MBMV222327

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpos of this amendment is to update Statement of Work Addendum #1.

email proposals to michael.kitchell.1@us.af.mil and 127WG.MSC.ConstructionOrg@us.af.mil REVIEW SECTION 00110 SUBMISSION REQUIREMENTS AND INSTRUCTIONS 1. PROPOSAL PREPARATION INSTRUCTIONS

1. CONTRACT ID CODE PAGE OF PAGES

J 1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Sep-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S8422R0003

X 9B. DATED (SEE ITEM 11)

12-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Sep-2022

CODE

USPFO MI 110 MISSION SUPPORT CONTRACTING

50 SABER ST

BATTLE CREEK MI 49015-5515

W50S84 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S8422R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 06-Sep-2022 12:00 PM to 08-Sep-2022 03:00 PM.

The following have been added by full text:

ADDENDUM#1 SOW

BASE CIVIL ENGINEER

MICHIGAN AIR NATIONAL GUARD

BATTLE CREEK ANG BASE, MICHIGAN 49037-5567

STATEMENT OF WORK

MBMV222327 REPAIR EAST ENTRANCE GUARD SHACKS

1 September 2022

1.1 Project Description:

A. Background:

1. Main Gate Entrance Guard Shack. This Guard Shack sits at the Main Gate. It provides space for up to two guards. There is a working bathroom. There is additional space for a microwave and small refrigerator. Along the north wall is bullet and blast proof windows. Just below the windows is a working counter.

Above the windows is a shelf for additional storage. On the west and east walls is a manual door to allow the guard to monitor and interface with both inbound and outbound traffic. There is also blast and bullet proof windows flanking the doors.

On the south side of the shack is a mechanical room and is inaccessible from the interior. In between the mechanical room and guard room is the restroom and additional storage space.

a. Interior Condition: The interior countertop has deteriorated. Large chunks of countertop are missing. Shelving is missing from countertop attach file cabinet.

Existing finishes on floor, walls, and ceilings have deteriorated.

b. Exterior Condition: Exterior condition is in reasonable shape. However it shows wear.

2. Contractors Gate Entrance Guard Shack. This Guard Shack sits at the Contractors Gate. This gate has space for one guard. It contains a countertop and has limited space for storage. There is no restroom. There are bullet and blast proof windows on all four sides.

a. Interior Condition: This guard shack has severely worn. Existing countertop is broken. Weather penetrates to the interior.

b. Exterior Condition: The exterior brick is in reasonable shape. However, it is showing sign of wear.

B. Purpose: Repair and replace existing guard shacks to good condition with established utilities which meet the current occupancy and use of the installation.

C. Objective: Repair Main Gate Guard Shack. Replace Contractor Gate Guard Shack.

D. The performance period for this contract shall be 180 calendar days from contract award to substantial completion. The Contractor shall commence all non-physical construction requirements of this contract; to include submittal of bonds and/or insurance documents, background investigation documents (as applicable), and material submittals within 10 calendar days after contract award. Notice to Proceed will be issued by the Contracting Officer upon acceptance of all required documents, submittals and receipt of Security clearances. Physical work shall only be allowed after the issuance of Notice to Proceed.

E. Final completion shall occur no later than 30 days after substantial completion. Final completion includes, all site cleanup activities, punch list items, and closeout documents (see 1.7 Submittals).

1.2 Work Specifications:

A. Contractor shall provide all labor, materials, tools and equipment necessary to:

1. DEMOLITION

a. Contractor Gate:

1. Demolish and remove existing countertop and shelving in the interior of the Contractor Gate Guard Shack.

2. Demolish and remove existing ballistics-resistant glazing.

3. Demolish existing flooring and ceiling.

4. Prep all areas for installation of new finishes, millwork, and glazing.

b. Main Gate:

1. Demolish and remove existing countertop and shelving in the interior of the Main Gate Guard Shack.

2. Demolish and remove existing ballistics-resistant glazing.

3. Demolish existing flooring and ceiling in Guard Area and existing Rest

Room.

4. Prep all areas for installation of new finishes and millwork.

2. MASONRY

1. Main Gate / Contractor Gate: Clean/Repair existing masonry and repoint.

3. FINISHES

a. Main Gate / Contractor Gate:

1. Paint walls

2. Install ceiling

3. Install flooring

4. Install new ballistics-resistance (Level 5) glazing / Mirror Tint Finish

4. HVAC

a. Main Gate / Contractor Gate: Install new A/C equipment Ductless mini-split providing heating/cooling.

