This document provides the statement of work for a federal construction contract to repair Building 1 at Punta Salinas Radar Site in Puerto Rico. The project includes repairing and upgrading the building envelope, roof, electrical and communications infrastructure, HVAC systems, interior and exterior finishes, doors, windows, ceilings, flooring, and bathrooms. The place of performance is Punta Salinas Radar Site in Toa Baja, Puerto Rico. The contract completion time is 180 calendar days. The North American Industry Classification System code is 236220 and this opportunity is set aside for small businesses. The pre-solicitation for the invitation for bid was issued on or around May 14, 2020, with a site visit scheduled for May 11, 2020. The bid opening will take place on June 15, 2020 at the radar site address. Interested contractors must register in the System for Award Management and can access solicitation documents on Contract Opportunities. The evaluation will be based on price and award will be made without discussions.

View the file

Other files

File Type Posted
BLDG 1 RPR Drawings.pdf PDF
DD369 - Police Record Check.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Repair Building 1 TVAD202204

156AW Muñiz Air National Guard Base (ANGB), Puerto Rico (PR)

1.0 GENERAL

1.1 Scope. The Contractor shall provide supervision, transportation, labor, materials, equipment, fuel and any other needed materials and quality control necessary, except as specified in Paragraph 3.0 as Government Furnished items, to perform testing of LBP and ACM, mitigation and repairs of

Building 1, located in Muñiz Air Base, Carolina, PR, as specified in this SOW.

1.2 Background. Building 1 was constructed in two phases. Phase I was constructed as open space office or building area space. Phase II was an addition of a kitchen area to turn the entire facility into a Mess or Dinning Hall. This facility has not received any significant upgrades in many years. The primary purpose of the project is to convert this facility into open space office area for the new Combat Communications Mission. This will require repair and upgrade to the entire building envelope inside and outside, roof (new roof treatment system) and entire interior of the building. New Electrical Room, Communications Room, and entire electrical infrastructure (Power distribution, Lighting distribution, Fire Alarm and Detection systems, electrical ground system, new finishes inside and outside, doors, roof system, windows, reflected celling, HVAC units, floor tiles and bathroom areas. More details of the renovation are below. Some of the requirements of this SOW are design-built as specified.

1.3 Period of Performance (PoP). The Period of Performance shall be 120 calendar days (4 months).

1.4 General Information.

1.4.1 Quality Control (QC). The contractor shall develop and maintain an effective QC Plan

(QCP) to ensure services are performed in accordance with this SOW. The contractor shall develop and implement procedures to identify, prevent, and ensure no recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements

Summary. A final QCP shall be submitted to the Contracting Officer Representative (COR)

NLT 10 days after contract award. After acceptance of the QCP, the contractor shall obtain the

Contracting Officer’s (KO) acceptance in writing of any proposed changes to its QCP.

1.4.2 Quality Assurance (QA). The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).

1.4.3 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these days.

1.4.3.1 New Year’s Day

1.4.3.2 Martin Luther King Jr.’s Birthday

1.4.3.3 President’s Day

1.4.3.4 Memorial Day

1.4.3.5 Independence Day

1.4.3.6 Labor Day

1.4.3.7 Columbus Day

1.4.3.8 Veteran’s Day

1.4.3.9 Thanksgiving Day

1.4.3.10 Christmas Day

1.4.4 Place and Performance of Services. The contractor shall provide services between the hours of 0730-1600 on Monday through Friday, except on recognized US holidays or when the

Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at

Muñiz Air Base, Carolina, Puerto Rico 00979. The contractor, shall at all times, maintain an adequate work force for the uninterrupted performance of all tasks defined within this SOW when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.

1.4.4.1 Reserved

1.4.4.2 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented. Contractors are not compensated for unexpected closures or delays.

Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.

1.4.4.3 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval. All contractor employees shall carry proper identification with them at all times. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance.

1.4.5 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the installation Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes. The contractor shall coordinate all on-site activity, as required, in conjunction with the COR and the appropriate Muñiz Base representatives.

Installation Entry Access List (EAL) is required fifteen to thirty (15-30) calendar days ahead for processing, prior to base access approval being granted, along with DD Form 369, Police

Record Check and driver license copy.

