This is a Statement of Work (SOW) for the repair of interior finishes in Building 145 at Pease Air National Guard Base in Newington, New Hampshire.
The contract requires the contractor to perform interior construction work including installation of approximately 900 square feet of drywall, 400 square feet of wall cavity insulation, 600 square feet of ceiling tiles, 300 square feet of ceiling grid repairs, 600 square feet of carpet, 160 linear feet of cove base, and 1,250 square feet of drywall painting. Additional work includes reinstallation of facility infrastructure components such as electrical outlets, light switches, lighting fixtures, thermostats, fire alarm devices, HVAC supply/returns, network drops, plumbing, and other utilities to code-compliant locations. The contractor must install an 8-inch HVAC return duct and create a new wall section with an office door. The performance period is 90 days after notice to proceed. The facility will remain partially operational during construction, with the immediate repair area vacated prior to project start.
The contractor must furnish all materials, equipment, tools, and labor, as the government provides no materials or equipment. The contractor is responsible for facility infrastructure reinstallation, quality control, safety compliance, and debris removal. Specific requirements include use of Sherwin Williams Pro Mar 200 Eggshell paint, certification of ceiling tiles to UL 2818 standards, low-VOC carpet adhesives, and mineral wool insulation with R-15 minimum value. A pre-construction walkthrough is required to identify fire alarm faults, electrical hazards, and building management system issues. The contractor must submit multiple plans and documentation within 10 days of notice to proceed, including quality control, environmental protection, accident prevention, waste management, and hazardous materials plans. Weekly progress reports and material submittals are required throughout performance. Security requirements include AT Level 1 awareness training, identification badges, background checks, and compliance with base access procedures.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OFFICE SPACE RENOVATION BLDG 145
New Hampshire Air National
Guard Pease ANGB
Newington, NH
This Page Intentionally Left Blank
Part I: Statement of Work
(SOW) BLD 145 DCMA
Repair of Interior Finishes
1.0 General: The New Hampshire Air National Guard requires the repair of interior finishes inside building
145. The part of the facility requiring repair consists of office space. The in-scope area is a single-story office facility. The facility will need to remain partially operational during the scope of the repair and construction.
1.1 Scope: This work statement includes all work necessary to support the required effort, equipment, and supplies needed (description below) to replace interior finished surfaces inside building 145, within the identified area on the supplied floor plan, located at the NHANG, Pease ANGB, Newington, NH 03801.
1.1.1 Objectives: Provide repair of interior finished surfaces.
1.2 Background: Inside building 145, minor demolition, debris removal, and mold remediation of water damaged office space was completed. Interior finished surfaces were selectively demolished, and infrastructure was left in a condition to be reinstalled during repair. The damaged office area of the facility is occupied, but the immediate space to be repaired will be vacated prior to project start and will remain unoccupied throughout the term of this effort.
1.3 Period of Performance: 90 days after notice to proceed.
1.4 For contractors that do not require a CAC, but require access to a DoD facility or installation: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification (NCIC-III) and Terrorist
Screening Database (TSDB) (Army Directive 2014-05), and applicable installation, facility and area commander installation/facility access, and local security policies and procedures (provided by a
Government representative).
1.5 Physical Security. The contractor shall safeguard all Government property provided for, and in the vicinity of, contractor work. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.6 Special Qualifications: Contractors must have past performance equal to the level of difficulty and size of the facility. The contractor shall ensure all employees possess all required licenses for operating contractor equipment used in the performance of this contract. This does not include education or other qualifications for the position in which the contractor employee is performing, dress codes, or other information. (NOTE: The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, licensed, certified, and otherwise qualified to provide services.)
1.7 Combating Trafficking in Persons: The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in severe forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract.
The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. The contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17.
1.8 Contractor Travel Not Authorized.
1.9 Data Rights Reserved.
1.10 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications, or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO. In the event the
KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may impose other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.11 Awareness Training (AT) Level 1: All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled access areas shall complete AT Level
1 training within 30 calendar days after contract start date and within 30 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee to the COR within 15 calendar days after completion of training by each employee or subcontractor personnel. AT Level 1 awareness training is available at the following website: https://jko.jten.mil/courses/atl1/launch.html \
1.12 Contract Manager (CM): The contractor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
https://jko.jten.mil/courses/atl1/launch.html%20/
1.13 Identification of Contractor Employees: All contractor personnel attending meetings, answering
Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are
Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e-mail) and dealings with Government or non-Government entities. Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word
“contractor” displayed.
1.13.1 The contractor shall retrieve all identification media (including vehicle passes) from its employees who depart employment for any reason. The contractor shall return all identification media (i.e., badges and vehicles passes) to the KO within 14 days of an employee’s departure.