5. CASEWORK

a. Main Gate:

1. Install new countertop and under countertop cabinets.

2. Install new shelving above countertop.

3. Repair/repaint existing exterior doors and frame to remove rust

b. Contractor Gate:

1. Install new countertop.

6. ELECTRICAL

a. Main Gate / Contractors Gate:

1. Install exterior electrical IR light heater above Entrance Lane Guard

Shacks door

2. Replace existing interior/exterior lighting with LED Fixtures

1.3 General Requirements

A. Utilities

1. Existing utilities are to remain in service throughout the performance of the scope of work (e.g., data/communications cabling, power, lighting, etc.). Identify and protect against damage during work.

2. Verify location of utilities and existing conditions. Soil disturbance activities must not commence until utility clearance and marking activities are completed.

Contractor will initiate a MISS DIG (State of Michigan 3rd Party Utility Locate Service) and an AF Form 103 Work Clearance is on site.

3. Power will not be made available for the Contractors use by the Government.

Power shall be provided by the Contractor’s own resources if needed, unless approved by Contracting Officer Representative (COR).

4. Utility outages – Coordinate with the COR or his Inspection Representative.

Utility outages are to be outside of the BCANG Base business hours unless approved by the COR. 7 day notice is required.

B. Surface preparation and painting

1. Volatile materials, including soiled rags, soiled brushes, etc., shall be stored in airtight containers or removed from the job site at the end of the day.

2. Take all precautions necessary to prevent fire or explosion.

3. Painting shall be performed by a licensed painting contractor.

C. Contractor coordination

1. Provide notice to the COR/Inspection Representative five days prior to starting work on the job site.

2. Contractor shall provide any and all equipment necessary for working at heights above six (6) feet. This work pertains to selective demolition, lead paint removal, surface preparation and painting.

3. Advanced approval is required by the COR for location of all material lay-down, dumpster, debris, temporary facilities, and equipment locations.

4. Contact the COR/Inspection Representative immediately upon entrance to the work site. Contractor is to again provide notification the day he moves back to the work site after an interruption of work for two or more days in duration.

D. Contractor shall obtain all required approvals, permits and licenses from the State of Michigan and shall submit copies of all required notifications, forms, and project reports.

E. Site Safety Plan

1. The Contractor shall prepare and submit to the COR for approval, an Accident

Prevention and Site Safety Plan within 10 calendar days following award. The Site Safety Plan is a living document and shall be updated to address emergent, current or national conditions. The Plan shall define how the contractor will protect the general public, their employees and the environment, to include, but not limited to:

a. Responsibilities and Lines of Authority

b. Prime Subcontractors and their participation in the Plan

c. Activity Hazard Analysis (AHA)

d. Accident Prevention Plan

F. Contractor shall fill out an Initial DD Form 1354 before construction starts, an Interim DD Form 1354 midway through the construction period, and a Final DD Form 1354 14 days before Beneficial Occupancy date. The Final DD Form 1354 must include actual cost of each line item. For assistance contact COR or call BCANG Real Property Officer, ph

(269) 969-3376. Turn over the Final DD Form 1354 to the COR.

G. Client Equipment, Furniture, and Fixtures

1. Contractor shall relocate any and all client owned equipment, fixtures, or furniture that is within their designated area of work prior to the onset from installation.

2. Following completion of installation, testing, and commissioning the contractor shall replace/reset all client owned equipment, fixtures, or furniture to existing conditions.

H. Archeological Monitoring

1. Although archaeological artifacts and features are not anticipated, if during the disturbance process, artifacts, archaeological features and or bone/bone fragments are discovered, the contractor shall suspend excavation immediately and contact the COR.

I. Phasing and Temporary Services

1. Building operations shall remain fully operational during the performance of the work required under this contract and contractor shall minimize impact to area immediately surrounding work site.

a. Contractor shall provide phasing, continuity of service, and switch over plans and schedules, if any, for approval by COR.

b. If any systems are not fully serviceable/functional, contractor shall provide all backup services for base personnel until permanent services are restored. Provide plan for approval.

c. Government personnel will occupy the premises during entire period of contract.