1.4.5.1 Reserved.

1.4.5.2 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures. Using the National Crime Information Center

Interstate Identification (NCIC-III) and Terrorist Screening Database (TSDB) (Army

Directive 2014- 05/AR 190-13), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a government representative).

1.4.5.3 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that any time contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.

1.4.5.4 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoDD 5400.11, Department of Defense Privacy

Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.

1.4.5.5 AT Level 1 Awareness Training (AT). All contractor employees requiring access to

Army Installations, facilities, and controlled access areas shall complete Level 1 AT within

10 calendar days after contract start date and within 10 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level 1 AT is available at http://jko.jten.mil/courses/atl1/launch.html.

1.4.6 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.

1.4.6.1 Key Control. This SOW does not require handling of keys or key cards issued by the government.

1.4.7 Special Qualifications. The contractor shall ensure all employees possess all required http://jko.jten.mil/courses/atl1/launch.html licenses for operating heavy equipment, welding licenses, Material Handling Equipment (MHE) i.e. Forklift and any others, in the performance of this contract. The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified and qualified to provide services.

1.4.8 Post Award Conference/Periodic Progress Meetings. The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations

Subpart 42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the

Government views the contractor’s performance and the contractor shall apprise the

Government of problems, if any, being experienced. The contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.

1.4.9 Contract Manager (CM). The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO within 3 calendar days after contract award. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.

1.4.10 Identification of Contractor Employees. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on email) and dealings with Government or non- Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicle passes shall be returned to the

COR within the 10 days of an employee’s departure) or contract completion.

1.4.11 Combating Trafficking in Persons. The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the

United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.Contractor shall complete the following online training within 10 calendar days after contract award: Course number is N-

US189-HB; available at: http://jko.jten.mil/.

1.4.12 Reserved.

1.4.13 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the

Government with all rights and privileges of ownership /copyright belonging exclusively to the

Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy 10 calendar days after contract completion. This right does not abrogate any other Government rights.

1.4.14 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive have access to or participate in the development of proprietary or source selection. In addition to substantial (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.). Perform evaluation services, which may create current or subsequent OCIs, as defined in FAR Subpart http://jko.jten.mil/

9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.4.15 Safety Plan: Provide a safety plan to the COR within 10 calendar days after contract award.

1.4.16 Environmental Plan: Provide an environmental plan to the COR within 10 calendar days after contract award.

1.4.17 Waste Management Plan: The Contractor shall submit a preliminary Waste Management

Plan and a final Waste Management Plan. The preliminary waste management plan and final

Waste Management Plan should address key components (see Appendix F1 for key components). The contractor shall submit to the COR for approval prior to commencement of demolition services, IAW UFGS 01 74 19, para 1.6 and UFGS 02 81 00, para 3.1.2. The project waste diversion goal is 60%. Approval of the contractor’s plan will not relieve the contractor of responsibility for compliance with applicable environmental regulations or meeting project cumulative waste diversion requirement. This plan shall be coordinated with the installation waste management plan so there are no conflicts. This plan may be incorporated with the work plan. Disposal slips from landfill and/or recycler must be submitted to the Base Environmental

Management Office to report amounts of debris landfilled or recycled.

1.4.18 Health and Safety Plan (HSP): The Contractor shall prepare a site-specific HSP to comply with Air Force, Occupational Safety and Health Administration (OSHA), United States

Environmental Protection Agency (USEPA), state PR-OSHA, and local health and safety regulations regarding the proposed work. The contractor shall also submit a HSP that includes worker health and safety practices for the asbestos and lead work activities. The HSP must include valid certificates for each worker that will be involved in the demolition, showing they have completed the Asbestos Hazard Emergency Response Act (AHERA), OSHA, and PR-

OSHA training requirements. The Contractor shall notify the KO and COR within 3 calendar days if a change is required to the HSP. The Contractor shall adhere to USEPA guidelines for designating the appropriate levels of protection needed at the demolition site(s) as applicable.

The Contractor shall maintain and have readily available written certification that the approved

HSP has been reviewed and briefed with all personnel that work at the project site prior to the employee’s start date.

1.4.19 Site Closure Report. The contractor shall prepare and submit to the Base Environmental

Management Office and COR, for review and approval, a draft and final closure report as required for the asbestos and lead abatement permits. Typical processing time is 21 calendar days for the initial review/approval and, if necessary, 14 calendar days for resubmittal review/approval.

