Questions and Answers.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- Corrosion Control Facility Furniture
- Solicitation number
- W50S8Z22Q0014
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Question and Answer.docx | DOCX document | |
| Corrosion FAC furniture Specifications.docx | DOCX document | |
| Corrosion FAC building layout.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions to be submitted
| Q&A due by: No Later Than 31 May 2022. | ||||
| Instruction: | 1. Questions: All questions shall be in writing. Questions shall be submitted to Christin Davila at christin.davila@us.af.mil. Questions must be submitted No Later Than 31 May 2022. | |||
| Submitted by: | Reference what Section of SOW | Question to be asked | Submission Date | Government Response |
| Johnathon Shepherd | Required Delivery Date | Please Verify the Required Delivery date : Specifations document states the furniture to be delivered by june 15th ,2022 however in the RFQ technical states a 60day ADC | 5/31/22 | 60 Days ADC |
| Dave Giles | General | What is the estimated award date? | 5/31/22 | N/A |
| Dave Giles | Para 3 | What format (Xcel, Microsoft Project, Visio, etc) does the government want to the schedule to be in? | 5/31/22 | No specified format |
| Dave Giles | Para 3 | What font type does the government want the proposal to be? | 5/31/22 | No specified font type |
| Dave Giles | Para 3; Corrosion+FAC+furniture+Specifications, CLIN 0006-1 Job- Installation | Given the submission date and current industry standards, due to national and global labor and supply shortages, of at least 16 calendar weeks for furniture to be produced and delivered, is the government still expecting furniture to be delivered by June 15? Assuming award of contract in June, can this date be changed to at least the end of September? | 5/31/22 | 60 Days ADC |
| Dave Giles | CLIN 0006 | Upon installation of furniture, is there a government document that needs to be completed and accepted by the government to confirm completion of task(s)? | 5/31/22 | Govt acceptance will occur upon complete installation of all requested furniture. |
| Dave Giles | Corrosion_FAC_building_layout.pdf | Can the governemnt provide Mechanical, Electrical, and Plumbing and Voice/Data PDF drawings of the space(s) so the contractor can properly design the furniture and ensure it supported with MEP and Commz? | 5/31/22 | Building layout/floor plan is provided as attachment in solicitation. |
| Dave Giles | CLIN 0006 | Will these CLINS be able to be completed in one effort or should the contractor plan a phased effort? | 5/31/22 | One effort is preferred |
| Dave Giles | CLIN 0001 thru CLIN 0005 | Are variations to the dimensions provided allowed to ensure furniture can be 'off the shelf' vs. custom? | 5/31/22 | Dimensions are standard desk dimensions, no customer furniture requested |
| Dave Giles | CLIN 0001 thru CLIN 0005 | Does the government want wood finishes or is the government's intent for wood grain laminate? | 5/31/22 | Wood grain laminate |
| Dave Giles | Para 3 | In order for the contractor to provide a detailed design layout with the proposal, the government will need to provide the facility drawings in Revit or AutoCad. When can the government provide these documents? | 5/31/22 | Govt does not have the drawing available in Revit or AutoCad |
| Dave Giles | CLIN 0001 | Can the stackable chairs be steel framed? | 5/31/22 | Yes |
| Dave Giles | CLIN 0006 | Will the contractor be responsible for making any electrical, voice, or data connections to the furniture? | 5/31/22 | No |
| Dave Giles | Para 3 | Is there a page limit to the proposal? | 5/31/22 | No |
| Dave Giles | Instructions to Offerors | Given the absence of some of the above documents intrinsic to the contractor effectively putting the proposal together, can the proposal due date be adjusted to a later date? | 31-May-22 | Proposal due date will not be adjusted at this time |
| Fawn Ward | Instructions to Offerors #3 | It reads we must submit a detailed design layout of items are they fit into the floor plan…..are there floor plans available in Revit that could be sent to us? | 5/31/22 | Govt does not have the floor plan available in Revit |
| Fawn Ward | CLIN 0004, CLIN 0005, CLIN 0006 --"Rectangle shaped Desk with Glass Door Hutch 72"W/42"W x 24"Deep" | By "Rectangle Desk", do you mean a straight desk at 72" or 42"? Or do you mean an L-Shaped Desk that is 72" x 42" x 24" wide? | 5/31/22 | L-Shaped Desk that is 72" x 42" x 24" wide |
| Fawn Ward | CLIN 0001-CLIN0005 | Is wood furniture desired? Or can it be laminate or metal? | 5/31/22 | wood grain laminate is acceptable |