Thus the Contractor shall coordinate their activities with the Building Manager and COR on a daily basis during onsite operations to minimize conflicts and disruption of Government's operations.

2. Temporary Toilet Facilities

a. Contractor shall provide portable toilet unit(s) for use by contractor employees during the duration of this project. If toilet facilities are not available in the building for government employees and the public, contractor shall provide temporary toilet facilities for their use.

1. Contractor shall maintain portable toilet units in a clean and sanitary condition at all times.

2. Provide temporary barricades and other protection required to prevent injury to occupants, personnel and any damage to the building or adjacent surfaces.

3. Traffic Control: Provide temporary traffic control required to support the work of the contract in accordance with Part 6 of the Michigan Manual of Uniform Traffic Control Devices (MMUTCD). A traffic control plan shall be submitted to the Contracting Officer for approval prior to commencing work.

J. Contractor shall provide dust control measures during renovation and repainting activities.

Provide plan for approval.

K. Clean-up:

1. The contractor shall install protective measures to protect existing conditions and to contain dust and debris during construction to ensure a safe and irritant free work environment for building occupants.

a. Work shall provide for protection of all finishes and furnishings, and shall include cleanup of work site during and after work performed. Work shall include removal of all unused material, refuse and debris from the work area.

1. Dispose of all construction debris according to Federal, State and Local requirements. Provide bill of lading/tickets/invoices etc. to the contracting officer as submittal (using AF Form 3000) indicating equipment recycling location and disposal weights.

2. Work areas shall be free of debris and cleaned to a dust free environment prior to the end of the contractor’s work day.

2. If equipment or building surfaces are damaged, contractor shall repair to original specification.

a. Material used for touchup and repairs shall blend with the color and texture of surrounding surface and be applied in accordance with the manufacture's recommendations.

3. Following the completion of work, the contractor shall cleanup site and adjacent areas affected by their work.

1.4 Asbestos Requirements

A. It is assumed based on the location and scope of work herein that there will be no encounter of asbestos containing materials or similar environmental health hazards.

1.5 Historical Requirements

A. It is assumed work site does not include historical facilities.

B. All work performed shall be in accordance with the Secretary of Interior’s Standards for the Treatment of Historic Properties. Link: https://www.nps.gov/tps/standards.htm. The facility is listed on the National Register of Historic Places and care shall be taken to prevent damage to all finishes.

1.6 Submittals

A. Material submittals shall be provided to the Government using AF Form 3000 no later than (NLT) 15 calendar days after award of contract. Clearly mark material submittals to identify which products and options are applicable to this contract (this is especially important with product data in which multiple items and/or optional items are provided for on the same sheet). The rejection of a submittal by the COR (Contracting Officer’s Representative) is not sufficient reason to extend the contract performance period. Upon COR acceptance of submittals, the Contracting Officer (CO) will issue notice to proceed (NTP) to the Contractor. The actual Construction Period available to the Contractor will vary depending on the amount of time taken to complete the bonds, background investigations, and material submittal process. Allow 10 (ten) calendar days for review and approval of all submittals. Contractor shall provide submittals and receive approval prior to ordering materials.

1. INITIAL SUBMITTALS

a. Submit the following items no later than the Preconstruction Meeting.

1. AF 3064 (or equivalent) – Project Schedule

2. AF 3065 – Schedule of Values

b. Submit the following items at least seven working days prior to onsite work.

1. Safety Plan

2. Quality Control Plan

c. The Government shall have up to five working days to review submittals.

2. PRODUCT SUBMITTALS

a. Submit product data for all materials using AF Form 3000 detailed on the AF Form 66.

b. Submit shop drawings as indicated.

c. The Government shall have up to five working days to review submittals.