2.0 Definitions and Acronyms

2.1 Definitions.

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or services to the government. The term used in this contract refers to the prime. 2.1.2

CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government.

Note: The only individual who can legally bind the government.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S.

Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does

NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5 DELIVERABLE. Anything that can be physically delivered and includes no manufactured things such as meeting minutes or reports.

2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the SOW. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The

Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.

2.2 Acronyms

AEI Army Enterprise Info Structure

AFARS Army Federal Acquisition Regulation Supplement

ANG Air National Guard

AR Army Regulation

AUP Acceptable Use Policy

BBP Better Business Practice

CDM Concept Development Meeting

CFR Code of Federal Regulations

CM Contract Manager

COMSEC Communications Security

CONUS Continental United States

COR Contracting Officer Representative

COTS Commercial-Off-the-Shelf

CUI Controlled Unclassified Information

DA Department of the Army

DD250 Department of Defense Form 250 (Receiving Report)

DD254 Department of Defense Contract Security Requirement List

DFARS Defense Federal Acquisition Regulation Supplement

DMDC Defense Manpower Data Center

DOD Department of Defense

FAR Federal Acquisition Regulation

FEMA Federal Emergency Management Agency

FPCON Force Protection Condition

FPM Final Planning Meeting

HQDA Headquarter Department of Army

IA Information Assurance

IPM Initial Planning Meeting

IT Information Technology

JTR Joint Travel Regulation

JTF Joint Task Force

KO Contracting Officer

MHE Material Handling Equipment

MOA Memorandum of Agreement

MPM Mid-Planning Meeting

MSR Monthly Status Report

NACI National Agency Check Inquires

NGB National Guard Bureau

NLT Not Later Than

OCI Organizational Conflict of Interest

OCONUS Outside Continental United States

ODC Other Direct Costs

OPSEC Operations Security

PCO Procuring Contracting Officer

PII Protection of Personally Identifiable Information

POC Point of Contact

PRS Performance Requirements Summary

SOW SCOPE of Work

QA Quality Assurance

QAP Quality Assurance Program

QASP Quality Assurance Surveillance Plan

QC Quality Control

QCP Quality Control Program

SME Subject Matter Experts

TAR Travel Authorization Request

TE Technical Exhibit

WWAF-RA Wide Area Workflow-Receipt and Acceptance

3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S). The

Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.

3.1 Property: Government will authorize contractor to an area for material storage and temporary office.

3.2 Materials: None.

3.3 Equipment: None.

3.4 Services: None.

3.5 Utilities: None.

4.0 Contractor Furnished Property, Materials, Equipment and Services (GFP/M/E).

4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph

3.0, the contractor shall furnish everything required to perform these services as indicated in

Paragraph 1.1.

4.2 Bathrooms: The contractor shall provide portable bathrooms for their employees during the period of performance accompanied by its periodical maintenance.

5.0 Requirements. The contractor shall:

5.1 Building Interior:

5.1.1 Contractor is responsible for all required Asbestos and Lead studies. Contractor is also responsible for all required permit state and federal for the removal and disposition of all Asbestos and Lead containing materials. The first phase of the project will be all abatement and environmental requirements before commencing the rest of the project.

5.1.1.1 Floor tile has asbestos containing materials in it; see report attached for amounts and areas. Proper permits and disposition to remove and dispose are requirements of this contract. After tile and asbestos abatement the floor will be, resurface with a self-leveling concrete (6,000psi) for a new floor finish to receive new floor tile installation.

5.1.1.2 Gut the entire interior of the building. Demo all existing utilities to include HVAC, Electrical circuits, Lighting fixtures, reflected celling, floor tile, potable water and sanitary lines, kitchen equipment to include vent conduit on the roof, nonstructural walls, doors, windows and bath rooms to include ceramic tile and fixtures.