2.0 Definitions and Acronyms:
2.1 Definitions:
2.1.1 Contractor: A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 Defective Service: A service output that does not meet the standard of performance associated with the
SOW.
2.1.3 Deliverable: Anything that can be physically delivered and includes non-manufactured things such as meeting minutes or reports.
2.1.4 Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the SOW. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.5 Physical Security: Actions that prevent the loss or damage of Government property.
2.1.6 Quality Assurance: The Government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.7 Quality Assurance Surveillance Plan (QASP): An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.8 Quality Control: All necessary measures taken by the Contractor to ensure that the quality of an end product or service shall meet contract requirements.
2.1.9 Subcontractor: One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.2 Acronyms:
AEI Army Enterprise Infostructure
AR Army Regulation
AT/OPSEC Antiterrorism/Operational Security
BI Background Investigation
CM Contract Manager
COR Contracting Officer Representative
DA Department of the Army
DD254 Department of Defense Contract Security Classification
Specification
DFARS Defense Federal Acquisition Regulation Supplement
DoD Department of Defense
DSCA Defense Counterintelligence and Security Agency
FAR Federal Acquisition Regulation
GFP/M/E/S Government Furnished
Property/Material/Equipment/Services
HQDA Headquarters, Department of the Army
HSPD Homeland Security Presidential Directive
IA Information Assurance
IS Information System(s)
KO Contracting Officer
NGB National Guard Bureau
OCI Organizational Conflict of Interest
PII Personally Identifiable Information
PIPO Phase In/Phase Out
QA Quality Assurance
QASP Quality Assurance Surveillance Plan
QC Quality Control
QCP Quality Control Program
SCR Service Contract Reporting
SSN Social Security Number
TE Technical Exhibit
USD(I) Under Secretary of Defense for Intelligence
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S): The
Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract:
3.1 Property: None.
3.2 Materials: None.
3.3 Equipment: None.
3.4 Services: None. Bathroom facilities shall not be used by the contractor for the duration of the renovation.
Cleaning and stocking of toileting supplies is the burden of the government for government use and the contractor shall make arrangements for their own lavatory facilities.
3.5 Utilities: Water: standard water hose connections. Electrical: Most outlets in the area are 120v 20amp connections. Connections or temporary outlets or alterations to panels will require a licensed electrician and concurrence from the COR. Delays in coordination will be at no fault of the government.
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E):
4.1 General: Except for those items specifically stated to be Government-Furnished in Paragraph
3.0, the contractor shall furnish everything required to perform these services as indicated in
Paragraph 1.1. This includes all tools, equipment, ladders and all PPE for their labor force, which are customary and reasonable for performing construction trades work and check general condition of items left at the end of this effort.
5.0 REQUIREMENTS: The New Hampshire Air National Guard has a requirement for the installation of roughly 900sqft of drywall, 400sqft of wall cavity insulation, 600sqft of ceiling tiles, 300sqft of ceiling grid repairs, 600sqft of carpet, 160LF of cove base, and 1250sqft drywall painting. Additional requirements include the installation/reinstallation of standard facility infrastructure and installation of a new wall section and office door, which are outlined further in this paragraph. The installation of an 8” HVAC return duct will be required from the newly established office to the closest tie-in opportunity. Limited carpet and VCT removal and floor preparation will be required to allow for the seamless installation of carpet tiles.
The location in scope is identified on the supplied floor plan and will be viewed during the pre-bid site visit.
Utilities left unmounted after a recent demolition that require reinstallation include outlets, switches, lighting, fire alarm sensing/notification devices, conduits, junction boxes, panels, network drops, plumbing, thermostats, sensors, HVAC supply/returns, and other utilities. The contractor is responsible for re-installing these facility infrastructure components and appurtenances back into a serviceable and operable state in local and federal code compliant locations. Per the scope in this section, the vendor will provide all necessary supervision, labor, materials, and equipment to perform these operations throughout the identified areas of the facility.
A preconstruction walkthrough, after notice to proceed, is required to identify the following: Any Fire
Alarm Panel fault codes, electrical hazards, the status of HVAC and building management system controls capabilities that may have been damaged by the recent demolition contract and or previous water damage.
The contractor will furnish a list of preconstruction deficiencies to be signed by the COR and contractor.
During construction, any new alarms or faults within the area will be monitored by the base Fire
Department, a list of which they will provide to the COR and subsequently to the contractor for repair.
DESCRIPTION OF SERVICES
This section defines the minimum requirements necessary to perform interior construction efforts in the scope of this contract; to comply with installation and facility standards. The COR shall inspect and make determinations for acceptance on all items listed in the SOW.