3. HAZARDOUS MATERIALS

a. IAW FAR Clause 52.223-3, each offeror must provide the Contracting Office with a list of proposed HAZMAT that it plans to use on the installation during the performance of the contract. IAW AFFARS Clause 5352.223-9003, contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to the HAZMART. HAZMAT Reporting:

IAW FAR Clause 52.223-3, the contractor must provide the Contracting Office with a list of proposed HAZMAT that it plans to use on the installation during the performance of the contract. IAW AFFARS Clause 5352.223-9003, contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to the COR. Use AF Form 3952, Chemical Hazardous Material Request Authorization Form and submit to COR as a submittal using AF 3000 form.

b. Submit two copies of the manufacturer’s Material Safety Data Sheets (MSDS) for all hazardous materials used during the course of the project along with the following additional information:

1. Number of components in material if it is a kit

2. Container type

3. Unit of packaging (oz, gal, lb, qt, ea, etc.)

4. Package (can, drum, bottle, cylinder, etc.)

1.7 Antiterrorism / Operations Security / Information Protection Requirement:

A. Battle Creek Air National Guard Base is a closed base, pursuant to Section 21, Internal Security Act of 1950, 50 U.S.C. 797 and, as such, only those persons granted permission may enter. It is, therefore, required that control be exercised over Contractor personnel while working on the Base. To maintain this control, a list of all Contractor personnel (prime and all tiers of subcontractors) who will be working under the contract, must be submitted to the Contracting Officer a minimum of 5 working days prior to the start of work. The preferred method of providing this list is via email, to the Contracting Officer.

The list shall include, but is not limited to, contract number, project number, project title, company names, employee names, and the estimated start and end date of each person’s employment on the Project. Subsequent lists updating all personnel additions and/or deletions will be submitted as indicated above as employees are hired or released.

B. The General Contractor shall e-mail a completed Base Access Request form and a copy of the person’s Driver’s License to for each person who will be working on base (including Subs) to the COR or construction inspector. E-mail the forms one week prior to commencement of work (three weeks prior for workers with an out of state Driver’s License). Workers cleared for entry onto the base need to enter the Contractor’s Gate and tell the guard they have been cleared by Security Forces. The guard will send them to Security Forces where they will be issued a contractor’s badge. The government reserves the right to refuse to issue a pass to an employee of the contractor for any reason deemed valid by the government. Driver’s License, vehicle registration, and proof of insurance are required for entry onto Battle Creek ANG Base. All contractors and their vehicles will be searched each time they enter the base. Weapons, ammunition, and controlled substances are not allowed on base.

C. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

D. For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

E. AT Level I Training. This standard language is for contractor employees with an area of performance within a Government controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Government Installations, Facilities and Controlled Access areas shall complete AT Level I awareness training within 10 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Certificates of completion for each affected contractor employee and subcontractor employee will be maintained by the COR or Antiterrorism Representative. AT level I Awareness Training is available at the following website: http://jko.jten.mil

1.8 Specification Compliance Requirements:

A. Code and Design Standards:

1. The Contractor shall secure all needed permits, certifications and for ensuring compliance with federal, state, and local codes and design standards, latest editions, including, but not limited to the following as applicable:

a. International Building Code (IBC, International Code Council)

b. Occupational Safety and Health Administration (OSHA) Code of Federal

Regulations Part 1910 and Part 1926.

c. Facility Standards for the Public Building Service, PBS/P-100

(2018): https://www.wbdg.org/ffc/gsa/criteria/pbs-p100

d. City of Battle Creek; municipal code, Public ways and property.

e. Fire Protection Association Standards

f. ABA (Architectural Barriers Act) Standards. https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-the-aba-standards/aba-standards

g. Michigan State Department of Labor and Industry asbestos requirements:

http://www.lni.wa.gov/wisha/rules/asbestos/Default.htm

h. EPA 40 CFR 745 and Michigan State Dept. of Commerce WAC 365-230 11.10

i. Michigan State Lead in Construction Standard (WAC 296-155-176)

(app.leg.wa.gov)

j. OSHA safety regulations: https://www.osha.gov/law-regs.html

k. Secretary of Interior’s Standards for the Treatment of Historic Properties.

https://www.nps.gov/tps/standards.htm.

l. FAR 52.225-9 Buy American—Construction Materials.

https://www.govinfo.gov/content/pkg/CFR-2014-title48-vol2/pdf/CFR-2014-title48-vol2-sec52-225-9.pdf

1.9 Material Compliance Requirements:

A. Contractor shall reduce the quantity of indoor air contaminants that are odorous, irritating, and or harmful to the comfort and well-being of installers and occupants.

1. All adhesives and sealants used in interior of building used under this contract shall comply with South Coast Air Quality Management District (SCAQMD) Rule #1168 and Green Seal (GS) Standard for Commercial Adhesives GS-36.