5.1.1.3 See drawings for more details on requirements.

5.2 Building Exterior:

5.2.1 Pressure wash and resurface or refinish entire exterior of building and paint with primer and two coats of paint. Contractor is to coordinate with base civil engineering on paint standards and colors. Repair five (5) entrance of the building to include a handicap ramp entrance with handrails on south side and stairs refer to drawings for details. Remove and replace existing handrails. All hand rails will be aluminum similar to existing handrails on building 6 see pictures

5.2.2 See drawings for more details on requirements.

5.3 Building Exterior:

5.3.1 No structural members will be demolish or removed from the building. The building is a one-story structure. All walls, exterior are concrete block. New access ramps will be constructed, stairs repaired and hand rail replaced with corrosion resistant aluminum handrails. Roof penetration where exhaust hood was will be closed with concrete to match existing surroundings.

5.3.2 See drawings for more details on requirements.

5.4 Roof:

5.4.1All roof to include overhangs around the perimeter of the building will be repaired were needed in addition, brought up to original state. Existing roof treatment shall be entirely removed and a new Modified Bitumen Membrane (MB Membrane) roof system will be design-built for this building following the latest UFC 3-110-03.

5.5 HVAC:

5.5.1 The contractor is to procure, install, and commission five (5) HVAC units cassette model split type (3 Tons each) as shown on drawings a gypsum board fascia or frame will be built around the new units. The exterior condensing units are to be placed on a new concrete pad a minimum of 6 inches above the existing exterior ground elevation and tide down to them with stainless steel tensors. New protective removable 4in diameter aluminum bollards are to be installed on the exterior corners of the units. All refrigerant lines are to be insulated and installed in protective aluminum chases from the where they leave the interior of the building to the condensing unit. Exterior unit disconnects are to be sized per unit manufacturer recommendations and NEC requirements. Follow applicable UFC’s.

5.5.2 See drawings for more details on requirements.

5.6 Plumbing:

5.6.1 The building bathroom (Latrine areas will be completely demolish and redone as per drawings provided. All sanitary and potable installation will comply with applicable UFC’s, UFGS’s and local State and Federal codes. Approved and signed drawings by a registered engineer are required as submittals.

5.6.2 See drawings for more details on requirements.

5.7 Fire Alarm and Detection:

5.7.1 System will be design-build following UFC 3-600-1 and NFPA regulations.

Plans approved by a Fire Protection Engineer are required. Fire protection (Wet system (Sprinkler) is not included in this SOW).

5.7.2 Alarm: Contractor is to install a new fire alarm system; to include but not limited to a new panel, annunciator, transmitter and all devices with a new addressable system. All new components should be Monaco compatible and shall comply with NFPA and NGB ETL standards. Contractor is responsible for all testing and integration into the existing base system.

5.8 Electrical:

5.8.1 Contractor is to design and build electrical system capable to accommodate all required electrical systems on the drawings. To include HVAC system, Water heater, LED Lamp fixtures (2’x4’) in the office area and (2’x2’) in bath room areas, receptacles, communications room and main distribution panel and circuit breakers for building main electrical connection. A new main distribution panel and circuit breakers with remote capable reading capable meter will be included, with two additional distribution panels in the electrical room. One for all lighting circuits and receptacles circuits and the other for all HVAC, and other equipment, in-line heavy duty water heater (240V) with variable temperature and COMM room requirements.

Electrical system shall accommodate all electrical loads. Provide new, energy efficient dimmable interior and exterior modern LED lighting fixtures, three and four way switches, occupancy sensors, and controls IAW UFC 3-530-01. Electrical design shall include a lightning protection system; Electrical design shall be approved and signed by a licensed Professional Engineer. Before Electrical, work can begin.

5.8.2 See drawings for more details on requirements.

5.9 Lighting Protection System:

5.9.1 Contractor is to install a complete building lightning suppression system in accordance with the latest version of UFC 3-575-01 and NFPA 780.

5.10 Communications:

5.10.1 Install communications system as required by drawings. Install new LAN drops and cable tray around the inside perimeter of the entire facility entering into the Communications Closet following applicable ETLs and UFGS. The contractor is to provide and install 18” wide by 1 ½” deep (minimum) wall mounted cable tray.

Cable tray height shall be above door opening heights inside suspended celling.

Communications, electrical and 3 storage closets will have up to 4 individual circuits up to 30 AMPS 120V or 240V connections each to be coordinated with the COR during construction. Install IAW ANSI-NECA-BICSI 568-2001.

5.11 Reflected or suspended celling:

5.11.1 Install new Aluminum Degreased finish suspended celling system to include mineral boards to comply with all applicable UFGS, to include bath room areas with moisture and mold resistant system and tiles.

