RFIs W50S8421B0001 W50S8421B0002 and W50S8421B0003.pdf

PDF 51 KB Posted

Attached to
MBMV212807 – Repair Warehouse Floor – BLDG 6903
Solicitation number
W50S8421B0002
Issued by

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs W50S8421B0001, W50S8421B0002 and W50S8421B0003

Q1 What width is required for the actual trench drain? 4" is standard.

Response: This question speaks to means and methods

Q2. Can the proposal for this project be submitted via email to include the bid bond? Or are bids only be accepted via mail in only?

A2. Bids and Bid bonds are either accepted in person or via email

Q3. Is there an estimated linear footage amount or a line layout plan of the existing striping that can be provided? Also, what is width of the lines going back that is required?

A3: No such plan exists. Base no longer has an active flight mission so it’s unknown at this time if striping will need to be re-applied. Base has on-base painter is striping is required at a future date.

Q4: Can all the work area(s) be completed at one time or will phasing be required? If phasing is required, please provide a preliminary phasing plan to include how much square footage can be done at once and how many separate phases is required as this will greatly affect the work times and dates.

A4: Contractors responsibility to provide phasing plan. We cannot speak to means and methods. We can have conversations about contractor’s ideas and/or plans and coordinate with current staffing requirements for each of the buildings.

Q5. Will weekend work or after-hours work be allowed?

A5: Please refer to specifications

Q6.Will there be an area to place a dumpster?

A6. Yes

Q7. Are any of the areas in a restricted access area?

A7: No.

Q8. Are there any pictures of the existing work area that can be provided?

A8. No

Q9.Will the Contractor be responsible for moving and furniture or equipment?

A9: No

Q10. Do these spaces have central heating or air conditioning?

A10: Heating will be provided.

Q10: Where is the existing storm sewer locations in relation to where the new trench drain is going and tying into?

A10: See attached drawing: entitled Storm Sewer 6901(This answer applies only to W50S8421B0003)

Q11. We would like to know if you can provide a drawings that shows Scale or Dimensions of Building. The one provided does not show dimensions or Scale A11: Please see attached drawings that are for informational purposes only.

File details come from the government source that posted it. Updated .