but only states “5 rolls” as the requested quantities when some items do not come in rolls, they come in cartridges, panels, etc.
A13: Weatherproofing (House Wrap) 1 Roll 9' x 100' (900 sq. ft.) , Flashing Tape (Zip/Tyvek) 3 Rolls 90' per roll; Polyurethane Sealant 12 Tubes 10.1 oz Cartridge, Expanding Foam (Low Expansion) 6 Cans 24 oz Cans
Q14: Item 58, This “Lot”, is unclear on how many of each items are being requested.
A14: 12” masking @ 200’, 48” masking @ 200’, 2” masking tape 60 yards @ 10 rolls, canvas drop cloth 9’x12’ @ qty 10.
Q15: Item 139, Is the end user asking for 4 ea 3/4in and 4 ea 3/8in couplings, or two each to have a total of 4?
A15: 4 of each size
Q16: Item 140, same question as above?
A16: 25’ of 18/5 wire
Q17: Item 141, The requirement is unclear, what is being requested in the way of “& fittings”?
A17: 15’ of pipe, 8- 90 deg elbows, 4-couplings
Q18: Item 142, what kind of sign, (color, size, verbiage, etc)?
A18: Disregard this request, custom signs will be ordered at end of project.