5.1 FINISHED INTERIOR SUFACES INSTALLATION
5.1.1 Services: The Contractor shall manage all aspects of this contract to for the restoration and installation of interior finished surfaces: Drywall, painting, carpets, cove base, ceiling tiles, wall insulation, and the reinstatement of facility infrastructure to working order throughout the designated areas within the in-scope area of the facility.
5.1.2 Material Installation Requirements: The following is a list of installation standards and practices. All have specific minimum standards that are required: drywall, ceiling grid, ceiling tiles, insulation, cove base, stud walls, carpet tiles, HVAC duct, and painting.
Contractor shall adhere to the finish schedule provided by the government.
5.1.3 Gypsum Wall Board / Application: There is no requirement for a negative pressure work space during this contract. Roughly 900sqft of repaired/replaced gypsum wallboard must be taped, finished, and paint primed before the installation of any high emitting volatile organic compound (VOC) materials. Fasten gypsum board to framing and furring members in accordance with ASTM C840 or GA 216 and the requirements specified. Apply gypsum board with separate panels in moderate contact; do not force in place. Stagger end joints of adjoining panels. Neatly fit abutting end and edge joints. Use gypsum board of maximum practical length; select panel sizes to minimize waste. Cut out gypsum board to make neat, close, and tight joints around openings. In vertical application of gypsum board, provide panels in lengths required to reach full height of vertical surfaces in one continuous piece.
Lay out panels to minimize waste; reuse cut offs whenever feasible. Surfaces of gypsum board and substrate members may[not] be bonded together with an adhesive [except where prohibited by fire rating(s)]. Treat edges of cutouts for plumbing pipes, screw heads, and joints with water-resistant compound as recommended by the gypsum board manufacturer.
Minimize framing by floating corners with single studs and drywall clips.
5.1.4 Install 5/8-inch fire rated type-x gypsum over framing 16 inches on center. Limited framing will need to be accomplished after the recent demolition to provide a suitable surface for drywall installation. Metal stud framing is typically 20-25 gauge. The government estimates 12lnft of framed metal stud wall will be required for the new wall installation, plus minimal sections of repair to existing steel studs. A light switch to operate the overhead lights in the new office will be the only utility installed on the new wall. The new office door will be installed and finished to match existing doors in the area. Provide, at a minimum, type-x fire rated 5/8-inch gypsum wallboard. Apply gypsum board prior to the installation of finish flooring and acoustic ceiling.
5.1.5 Mudding, jointing, and taping will conform to industry standard practices to provide a neat and smooth appearance for the application of paint when ready.
5.1.6 Finished paint will be Sherwin Williams Pro Mar 200 Eggshell, Shoji White SW7042 or equivalent. Any non Sherwin Williams paint color will need to be approved by the COR.
All rooms within the scope of this contract will be painted to provide a clean and presentable surface. Painting should take place before flooring and ceiling tile installation are completed.
5.1.7 Ceiling grid was left in place during the demolition phase. The contractor will be responsible for matching and repair or reinstall to create an effective, uniform, and complete suspended ceiling. The ceiling will need to be reconfigured where the new wall section will be installed, as it must extend at least 2 inches above the ceiling grid.
5.1.8 Ceiling tiles and grids are 2’x4’ sizes. It is the contractor’s responsibility to match the ceiling grids. Light troffers may need to be moved or rehung to provide a seamless installation. Provide the same manufacturer and surface texture of ceiling tile throughout the identified areas. There are no requirements for a certain manufacturer of ceiling tiles.
Replacement of ceiling grid sections or perimeter grid may need to be accomplished to ensure a complete and finished installation. Color match replacement ceiling grid if necessary. Provide ceiling tile certified to meet indoor air quality requirements by UL 2818
(Greenguard Gold, SCS Global Services Indoor Advantage Gold or provide certification or validation by other third-party programs that products used meet the requirements of this section.
5.1.9 Carpet Tile: Provide the COR with samples to approve and select color and for verification of adherence to standards after notice to proceed is given by the KO. Carpet installation location will be the entire scope area. Carpet will need superior soil resistance and appearance retention. It will have a manufacturer of continuous filament nylon 6. 6 or nylon 6 with a cross-section modification ratio no greater than 2.5, per AF
ETL 07-04, 9.4.2. There will be no PVC backing. Thresholds and transitions will be used when carpet meets a different flooring material or at a termination point. Carpet adhesive will be low VOC. All adhesives for carpet and sheet vinyl installation shall be environmentally safe products meeting all requirements of and all other local, state, and federal environmental agencies. Flooring adhesives should be certified as Carpet and
Rug Institute (CRI) “Green Label” or “Green Label Plus” per AF ETL 07-04,
9.4.7.7. All Safety Data Sheets (SDS) need to be submitted to the installation
Environmental Manager for approval before installation. For reference Mohawk -
2OCR-T: DATUM 7559 meets all government specifications for carpet tiles.