5.12 Windows:

5.12.1 Replace all windows and install new windows as per drawings. Windows will be similar or same model to new windows installed on building 02. Window shall be painted aluminum, safety window and wind resistant tempered glass will include integrated storm shutters rated for Puerto Rico hurricane zone requirements. See attached picture for example.

5.13 Interior finishes:

5.13.1 All walls shall be covered with a metal frame and moisture/mold resistant gypsum board system following applicable UFGS. Floor will be covered with heavy duty and heavy/high traffic Vinyl tile. Bathroom floor will have modern high quality ceramic on all floor and on the walls up to six (6) feet high around the entire bathroom. Shower area will be cover up to the roof. Toilets and shower areas will have handrails to comply with ABA requirements.

5.14 Bathrooms:

5.14.1 Bathroom fixtures will be modern high quality water efficient. Will comply with applicable UFGS. Colors and models are required submittals for approval. All fixtures will be included and not limited to soap dispensers, paper towel dispenser and toilet paper holders mirrors, shelves and fix bench.

5.15 Windows and Doors:

5.15.1 New windows will be the same or similar to new windows at building 02. See attached picture. Door will comply with all applicable UFGS Exterior Doors are all main entrance type interiors doors are closet doors and bath room type. See attached pictures for window model, type and materials required. All main entrance doors will have a weatherproof threshold and frame

5.16 This statement of work does not supersede any Federal Acquisition Regulation stipulations that may appear in this contract.

5.17 The Contractor is subject to all Installation Fire, Safety, Security, Civil Engineer, OPSEC, Traffic Regulations and all applicable Federal and State regulations.

5.17.1 Fire Safety: The Contractor shall comply with all local fire regulations and NFPA 241 during all demolition and construction work. All fire extinguishers required shall be provided and maintained by the contractor, but must be approved for use by the contracting officer prior to use. “Hot-work” operations, those involving welding, soldering, brazing, or torch heating shall not commence before an AF Form 592 is completed and signed by the Fire

Inspector. The contractor shall contact the Fire Department’s inspection section at least one work day prior to hot-work operations for assistance and completing the Form 592. There shall be no open burning of waste materials or debris during this contract.

5.18 The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.

5.19 The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor.

5.20 The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate abatement action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.

5.21 Accident prevention principles must be thoroughly integrated into all operations. Unsafe

Conditions and practices, as identified by the Contracting Officer or designated representative, must be corrected immediately.

5.22 Any and all debris generated by the Contractor’s operations shall be removed from the base.

Solid Waste Management: All waste materials and debris generated by work under this contract shall be processed, handled, transported, stored, and disposed of by the contractor in accordance with all federal, state, local, regulations, and laws. All waste streams will be quantified and reported to the Base Environmental Manager. The Contractor shall be responsible for any permit or fees associated with the use of off-base disposal locations.

5.23 The Contractor shall be liable for any loss, destruction or damage and deterioration to

Government property, including vegetation and landscaping, resulting from Contractor operations.

Any damage to government or personal property shall be repaired or replaced to the Contracting

Officer’s satisfaction at the Contractor’s expense.

5.24 All work under this project shall meet applicable County, Territorial, Federal and Air National

Guard construction codes, regulations and policies.

5.25 Contractor shall coordinate with Contracting Officer to verify the existing site and facility conditions. Any differing conditions shall be notified in writing to request clarification.

5.26 Equipment or fixtures Government Furnished Contractor Installed (GFCI): None anticipated.

5.27 Comply with all Specifications applicable found and included by reference in the www.wbdg.org site. This will include all UFC and UFGS.

5.28 For additional information on drawings and specifications, and for entering the Site premises http://www.wbdg.org/ contact the Base Civil Engineer (BCE) office in Building 25, Muñiz ANG Base telephone (787) 253-

5172, or fax (787) 253-5226 or 7415.

Must request Digging Permit before work start.

5.29 For additional contracting issues will be directed to the Contracting Officer in Building 29, Muñiz ANG Base at telephone (787) 253-5238 or 7438.

Must fill out Base Access Letter before project start.

5.30 For additional Environmental information contact the Environmental Manager Office in

Building 25, Muñiz ANG Base telephone (787) 253-5192, or fax (787) 253-5226 or 7415.

