B08 143LRS P3 VMS Lifts Combo - Q and A Rev 1.docx
DOCX document 119 KB Posted
- Attached to
- 143LRS P3 Vehicle Maintenance Equipment – Lifts
- Solicitation number
- W50S94-22-Q-0009
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08 143LRS P3 VMS Lifts Combo - Q and A.docx | DOCX document | |
| W50S94-22-Q-0009 CLINs.xlsx | XLSX spreadsheet | |
| B08 143LRS P3 VMS W50S94-22-Q-0009 Combo Rev1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RHODE ISLAND AIR NATIONAL GUARD
143d MISSION SUPPORT CONTRACTING
1 HERCULES DRIVE
NORTH KINGSTOWN, RI 02852-7502
Questions and Answers for Solicitation W50S94-22-Q-0009 143LRS P3 Vehicle Maintenance Lifts
1. Q: Will the contractor be responsible for providing an electrician to supply power to the vehicle lifts and if so is the building currently wired for additional equipment from the breaker box to the location of lift in service area.
A: The contractor will not be responsible for providing an electrician to supply power. All wiring will be accomplished by the RIANG Civil Engineer Squadron prior to delivery of lifts.
2. Q: Are we allowed to quote only some items, for instance CLIN 0003?
A: Interested vendors must provide quotes for all requested items to be considered responsive.
3. Q: What is the period of Performance?
A: RIANG is requesting delivery 30-90 days after receipt of order. The solicitation is published subject to availability of funds. If funding is received, award will be made on or before 30 September 2022.
4. Q: Will this be a new install at an empty location? Are there any lifts that will need to be uninstalled or disposed?
A: This will be a new install in an empty location – there are no lifts to uninstall or dispose of.
5. Q: Could you provide bay size information like: height from the lowest ceiling obstruction, length and width of bay, and garage door dimensions?
A: The height of the lowest obstruction from the ceiling is 14ft. The width of the bay door is 11.5 ft.