5.1.10 Cove base will be applied to the perimeter in each room where carpet is installed. The amount is approximately 160LF. Cove base will be vinyl material with a matte finish.
Colors and material samples will be provided to the COR to match with the color of the carpets chosen. Cove base adhesive will be low VOC and an SDS will need to be submitted to the COR for record retention purposes. Self-adhesive cove base will not be accepted. Prefabricated corners are acceptable. The installation shall be neat and present a professional appearance.
5.1.11 Metal stud walls 20-25 gauge are consistent throughout the space. Any unserviceable studs should be repaired or replaced in kind. It is expected that adjustment or minimal replacement to ensure proper drywall installation will be required. The government does not anticipate more than 12lnft of metal stud framing.
5.1.12 Insulation will be installed per the plan provided. The approximate replacement amount is 400sqft. The type used will be a mineral wool material, designed for fire resistance, Suitable for interior metal stud wall application. A minimum R value of 15 is required.
5.1.13
Furnish extra materials “Attic Stock”. Furnish 5% over required installation amounts for acoustic ceiling tiles. Furnish extra carpet tiles, from the same product run, that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. Full-size units equal to 5 percent of amount installed for each type indicated, but not less than 8.3 sq.m (10 sqyd.)
5.2 Facility Infrastructure
5.2.1 Electrical outlets, light switches, lighting, surface mounted fixtures, thermostats, fan controls, motion sensors, communications equipment, fire alarm sensing / notification and alarm and other wall mounted devices and components not specifically listed will need to be reinstalled to code compliant heights and locations. During the recent demolition to remediate mold, care was taken to remove and make secure components in preparation for reconstruction. The reinstallation of these items may require partial and complete isolation of circuits or other utilities to complete. Licensed trades work will be required for reinstallation on a like-for-like basis i.e. licensed electricians for electrical, licensed HVAC technicians for heating ventilation and air conditioning systems.
5.2.2 Any trouble codes or alarms on the Fire Alarm Control Panels (FACP) that are monitoring the areas in the scope of this effort will need to be addressed and corrected by the contractor, if they arise during the period of performance. The existing system is a Monaco Enterprises Inc manufactured product. Civil Engineering has a limited supply of devices and may be able to provide a replacement if available. If a faulty fire alarm device is found the contractor may be provided with a replacement device by the COR. Installation of replacement devices, along with any wiring, or programming of addressable components found to be faulty or in need of replacement, will be completed by a contractor utilizing technicians certified on the Monaco
Enterprises Inc system in use at BLD 145
5.2.3 Any previously damaged or found to be non-functional infrastructure i.e. electrical outlets, switches, light bulbs, troffers, or other devices will be identified by the contractor by room, location, and amount for each will be supplied to the COR.
6.0 Applicable Publications: Publications applicable to this SOW are listed below:
Publication
(Chapter/Page)
Date of
Publication
Mandatory or
Advisory
Website
Federal Acquisition Regulation https://www.acquisition.gov/?q=browsef ar
Defense Federal Acquisition
Regulation Supplement http://www.acq.osd.mil/dpap/dars/dfarsp gi/curr ent/index.html or https://www.acquisition.gov/dfars
Federal Information Processing
Standards (FIPS) Publication 201-2
Personal Identity Verification (PIV) of Federal Employees and Contract ors (paragraph 9)
August 2013 http://nvlpubs.nist.gov/nistpubs/FIPS/N
IST.FIP S.201-2.pdf
DoDM 5200.2 Procedures for the
DoD Personnel Security Program
(PSP)
04/03/2017 https://www.esd.whs.mil/Directives/issu ances/ dodm/
DoDI 5400.11
Department of Defense Privacy and
Civil Liberties Programs
01/29/2019 https://www.esd.whs.mil/Directives/issu ances/ dodi/
DoD 5400.11-R
Department of Defense Privacy
Program
05/14/2007 https://www.esd.whs.mil/Directives/issu ances/ dodm/
AFI 10-245
Antiterrorism
03/28/2013 (Certified current 03/30/2017) https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&c atID=1 &series=-
1&modID=449&tabID=131
AFI 31-101
Security Forces Standards and
Procedures
08/18/2020 https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&cat
ID=1