5.31 For additional Safety information contact the Safety Office in Building 22, Muñiz ANG Base telephone at (787) 253-5275

Must request Confine Space Entry AF Form 1024 before work start.

5.32 For additional Bioenvironmental information contact the Bioenvironmental Office in Building

16, Muñiz ANG Base telephone at (787) 253-5265

5.33 For additional Fire information contact the Fire Department in Building 3, Muñiz ANG Base telephone at (787) 253-5222

Must request permit to use open flame equipment or grinders.

5.34 For additional Security information contact the Base Defense Operation Center in Building 2, Muñiz ANG Base telephone at (787) 253-5204

5.35 Contractors must be registered (current) in the System for Award Management (SAM) internet program at: http://www.sam.gov

5.36 All invoices must be submitted using Wide Area Workflow (WAWF) internet program at:

https://wawf.eb.mil

5.37 Contractor will verify status of all invoices My Invoice link at: https://wawf.eb.mil

5.38 Contractor Manpower Reporting Application (CMRA): The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/ Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year

(FY), which runs October 1 through September 30.

5.39 Every day all refuse and remaining materials related to the work will be taken to a refuse container provided by the Contractor.

5.40 Only company cars with distinctive logos posted at passenger and driver doors will be authorized inside Base premises.

5.41 All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.

5.42 At the end of each working day all areas will be clear from equipment, tools and materials.

5.43 Special precautions will be taken at no cost to government to protect base property during the project execution.

5.44 The use of Personal Protective Equipment is mandatory at all time while working on the project.

6.0 Applicable Publications: Publications applicable to this SOW are listed below:

Technical Exhibit 1 Performance Requirements Summary (PRS)

This PRS includes performance objectives the Government will use to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).

Performance Objectives

Performance Standards

Acceptable Quality Levels AQL

Surveillance Method / By Whom

Publication (Chapter/Page)

Date of Publicatio n

Mandatory or Advisory

Website

Federal Acquisition Regulation

Mandatory https://www.acquisition.gov/?q=browsefar or http://farsite.hill.af.mil/

Defense Federal Acquisition Regulation http://www.acq.osd.mil/dpap/dars/dfarspgi/cu rrent/index.html or http://farsite.hill.af.mil/

AR 190-13 The Army Physical Security

February

Mandatory http://www.apd.army.mil/ProductMaps/PubFo rm/AR.aspx

AR 530-1 Operations Security

26 Sep

OK http://armypubs.army.mil/ProductMaps/PubF orm/AR.aspx

DoD 5220.22-M National Industrial Security Program

18 May

OK http://www.dtic.mil/whs/directives/corres/pub 1.html

DG 415-5 General Facilities Design

1 June 2011 Advisory https://www.wbdg.org/FFC/ARMYCOE/NATL GUARD/dg_415_5.pdf

UFC 4-010-01 1 Oct 2013 Mandatory https://pdc.usace.army.mil/library/ufc/4-010- 01/ DOD Min. AT/FP Standards for Buildings

29 CFR 1926 OSHA

Construction

January

Mandatory www.OSHA.gov

AR 385-10 Chapter 4 Safety Program http://www.ngbpdc.ngb.army.mil/pubs/385/ngr38 5_10.pdf http://www.acquisition.gov/?q=browsefaror http://www.acquisition.gov/?q=browsefaror http://www.acquisition.gov/?q=browsefaror http://farsite.hill.af.mil/ http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://farsite.hill.af.mil/ http://www.apd.army.mil/ProductMaps/PubForm/AR.aspx http://www.apd.army.mil/ProductMaps/PubForm/AR.aspx http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx http://armypubs.army.mil/ProductMaps/PubForm/AR.aspx http://www.dtic.mil/whs/directives/corres/pub1.html http://www.dtic.mil/whs/directives/corres/pub1.html http://www.wbdg.org/FFC/ARMYCOE/NATL http://www.wbdg.org/FFC/ARMYCOE/NATL http://www.wbdg.org/FFC/ARMYCOE/NATL http://www.osha.gov/ http://www.ngbpdc.ngb.army.mil/pubs/385/ngr385_10.pdf http://www.ngbpdc.ngb.army.mil/pubs/385/ngr385_10.pdf

Demolition

Demolition service

Meets the standard 100% of the time as approved on the work schedule.