2. Adhesives, sealants and solvents shall be no to very low VOC and environmentally preferred.

3. Key Sustainable Products (KSP): The use of KSP standards is mandatory and contractor shall provide documentation to the Contracting Officer for compliance for the products listed below as applicable to this scope of work. If the product is not listed below, the contractor shall use standards listed in the Green Procurement Compilation as appropriate. Refer to:

https://sftool.gov/greenprocurement

B. No asbestos containing materials shall be installed in the performance of this work.

C. Install materials in exact accordance with manufacturer’s instructions and approved submittals.

D. Install materials in proper relation with adjacent construction and with proper appearance.

Restore units damaged during installation.

E. Replace units which cannot be restored at no additional expense to the Owner.

1.10 Recycling Requirements

A. Maximum recycling of all construction & demolition debris required.

1. Divert demolition recyclable / reusable items and materials from landfills and incineration facilities to appropriate reusable material sites. Provide recycling plan and final documentation of compliance to COR.

1.11 Additional Project Requirements:

A. Contractor use of premises:

1. Contractor shall supply their own dumpster. No waste shall be put in building dumpsters or containers.

2. On-site storage is not available except in area of work. Any additional storage space shall be requested to the COR.

3. All persons working for or under a General Contractor or Sub-Contractor shall maintain safely marked areas of work.

4. The building tenants shall have no functional disruptions resulting from the contractor’s planning and execution of project work.

5. Deliveries of products by vendors shall be coordinated with the COR at least 24 hours in advance.

6. On-site parking is available only in designated locations.

B. Existing Documentation: BCANGB has a limited amount of documentation on existing construction and remodeling work at this facility.

1. This documentation is available to the Contractor in its original format for their use on this project. BCANGB assumes no liability for any of the documentation provided to the Contractor on this project; the Contractor assumes all liability and risk in using and relying on this information in the preparation of the Requests for

Proposals (RFP), development of the construction design and execution of the construction work.

2. All available record drawings will be provided upon request to the Contractor.

They should not however, be considered “as-built”. These drawing files are provided without warranty or obligation as to the accuracy or information contained in the files.

3. The Contractor and subcontractor(s) shall field verify furnished drawings to insure designs are accurate. It is the Contractor’s responsibility to determine existing conditions and to base the design on this information.

4. All information in the files shall be independently verified by the user. Any user shall agree to indemnify and hold the Government harmless from all claims, damages, losses, and expenses, including, but not limited to, attorney fees arising out of the use of the electronic drawing files.

1.12 Work Hours:

A. All work at the Battle Creek Air National Guard Base shall be accomplished during normal working hours (0745 to 1630 hours) exclusive of Saturdays, Sundays, and federal holidays unless other times are approved by the Contracting Officer, or otherwise stated in the Contract. Coordinate the work schedule with the Contracting Officer. Approval for other hours must be requested from the Contracting Officer at least 72 business hours in advance.

B. The following Federal legal Holidays are observed by this Base:

New Year's Day 1 January Martin Luther's King's Birthday Third Monday of January President's Day Third Monday of February Memorial Day Last Monday of May Independence Day 4 July Labor Day First Monday in September Columbus Day Second Monday in October Veteran's Day 11 November Thanksgiving Day Fourth Thursday in November Christmas Day 25 December

NOTE: Any of the above holidays falling on a Saturday will be observed the preceding Friday, holidays falling on a Sunday will be observed on the following Monday.

C. Prior to commencing work on the job initially, resumption of work after prolonged interruption (7 calendar days or more) commencement of any warranty work, and upon completion of warranty work, the Contractor must notify the Contracting Officer (or his/her Contracting Officer Representative). When relocating to new sites, returning to sites for follow-up work on a phased work plan, notification to the Contracting Officer’s Representative is sufficient. Notification should be by personal contact; however, advance notification may be by telephone, or in writing, and should be accomplished sufficiently in advance to allow scheduling of inspection forces. The above precautions are to ensure construction inspection and recording of work proceedings.

1.13 Attachments:

Attachment 2 Michigan National Guard Construction Division 01 Specifications

Attachment 3 AF Form 66 - MBMV222327 Attachment 4 Drawing B6927 Attachment 5 Drawing B6915

(End of Summary of Changes)