&series=-1&modID=449&tabID=131 https://www.acquisition.gov/?q=browsefar https://www.acquisition.gov/?q=browsefar http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html http://www.acq.osd.mil/dpap/dars/dfarspgi/current/index.html https://www.acquisition.gov/dfars http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf http://nvlpubs.nist.gov/nistpubs/FIPS/NIST.FIPS.201-2.pdf https://www.esd.whs.mil/Directives/issuances/dodm/ https://www.esd.whs.mil/Directives/issuances/dodm/ https://www.esd.whs.mil/Directives/issuances/dodm/ https://www.esd.whs.mil/Directives/issuances/dodi/ https://www.esd.whs.mil/Directives/issuances/dodi/ https://www.esd.whs.mil/Directives/issuances/dodi/ http://www.esd.whs.mil/Directives/issuances/ http://www.esd.whs.mil/Directives/issuances/ http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-
AFMAN 31-113
Security Forces Standards and Procedures
03/05/2013 Change 1:
12/02/2015 https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&cat
ID=1
&series=-1&modID=449&tabID=131
AFPD 17-1
Information Dominance
Governance and Management
04/12/2016 https://www.e-publishing.af.mil/Product- Index/#/?view=pubs&orgID=10141&c atID=1 &series=- 1&modID=449&tabID=131
AFMAN 17-1301
Computer Security (COMPUSEC)
02/12/2020 https://www.e-publishing.af.mil/Product-
Index/#/?view=pubs&orgID=10141&c atID=1 &series=-
1&modID=449&tabID=131 http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-http://www.e-publishing.af.mil/Product-
TECHNICAL EXHIBIT 1
Deliverables Submittals Schedule
(Deliverables must be identified in the SOW and then summarized here. See examples below)
SOW Reference /
Deliverable Title
Frequency / Description of
Deliverable
Number of
Copies
Medium/Format Subm it To
1.4.3
Quality
Control
Plan
Provide within 10 calendar days of contract award
1 Electronic
Submission
COR
1.11 AT Level 1
Awareness
Training Certificates
Provide within 30 calendar days after employee completes training.
1 Electronic
Submission
COR
1.13
Contract
Manager
Designation
Provide within 14 calendar days of contract award
1 Electronic
Submission
COR
1.13.1
Identification
Media (Access
Badges /Passes)
Return within 14 days of employee’s departure from contract performance.
Original Hard Copy COR
5.0 Pre
Construction
Deficiencies
List
Immediately after award of the contract prior to any construction work.
1 In person/ Hard
Copy
COR
5.1.6 Paint Color Prior to the purchase of
materials and application of paint. If deviating from suggested color.
1 Hard Copy COR
5.1.9 Carpet
Tile
Prior to the purchase of materials. 1 Hard Copy COR
5.1.10 Cove Base
Color
Prior to the purchase of materials 1 Hard Copy COR
5.1.13 Attic Stock
Materials
After finished installation prior to project close
1 Materials/Itemized
Listing
COR
PART II: DIV 1 SPECIFICATIONS
1. INSURANCE CERTIFICATES & PAYMENT BONDS - MINIMUM AMOUNTS
Provide Certificates of Insurance with the minimum insurance coverage required by FAR 28.307-2
Liability, during the entire period of performance under this contract within 14 days of contract award.
Reference Contract Clause titled, "Insurance - Work on a Government Installation (FAR 52.228-5)."
Provide other insurance coverage as required by New Hampshire law and as follows:
TYPE AMOUNTS
Workmen’s Compensation $100,000 (see paragraph 1.2 below
Comprehensive General Liability $500,000 per occurrence for bodily injury
Comprehensive Automobile Liability $200,000 per person and $500,000 per accident for bodily injury and $20,000 for property damage
Aircraft Public and Passenger Liability
(as applicable)
$200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability and $200,000 per occurrence for property damage; coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or $200,000 multiplied by the number of passengers, whichever is greater.
1.1 Except in states with exclusive or monopolistic funds that do not permit workers’ compensation to be written by private carriers.
1.2 The policies referenced in the certification (s) shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the
Government’s interest shall not be effective (1) for such period as the laws of the state in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting
Officer, whichever period is longer. The Contractor shall maintain a copy of proofs of required insurance and shall make copies available to the Contracting
Officer upon request. The Contractor shall maintain a copy of all subcontractors’ proofs of required insurance and shall make copies available to the Contracting Officer upon request.
2. RESERVED
3. SCHEDULING
3.1 Normal base work hours for the Contractor will be between the hours of
7:00 AM through 4:30 PM, excluding Saturdays, Sundays, and Federal
Holidays. If the Contractor desires to work during periods other than above, he must notify the Contracting Officer’s Representative (COR) five
(5) working days in advance of his intention to work during other periods to allow assignment of additional inspection forces. When the COR determines that they are reasonably available, he may authorize the
Contractor to perform work during periods other than normal duty hours/days. However, if inspectors are required to perform in excess of their normal duty hours/days solely for the benefit of the Contractor, the actual cost of the inspection, at overtime rates, will be charged to the
Contractor and will be deducted from the final payment of the Contract amount.