COR / Monthly.

Safety Standards

Compliance with safety requirements

Contractor shall have available all records as required on the SOW.

COR / Monthly.

A. SUBMITTAL LIST

DESCRIPTION TYPE QTY DUE REMARKS

Material Approval Submittals: All materials used on project:

1. Electrical Fixtures

2. Electrical Technician license

3. MB Membrane System

4. Worker Compensation

Insurance Certificate

5. Doors and Frame

6. Door Locks

7. Staircase and ramp shop drawing and Footer Design

8. HVAC Model and Technical

Data

9. ADSIL Treatment Certificate

10. Refrigerant Technician license

11. Electrical Panel Boards

12. Power Service Meter

13. Electrical Disconnects

14. Interior Vinyl Wall Treatment

15. Fire Alarm & Detection system

16. Lightning Suppression system and Certification

17. PE Sign certified Utilities drawings.

AF

Form

1 NLT 7 days after final shop drawings and 7 days before

NTP

Must be signed by:

Contracting

COR

Contractor (return copy)

Environmental & Hazardous Material Plan

AF Form

1 Approved 7 days before NTP

Must be signed by:

Contracting

COR

Contractor (return copy)

Quality Assurance Plan AF Form

1 Approved 7 days before NTP

Must be signed by:

Contracting

COR

Contractor (return copy)

Safety Plan AF Form

1 Approved 7 days before NTP

Must be signed by:

Contracting

COR

Contractor (return copy)

Warranty Certificate s

AF Form

1 Before final invoice is certified

Must be signed by:

COR

CE

B. DESIGN AND CONSTRUCTION STANDARDS AND REFERENCES:

• ASTM (American Society for Testing and Materials) – Latest Edition

• UL (Underwriter’s Laboratories) – Latest Edition

• National Electric Code (NEC) – Latest Edition

• Local, Federal, and International (IBC) Codes: ICC - IBC 2018

• ANG ETL 01-1-1 (Air National Guard Engineering Technical Letter)

• Applicable UFCs – Latest Edition

• Applicable NFPA– Latest Edition

• J-STD-607-A– Latest Edition

• ANSI EIS-TIA 607, Commercial Building Grounding (Earthing) and Bonding

• Requirements for Telecommunications ¶5, 6, 7 and Annex B

• MIL-STD 188-124B, Grounding, Bonding, Shielding

• MIL-HDBK-1004.6, Lightning Protection, May 88

• UFC 3-580-01, Telecomm Building Cabling System Planning and Design, ¶2-7

• UFC 3-520-01, Interior Electrical Systems

• MIL-HDBK 419A Grounding, Bonding & Shielding for Electronic Equipment,

• Appendix B Fig 10 & 11

• NFPA 70/NEC Article 250 and Section III and 250.66

• NFPA 780, Std for Installation of Lightning Protection Systems

• NESC C2-2002, Section 9, Grounding Methods for Electric Supply and

• Communications Facilities

• UFGS 13100A, Lightning Protection System

• UFGS 13100N, Lightning Protection System

• Unified Facilities Guide Specification (UFGS) Web Site:

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

• SECTION 32 31 13.53 HIGH-SECURITY CHAIN LINK FENCES AND GATES

• All federal applicable UFC, UFGS and ANG ETL’s must be verified at www.wbdg.org

C. INVOICE REQUIREMENTS:

• Electronic pictures of work to be invoiced (Before and After)

• Breakdown for Payment

• Monthly Report from: Contractor Manpower Reporting Application (CMRA)

• Progress Report of activities.

• Project Schedule (CPM): Baseline Vs Update

D. CLOSEOUT DOCUMENTATION:

• Contractor workmanship letter of warranty up to one year.

• Equipment Original Warranty

• Equipment (ACU/AHU) Original purchase receipt

• ADSIL Treatment Certificate http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

• Recycling or landfill proof of disposition document.

• Contractor certificates of no debts to suppliers and vendors.

• Contractor workmanship letter of warranty up to one year.

• Contractor certificates of no debts to suppliers and vendors.

• Commissioning and acceptance of system.

• Completed DD Form 1354.

• Certification of work by a professional refrigeration provider in accordance with Puerto Rico Lay 416