SOLICITATION W50S84‐22‐B‐0013 MBMV222330, Install Destrat Fans

‐ Include Building 6916 in scope of work (6 Fans), drawing included in set below.

‐ EMCS on Battle Creek ANG is TRANE, differential thermostatic controls will be tied into existing BCU in facility

‐ Total Count for provided fixtures is 50

This contract is subject to FAR 52.219‐14, Limitations on Subcontracting. Can you please confirm if this is a Construction, Construction by Specialty Trade, or Services) contract?

Reference : 52.219‐14(4)

NAICS 238210, (4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded. (f) The Contractor shall comply with the limitations on subcontracting.

Will the government accept modification requests if the cost of materials increases from the date the proposal was submitted to the date the contract is awarded and approved to commence?

No, clause included in this solicitation. Firm Fixed Price

3 Will the contractor be granted time extensions in the event of weather delays?

Time of performance extensions due to weather must be substantiated by the contractor and showing that the weather was “unusually severe” is not adequate justification. The Contractor is not entitled to a time extension just because it rained or snowed. Additionally, this is interior work.

Will the government provide bathroom facilities during contract or will the contractor be responsible for these facilities?

Contractor will be entitled to use on facility bathrooms based on location of work

5 Are there any specific permits that need to be pulled?

No

6 Will liquidated damages be included in this contract?

No, clause not included in this solicitation.

7 Will any independent tests be required on this contract?

No

Where on site should we expect to store equipment and materials. Do we need to provide any kind of storage containers on site?

A general Laydown site / indoors will be provided

9 Can we receive drawings for this project? At site visit, this was approved to be released.

PDFs provided. .dwg files can be downloaded https://safe.apps.mil/pickup.php?claimID=KmjoaThRdX949ZsH&recipCode=VbR5hS