3.2 The following Federal legal Holidays are observed by this base:
New Year’s Day 1 January
Martin Luther King’s Birthday Third Monday of
January President’s Day Third Monday of
February Memorial Day Last Monday of May Juneteenth 19 June Independence Day 4 July Labor Day First Monday in September
Columbus Day Second Monday in October
Veteran’s Day 11 November
Thanksgiving Day Fourth Thursday in
November
Christmas Day 25 December
3.3 NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday; holidays falling on a Sunday will be observed on the following Monday.
3.4 Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more), commencement of any warranty work, and upon completion of warranty work, the contractor must notify the Contracting Officer (or the Contracting Officer’s
Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting
Officer’s Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The purpose of the above precautions is to ensure construction inspection and recording of work proceedings.
3.5 The organization of the specifications into divisions, sections, and articles, and the arrangement of the drawings shall not control the
Contractor in dividing the work among subcontractors or in establishing the extent of the work to be performed by any trade.
4. 4 INVOICING AND PAYMENT
4.1 Properly prepared invoices, bearing the contract number, shall be submitted in duplicate to the Contracting Office, (302 Newmarket Street, Newington, NH 03801) on designated invoice forms provided at the pre-construction meeting PRIOR to uploading in Wide Area Workflow
(WAWF) the DFAS paying system. This submission will be for review prior to submitting an electronic invoice through Wide Area Workflow
(WAWF). See end of this Section for important information and codes needed.). Payment will be made by in accordance with FAR clause 52.232-
5 Fixed-Price Construction Contracts and FAR clause 52.232-27, Prompt
Payment for Construction Contracts, all payments will be made by electronic transfer of funds (EFT).
4.2 To meet compliance with DFARS 252.232-7003, Electronic Submission of Payment Requests, you shall submit your request for payment (invoice) through WAWF. For more information on the WAWF system, including how to register, visit https://wawf.eb.mil. Payment will be made by paying office specified in the contract award in accordance with the clauses
Payments under Fixed-Price Construction Contracts, FAR 52.232-5, and
Prompt Payment for Construction Contracts, FAR 52.232-27.
4.3 The Government will make payment through WAWF upon satisfactory completion of work AND receipt of a proper certification for payment. Do not input invoice into WAWF until the pre-approval of invoice is received from the contracting officer. This will lessen the need for rejections in
WAWF Payment may be withheld unless all contractual requirements including but not limited to: RECEIPT OF PROPER WEEKLY
PAYROLLS IAW DAVIS BACON REQUIREMENTS, Small Business
Subcontracting Reports, have been timely received.
4.4 All requests for payments through WAWF must include a Subcontractor
Payment Register pursuant to FAR Clause 52.232-5 and a contractor’s certification that reads as follows:
I hereby certify, to the best of my knowledge and belief that –
The amounts requested are only for performance in accordance with the specifications, terms and conditions of the contract; All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and requirements of Chapter 39 of Title 31, United States Code; This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from subcontractor or supplier in accordance with the terms and conditions of the subcontract; and This certification is not to be construed as final acceptance of a subcontractor’s performance.
4.5 The Government will make payment upon satisfactory completion of work
AND receipt of a proper certification for payment. Payment may be withheld unless all contractual requirements, including but not limited to:
RECEIPT OF PROPER WEEKLY PAYROLLS IAW CONSTRUCTION
WAGE REQUIREMENTS FAR 52.222-6, 1and Small Business Subcontracting Reports, have been timely received.
Payrolls shall indicate CLIN to which they are applicable.
https://wawf.eb.mil/
5. SCHEDULE OF PRICES
5.1 Within ten (10) days of Notice to Proceed (NTP), prepare and deliver to the Contracting Officer a Schedule of Prices (construction Contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable must be proportionately spread over all pay items and not included as individual pay items.
6. TELEPHONE COMMUNICATION & SECURITY MONITORING
6.1 All communications with DOD organizations are subject to
communications security (COMSEC) review. Contractor personnel must be aware that telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, civilian contractor personnel are advised that any time they place a call to, or receive a call from, a DOD organization, they are subject to COMSEC procedures. The contractor shall assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with DOD information.
7 UTILITY SERVICES
7.1 Make utility cutovers and interruptions after normal working hours or on
Saturdays, Sundays, and Government holidays. Work required by the
Contractor on a non-standard basis or at premium pay shall be done at no additional cost to the government. Permission to interrupt any activity utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
8 MATERIAL APPROVAL SUBMITTALS
8.1 The contractor shall submit all materials and articles requiring approval, such as contractor plans, shop drawings, product data, samples, design data, test reports, certificates, manufacturer’s instructions, operation and maintenance data, and warranties as required by the Material and
Workmanship Clause, FAR 52.236-5. Submittals shall be made using AF
Form 3000 or approved equal. Submittals shall be processed in accordance with the procedures in Section F, Submittals. Submittals shall be given a distinct identification system by CLIN if multiple CLINs are applicable.
