QA W50S8V-24-B-0005 Construct Asphalt Pad dated 9 August 2024.pdf

PDF 538 KB Posted

Attached to
Construct Asphalt Pad Federal contract opportunity
Solicitation number
W50S8V-24-B-0005
Issued by
Department of the Army National Guard

About this file

This document is a set of Questions and Answers related to Solicitation No. W50S8V-24-B-0005 for the Construct Asphalt Pad project. The solicitation is a Total Small Business Set-Aside with a NAICS code of 237310 and an expected value of less than $25,000. Davis-Bacon wage rates apply, and payment bonds will be required if the bid amount exceeds $35,000. The project involves constructing a 30' x 90' asphalt pad, with a 20' x 90' main lane and a 10' x 90' adjacent lane. The pad will have a 4" yellow strip 12' off each long end, as well as a 44' x 20' block marked by 3" white lines and subdivided as specified. The intent is to have the total 30' x 90' pad laid at the same time, if it is within the budget. The solicitation will be awarded to the responsible bidder whose conforming bid is most advantageous to the Government, considering only price.

View the file

Other files for this federal contract opportunity

Other files attached to Construct Asphalt Pad, newest first.
File Type Posted
Abstract of Offerors - Construct Asphalt Pad.pdf PDF
Site Visit PP - Construct Asphalt Pad.pptx PPTX presentation
Construct Asphalt Pad Site Visit Attendance Sheet.pdf PDF
Site Visit PP - Construct Asphalt Pad.pptx PPTX presentation
Visitor and Contractor Background Check Form - Construct Asphalt Pad.docx DOCX document
SOW - Construct Asphalt Pad.pdf PDF
W50S8V-24-B-0005 Construct Asphalt Pad.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers for Solicitation No:

W50S8V-24-B-0005

Construct Asphalt Pad 9 August 2024

Questions:

1. According to the specification, the assumption is that the 10’ x 90’ is laid adjacent to the 20’ x 90’ pad. If this is accurate, should it not be constructed as one entity or is there a reason for physical demarcation between the two?

A. The intent is to have the total 30’ x 90’ pad laid at the same time if it is within the budget. If the 20’ x 90’ lane eats up the budget, then we will not be adding the additional 10’ x 90’ lane to reduce the total cost.

2. In addition to the construction, there’ll be a 4” yellow strip 12’ off each long end as well as a 44’ x 20’ block marked by 3” white lines and subdivided as specified. Is this assumption correct? See screenshot below.

A. Yes, that is correct.