Bidder_RFIs_GOV_RESPONSES.pdf

PDF 87 KB Posted

Attached to
B618 B646 Canopy Doors Federal contract opportunity
Solicitation number
W50S8N24Q0002
Issued by
Department of the Army National Guard

About this file

This document contains a request for information responses related to a federal contract solicitation for hangar canopy door refurbishment. The solicitation seeks replacement of hangar canopy door systems at two buildings on an Air National Guard base. The contractor must demolish and remove existing doors and install new Door Engineering brand systems using approved parts. The performance work statement, drawings, and site visit details are provided. Quotes are due by February 26, 2024 following a site visit on February 20, 2024. The award will be made to the lowest price bid. Wage determinations, bid guarantees, payment bonds, and performance bonds are required. The project value is between $100,000 and $250,000 to be completed within 180 days. The soliciting agency is the Department of the Army National Guard.

View the file

Other files for this federal contract opportunity

Other files attached to B618 B646 Canopy Doors, newest first.
File Type Posted
SF30.pdf PDF
SOW_Attach 10.4_Mfr_Shop Drawings_B646.pdf PDF
SOW_HAAW242003 Repair Aircraft Hangar Canopy Door B618 B646_rev3.pdf PDF
Wage Determination.pdf PDF
SOW_Attach 10.1_Record Drawings_B618.pdf PDF
SOW_Attach 10.3_Mfr_Shop Drawings_B618.pdf PDF
SOW_Attach 10.2_Record Drawings_B646.pdf PDF
SF18.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Door questions

1. The SOW 3.0 states the “(POP) shall be 91 calendar days.” After discussion with the door manufacture lead times on materials required exceed the POP at 18 weeks for procurement.

ANSWER: Changing the POP to 180 days is reasonable as there are few Closeouts required.

2. Does the government wish to relocate the hanger door controls outside of the safe zone as they do not appear to be in compliance with AFI 91‐203.

ANSWER: Not under this contract; it will be addressed In‐house.