Individual submittal documents shall not be comprised of items for more than one CLIN. Address for delivery of submittals will be provided at the post award/pre-construction conference. The contractor is reminded that an individual within the company who has authority to make the certification must sign the certification on the AF Form 3000. The
Contractor shall submit a proposed list of materials within ten (10) days of the notice to proceed (NTP)
The Contracting Officer is the approval authority for all submittals. Allow a minimum of 14 days of turn-around time for each submittal.
9 WORK PROGRESS AND PREPARATION OF PROEGRESS SCHEDULES &
REPORTS
9.1 A weekly meeting may be held with the Contractor, COR and Contracting
Officer (KO), if necessary, to discuss work progress, problems and potential change orders. The Contractor shall attend these meetings at no additional cost to the Government. Prior to beginning work on specific work elements of a project, the contractor shall confer with the COR and agree on a sequence of procedures and means of access to premises and buildings; space for storage of materials and equipment; delivery of materials; and use of approaches, use of corridors, stairways and similar means of passage.
9.2 In accordance with FAR Clause 52.236-15, “Schedules for Construction
Contracts”, the contractor shall within fourteen (14) days of contract award, submit a preliminary progress schedule to the Government for review. The schedule shall outline the timeframe in which in which the contractor proposes to perform the work, and the dates on which the
Contractor contemplates starting and completing features of work. A composite schedule for the overall contract shall also be provided. The schedule shall be on an AF Form 3064, Contract Progress Schedule, or an approved computer-generated format similar to the AF Form 3064. The work shall be scheduled so that, upon the start of construction, work progresses in a continuous and diligent manner. A schedule which does not reflect steady and reasonable progress throughout the construction period will be rejected. Both the Contractor and the COR are required to provide monthly progress reports covering the period from notice to proceed through final inspection. Unless agreement cannot be made on the applicable percentage of progress a joint report will be submitted to the
Contracting Officer. These reports shall be submitted on the NGB Contract
Progress Report form (similar to an AF Form 3065), or an approved computer-generated similar format. These reports shall track progress by CLIN, if contract contains multiple CLINs, multiple AF Form 3064 and NG Contract Progress Reports will also be required for payment purposes.
9.3 Additionally, for projects exceeding $1M, the contractor shall provide a project plan in a commercially available network scheduling software that meets requirements of the specification to define work tasks and track progress. At least five days prior to work initiation, the contractor shall provide the Contracting Officer a copy of the plan that shall include definition of rescues. No work may start until the Contracting Officer approves the plan in writing.
9.4 The Contractor shall prepare a work progress schedule required for completion of each of the various divisions of work. Updated plans and
Form 3064 showing work progress shall be provided weekly if there are possible deviations from the original plan, those must be noted and approved by the Contracting Officer before work changes are implemented. The schedule shall be submitted to the Contracting Officer, in the number of copies as directed. Reference Contract Clause FAR
52.236-15, “Schedules for Construction Contracts”. The reports contemplated by the clause herein titled “Schedules for Construction
Contracts” shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, “Contract Progress Schedule” and a
National Guard Contract Progress Report
10 NOTICE OF COMPLETION OF CONSTRUCITON/PRE-FINAL AND
FINAL INSPECTION
10.1 The contractor shall conduct a pre-final inspection in the presence of the
Contracting Officer’s Representative (COR) prior to the date scheduled for Final Inspection. Any discrepancies noted shall be corrected prior to
Final Inspection
10.2 The contractor shall request scheduling of a final inspection in writing to the Contracting Officer at least five (5) working days prior to the desired date or as otherwise negotiated with the Contracting Officer.
10.3 Civil Engineering personnel and the Contracting Officer will perform the
Final Inspection in the presence of the contractor, and any discrepancies noted shall be corrected within the time specified by the Contracting
Officer.
10.4 Final Inspection shall not constitute acceptance of a project unless so stipulated by issuance of a separate acceptance notice.
10.5 The contractor is cautioned to ensure they have completed adequate
Quality Control reviews prior to scheduling pre-final or final inspections.
In the event the Contracting Officer finds that the project is not ready for the applicable inspection, (too many discrepancies) the contractor may be held liable for the costs of a repeat inspection. If the inspection involves expert personnel these costs may include additional labor, travel and miscellaneous expenses.
11 DESIGNATION OF A TECHNICAL REPRESENTATIVE
11.1 The Contracting Officer will appoint a qualified Contracting Officer’s
Representative (COR) for the purposes of technically administering the contract; however, all matters concerning this contract or any work ordered placed against this contract must first be approved by the
Contracting Officer. This in no way authorizes anyone other than the
Contracting Officer to commit the Government to changes in terms of the contract.
12 CONTRACTOR STAFF AND EMPLOYEES
12.1 List of contractor personnel: Provide a list of contact personnel of the
Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency within ten (10) days of the Notice to
Proceed (NTP). As changes occur and additional information becomes available, correct and change the information contained in previous lists.
12.2 Supervision. The Government shall not exercise any supervision or control over the contractor employees performing services under this contract; such employees shall be accountable not to the Government, but solely to the contractor, who in turn is responsible to the Government.
12.3 Contractor’s Employees. All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may, in writing, require the contractor to remove from the job site, any employee the Contracting Officer deems incompetent, careless or otherwise objectionable.
12.4 The contractor shall provide the Contracting Officer with a telephone number and email address at which the contractor or his representative may be contacted at any time during regular working hours and an emergency number at which the contractor may be contacted in situations requiring immediate attention.
13 CONTRACT OFFICE AND STORAGE
13.1 Parking of contractor vehicles shall be restricted to the contractor’s designed on-site area or the work area. The company name shall be prominently displayed on all construction vehicles parked on the job site.
13.2 Security of material storage areas on the job site shall be the responsibility of the contractor. The area shall be kept neat and orderly and free of debris.
14 RESERVED
15 RECORD DRAWINGS
15.1 During construction of a project and on the job site, the contractor shall maintain a completed record of all changes and corrections from the layout shown on the drawings, if applicable. The contractor shall enter such changes and corrections on contract or record drawings promptly and submit the “red line” drawings to the Contracting Officer upon completion of the project. The record drawings shall indicate all changes and corrections concerning the actual locations of all sub-surface utility lines.
In order for the location of these lines and appurtenances to be determined in the event the surface opening or indictors become covered or obscured, the record drawings shall show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction. Valves splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded. The
Government does not guarantee the accuracy of existing record drawings;
it is the contractor’s responsibility to verify all as-built conditions.
15.2 The contractor shall mark and safeguard files, plans, layouts, output products, and storage media per classification level and disseminate them only to individuals authorized to receive them with a valid need to know.
16 VERIFICATION OF DIMENSIONS
16.1 The contractor shall be responsible for the coordination and proper relation of all aspects of the work. He/she shall field verify all dimensions and advise the Contracting Officer of any discrepancies prior to proceeding with any phase of the work. Where exact locations are not given for the positioning of equipment and devices, they shall be positioned to permit easy access for maintenance and for removal and replacement of component parts.
16.2 IAW DFARS 252.236-7001, Contract Drawings and Specifications, Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
17 SECURITY REQUIREMENTS
17.1 The contractor shall comply with all security regulations imposed by the base/post commander and/or agency occupying the space where work is to be performed. Any necessary security clearances shall be obtained prior to commencement of work.
17.2 It is expected that new security requirements to satisfy contractor personal identification requirements in Homeland Security Presidential Directive
(HSPD-12), ''Policy for a Common Identification Standard for Federal
Employees and Contractors,'' and Federal Information Processing
Standards Publication (FIPS PUB) Number 201, ''Personal Identity
Verification (PIV) of Federal Employees and Contractors” are incorporated in the life of this contract. Contractor shall comply with all requirements, at no additional cost to the Government.
17.3 The contractor shall ensure that all parts of the facility where work is being performed are adequately protected against vandalism and theft.
17.4 The Prime Contractor and all its subcontractors will be required to wear orange or lime colored safety vests while performing work on the installation.
17.5 U.S. Government will not be held liable for any delays or breach of contract caused by refusal of the Security Forces to allow entry.
17.6 All prospective contractors MUST be U.S. citizens or MUST have established and maintain legal residence in the U.S. and are authorized by the US government to work in the United States (i.e., Green card, worker authorization, etc.). All prospective contractors MUST have at least one form of U.S. government issued photo identification (driver's license, U.S. passport, U.S. work visa, etc.) for entry to the installation.
Security Forces will review any questionable identification documents for determination as to whether said identification is authorized for access to the installation.
17.7 All prospective contractors/contractor employees, once it has been established that they maintain the appropriate credential as described in one above, are subject to a Criminal History Check.
17.8 Note: For the purposes of Contracting services, it is implied that, that all parties agree to a Criminal History Background Check once entered into any contract. Any documents that are provided and found fraudulent to include, but not limited to driver’s licenses, contracting licenses, etc., will result in an arrest and potential termination for default from the contract.
All contractors are subject to search in order to obtain entry onto the installation and while working on the installation.